Environmental Protection Commision
of Hillsborough County, Florida and Hillsborough County, Florida,
Petitioners,
v.
TAMPA BAY WATER, a Regional Water
Supply Authority,
Respondent.
________________________________________________/
Arbitration Award for Proposed Tampa Bay
Regional Reservoir
Pursuant to Sections 3.13 and 3.16 of the "Amended and Restated
Interlocal Agreement Reorganizing the West Coast Regional Water Supply
Authority," dated June 10, 1998, this is the arbitration award, including
findings of fact and conclusions of law, in the above-captioned proceeding.
Finding of Fact
Background of Parties to Arbitration Proceeding
1. Tampa Bay Water ("TBW") is a regional water
supply authority created pursuant to Sections 373.1962, 373.1963
and 163.01, Florida Statutes (2000). TBW was originally created as
the West Coast Regional Water Supply Authority in 1974 by an interlocal
agreement among Hillsborough County, Pasco County, Pinellas County,
the City of Tampa and the City of St. Petersburg. The City of New
Port Richey was later added as a member of the West Coast Regional
Water Supply Authority. Joint Pre-Hearing Stipulation filed March
16, 2001 ("Joint Pre-Hearing Stipulation"), p.13.
2. The West Coast Regional Water Supply Authority
was reorganized and restructured pursuant to the "Amended and Restated
Interlocal Agreement Reorganizing the West Coast Regional Water
Supply Authority" ("1998 Interlocal Agreement"), dated June 10,
1998. The reorganization of the West Coast Regional Water Supply
Authority was expressly authorized by Section 373.1963, Florida
Statutes, and was approved by Final Order of the Florida Department
of Environmental Protection (FDEP) dated June24, 1998, in OGC Case
No. 98-1921. The parties to the 1998 Interlocal Agreement are Hillsborough
County, Pasco County, Pinellas County, the City of Tampa, the City
of St. Petersburg, and the City of New Port Richey. The Board of
TBW is comprised of elected officials from each of the six member
governments. Joint Pre-Hearing Stipulation, p. 13.
3. By Joint Resolution No. 98-05, the West Coast Regional Water Supply
Authority was renamed "Tampa Bay Water, A Regional Water Supply Authority." Joint
Pre-Hearing Stipulation, p. 13.
4. Hillsborough County is a governmental entity
and a political subdivision of the State of Florida and a member
government of TBW.
5. The Environmental Protection Commission of
Hillsborough County ("EPCHC") is a governmental agency statutorily
created by a special act of the Legislature.
Need for Tampa Bay Regional Reservoir
6. TBW is the exclusive wholesale water supplier
responsible for meeting the potable water needs of its six member
governments. The member governments collectively serve approximately
2 million customers. Joint Pre-Hearing Stipulation, p. 14.
7. Under the 1998 Interlocal Agreement, TBW has
the unequivocal obligation to meet the potable water needs of its
six member governments on a regional basis. The Master Water Supply
Contract between TBW and the six member governments outlines how
TBWs facilities will be connected to the member governments'
facilities and sets forth provisions for billing and collecting
for the sale of water by TBW to the member governments. Joint Pre-Hearing
Stipulation, p. 14.
8. TBWs existing water supply facilities
consist of a series of wellfields located throughout Hillsborough,
Pinellas and Pasco Counties. These are: the Cypress Creek Wellfield;
the Cross Bar Ranch Wellfield; the Cypress Bridge Wellfield; the
Northwest Hillsborough Wellfield; the Starkey Wellfield, the North
Pasco Wellfield; the South-Central Hillsborough Wellfield; the
Cosme-Odessa Wellfield; the Section 21 Wellfield; the South Pasco
Wellfield; the Eldridge-Wilde Wellfield; and the Morris Bridge
Wellfield. With the exception of the South-Central Hillsborough,
Starkey and North Pasco Wellfields, these facilities are interconnected
and are part of an interconnected water production system. Joint
Pre-Hearing Stipulation, p. 14.
