For alternatives A & B the existing signal will be upgraded to a Mast Arm signal with pedestrian features. In addition, additional right of way will be required from commercial property owners adjacent to Humphrey Street for a designated pond site.
The PD&E Study Phase is expected to be completed by spring 2011. The design phase will be complete in the summer of 2011. Construction is anticipated to begin summer 2012, and would take approximately nine months. The County’s budget for this project is approximately $9.3 million dollars.