Crawley Road Culvert Replacement


The purpose of the proposed stormwater improvement project is to alleviate flooding on a section of Crawley Road in the Odessa area. The project will construct a new stormwater detention area on County-owned property located at the northeast corner of Crawley and Hanlon roads. The project will also regrade the existing roadside ditches and replace the culvert crossings under a section of Crawley Road.

What to expect

  • Construction will take place on weekdays between 8 AM to 5 PM
  • The work will involve heavy equipment and excavation, and will generate normal construction noise
  • Access to homes will be maintained throughout construction.
  • In some areas, traffic lane closures may be necessary
    • For the safety of the workers, pedestrians and other motorists, please observe all traffic control measures
  • Most construction will be in the right of way; however, at times it may be necessary to work on private property with prior approval
    • All areas affected by the construction will be restored
  • Excavation work can sometimes cause an accidental water pipeline break or similar problem
    • Should any water service interruption occur, instructions for a precautionary boil water notice will be issued and service will be restored as quickly as possible

Cost & funding

The project cost is $680,000. This project is being funded through the Stormwater Fee Capital Improvement Program.


  • March 28, 2018 - open house informational meeting
  • May 2018 – project expected to begin construction and should be completed within six months