9. The 1998 Interlocal Agreement requires that
TBW maintain a supply capacity that is six percent greater than
actual demand, on an average annual basis. The failure of TBW to
maintain this six percent reserve capacity for a continuous six-month
period is defined under the 1998 Interlocal Agreement as "Production
Failure." The six percent reserve capacity is intended to create
a buffer between demand and permitted capacity. Joint Pre-Hearing
Stipulation, p. 14.
10. Should TBW fail to maintain the six percent
reserve capacity for a continuous six-month period, a "Production
Failure," the member governments are entitled under the 1998 Interlocal
Agreement to independently pursue their own water supplies. Joint
Pre-Hearing Stipulation, p. 14.
11. In April, 1998, TBW, its six member governments,
and the Southwest Florida Water Management District ("SWFWMD")
entered into an agreement entitled the "Northern Tampa Bay New
Water Supply and Ground Water Withdrawal Reduction Agreement," commonly
called the "Partnership Agreement." Joint Pre-Hearing Stipulation,
p. 14.
12. The Partnership Agreement has four principal
stated objectives: to develop at least 85 million gallons daily
("mgd") annual average of new water supply to meet the needs of
the area; to effect a reduction in groundwater pumping from the
11 existing wellfields to no more than 121 million gallons daily
annual average as of December
31, 2002 through December 31, 2007, and to no more than 90 mgd annual average
as of December 31, 2007 through December 31, 2010, to allow environmental recovery;
to end existing litigation between the parties to the Partnership Agreement
and avoid future litigation, including administrative proceedings; and to create
a funding mechanism through which TBW can develop new water supply projects.
Joint Pre-Hearing Stipulation, p. 15.
13. Pursuant to the Partnership Agreement, the
existing water use permits for the 11 wellfields specified therein
(Cosme-Odessa, Cross Bar Ranch, Cypress Bridge, Cypress Creek,
Eldridge-Wilde, Morris Bridge, Northwest Hillsborough Regional,
North Pasco, Section 21, Starkey, and South Pasco) were consolidated
into a single permit ("Consolidated Permit") under which TBW is
the sole permittee. The expiration date of the Consolidated Permit
is December 31, 2010. Joint Pre-Hearing Stipulation, p.15.
14. Prior to execution of the Partnership Agreement,
the existing permits for the 11 wellfields allowed for cumulative
withdrawals totaling approximately 192 mgd. Upon execution of the
Partnership Agreement, the Consolidated Permit immediately reduced
allowed withdrawals to 158 mgd. Joint Pre-Hearing Stipulation,
p. 15.
15. The Partnership Agreement requires that wellfield
pumping from the 11 wellfields be further reduced to no more than
121 mgd by December 31, 2002, and then to 90 mgd by December 31,
2007.
16. The Partnership Agreement also requires TBW
to develop at least 38 mgd of new water supply by December 31,
2002, and a total of 85 mgd of new water supply by December 31,
2007. Joint Pre-Hearing Stipulation, p. 15.
17. The Partnership Agreement requires TBW to
submit to the SWFWMD by July 1, 1998, a "New Water Plan" describing
the projects that TBW intends to implement to meet the requirements
of 38 mgd of new water supply by December 31, 2002, and 85 mgd
of new water supply by December 31, 2007. Joint Pre-Hearing Stipulation,
p. 15.
18. TBW and Hillsborough County have each individually
approved a "New Water Plan" that is intended to meet the requirements
of the 1998 Interlocal Agreement and the Partnership Agreement.
The Environmental Protection Commission of Hillsborough County
is not a member government and thus did not approve the New Water
Plan. Joint Pre-Hearing Stipulation, p. 16.
19. The planning and development of the New Water
Plan took into account demand calculations based on population
projections and per capita usage, the six percent reserve capacity
required under the 1998 Interlocal Agreement, and the wellfield
pumping reductions and new water supply requirements mandated by
the 1998 Interlocal Agreement and the Partnership Agreement. The
New Water Plan is designed to meet all of these requirements, including
the projected increased demand during the period between December
31, 2002 (the first phase of wellfield pumping reductions) and
December 31, 2007 (the second phase of wellfield pumping reductions).
Joint Pre-Hearing Stipulation, p. 16.
20. The New Water Plan includes the following
projects: the Brandon Urban Dispersed Wells ("BUDW") project; the
North and South Central Interties; a seawater desalination project;
and the Enhanced Surface Water System, which includes the Alafia
River Project, the Tampa Bypass Canal/Hillsborough River High Water
("TBC") project, the South Central Intertie, the Tampa Bay Regional
Surface Water Treatment Plant, and the proposed off-stream water
reservoir (described in more detail in subsequent sections of this
arbitration award and referred to as the "Proposed Reservoir")
that is at issue in this arbitration proceeding. Joint Pre-Hearing
Stipulation, p. 16.
21. The Proposed Reservoir will provide an additional
25 mgd of water supply to the region in average year conditions
and 40 mgd in drought conditions, without increasing any water
use permits. When withdrawals from other surface water sources
cannot occur because of drought or other conditions, the Proposed
Reservoir can provide up to 66 mgd of water supply.
22. The June 2000 New Water Plan states that the
Enhanced Surface Water System is eligible for a maximum of $120
million from SWFWMD, pursuant to its funding obligation under the
Partnership Agreement. Joint Pre-Hearing Stipulation, p. 16.
23. TBW does not furnish water to any person or
entity other than its six member governments and does not sell
any water on a retail basis. All potable water produced by TBWs
facilities is for resale on a wholesale basis to the member governments.
Joint Pre-Hearing Stipulation, p. 16.
24. The 1998 Interlocal Agreement empowers TBW
to produce and supply drinking water "in such manner as will give
priority to reducing adverse environmental effects of excessive
or improper withdrawals of water from concentrated areas." Joint
Pre-Hearing Stipulation, p. 17.
Background of This Arbitration Proceeding
25. The 1998 Interlocal Agreement requires the
member governments, like Hillsborough County, and TBW to enter
into binding arbitration if there is a dispute regarding "Primary
Environmental Permit Applications," as that term is defined in
the 1998 Interlocal Agreement, for TBW projects. The EPCHC is also
subject to the binding arbitration process set forth in the 1998
Interlocal Agreement for Primary Environmental Permit Applications.
Hillsborough County, by entering into the Interlocal Agreement,
and the EPCHC, by separate agreement with the Authority, waived
their right to challenge proposed agency action on Primary Environmental
Permit Applications pursuant to Chapter 120, Florida Statutes (2000).
26. On September 18, 2000, TBWs Board of
Directors approved the filing of a joint application for an Environmental
Resource Permit from the FDEP and a U. S. Army Corps of Engineers
Section 404 Dredge and Fill Permit (collectively "Joint Application")
for the Proposed Reservoir. The Proposed Reservoir is designed
to be an off-stream water reservoir more particularly described
subsequently in this arbitration award. The Joint Application is
a "Primary Environmental Permit Application" under the 1998 Interlocal
Agreement and is therefore subject to binding arbitration.
27. The approval by TBW of the Joint Application
triggered the timetable under the 1998 Interlocal Agreement for
appropriate parties to file for binding arbitration. On October
16, 2000, Hillsborough County and EPCHC (jointly referred to herein
as "Petitioners") notified TBW of their opposition to the Joint
Application and demanded binding arbitration in accordance with
the 1998 Interlocal Agreement.
28. The 1998 Interlocal Agreement delineates an
expedited and strict procedural process for the binding arbitration,
including a detailed discovery process and an expedited time line
for the completion of all arbitration proceedings. 1998 Interlocal
Agreement, Sections 3.13, 3.16 and Appendix N.
29. This Arbitration Panel was impaneled on November
17, 2000, in accordance with the 1998 Interlocal Agreement. Arbitrator
Daniel Fernandez was selected by TBW and arbitrator Daniel Thompson
was selected by Petitioners. Arbitrator and Chair of the arbitration
panel, Carlos Alvarez, was selected by Mr. Fernandez and Mr. Thompson
in accordance with the 1998 Interlocal Agreement. (The three arbitrators
are jointly referred to as the "Arbitration Panel.") On December8,
2000, each member of the Arbitration Panel took an oath, pursuant
to Section 3.16 of the 1998 Interlocal Agreement, to conduct all
of his duties and responsibilities for the totality of the arbitration
proceedings with "impartiality and fidelity." 1998 Interlocal Agreement,
Section 3.16 (B). In compliance with paragraph 6 the Agreed Order
on Case Management dated December 12, 2000, there have been no
ex parte communications between the arbitrators and any of the
parties or their counsel
30. The Arbitration Panel issued a number of orders
throughout the arbitration process. Two of the orders, Order on
Motion to Determine Scope of Arbitration and Related Motion to
Strike dated December22, 2000 ("Arbitration Panel Order, December
22, 2000"), and Order on Respondents Motion for Order Determining
Applicable Agency Rules, Policies and Statutes dated February 28,
2001 ("Arbitration Panel Order, February 28, 2001"), are attached
as Attachments 1 and 2, respectively, to this arbitration award.
Because the substance of these orders defines the scope and nature
of the arbitration proceeding and ultimately the arbitration award,
these orders are part of this arbitration award.
31. Pursuant to Agreed Order on Case Management
Order dated December 12, 2000, and AppendixN of the 1998 Interlocal
Agreement, the parties proceeded through an expedited discovery
process that ended on March 1, 2001. On February 27, 2001, TBW
also submitted to the FDEP the Response to Request for Additional
Information ("RAI Response"), which provides additional information
about the Proposed Reservoir. The RAI Response was TBWs answer
to the Request for Additional Information ("RAI") submitted by
the FDEP in connection with its permitting review of the Joint
Application.
32. The final hearing on the arbitration award
began on March 16, 2001, and ended on April9, 2001. Within these
dates, the Arbitration Panel heard testimony and argument on 13
days. The hearing was held in Hillsborough County with the consent
of all the parties.
33. On April 4, 2001, the Arbitration Panel visited
the site of the Proposed Reservoir and surrounding areas, accompanied
by counsel and consultants for all parties.
34. All parties were represented by counsel. Appearing
on behalf of TBW were:
Donald D. Conn, General Counsel
Tampa Bay Water
2535 Landmark Drive, Suite 211
Clearwater, FL 33761-3930
E. A. "Seth" Mills, Jr., Esquire
Robert L. Olsen, Esquire
Fowler, White, Gillen, Boggs, Villareal and Banker, P.A.
P.O. Box 1438
Tampa, FL 33601-1438
Appearing on behalf of Petitioners were:
Roger W. Sims, Esquire
Rory C. Ryan, Esquire
Jeffrey T. Donner, Esquire
Holland & Knight LLP
200 S. Orange Avenue, Suite 2600
P.O. Box 1526
Orlando, FL 32802
Frederick T. Reeves, Esquire
Hobby Grey & Reeves
5709 Tidalwave Drive
New Port Richey, FL 34652-3281
Patrick B. Courtney, Esquire
Lansky & Courtney
512 E. Kennedy Blvd.
Tampa, FL 33602
Edward B. Helvenston, Esquire
Rick Muratti, Esquire
Assistant County Attorneys
Office of the Hillsborough County Attorney
P.O. Box 1110
Tampa, FL 33601
Kristin K. Bennett, Esquire
Hillsborough County Environmental Protection Commission
1900 Ninth Avenue East
Tampa, FL 33605
35. TBW presented the following witnesses:
(a) Jerry Maxwell. Mr. Maxwell was a fact witness.
(b) Ed Copeland. Mr. Copeland was qualified as an expert witness in civil engineering,
the management and direction of projects like the Proposed Reservoir, and environmental
resource permit application projects in general.
(c) Dr. Anwar Wisa. Dr. Wisa was qualified as an expert in the area of geotechnical
engineering, specifically with an emphasis in embankment stability of earthen
dams.
(d) Richard Donovan. Mr. Donovan was qualified as an expert in the areas of
civil and geotechnical engineering as they relate specifically to dam embankment
design and stability analyses.
(e) Dr. Sam Upchurch. Dr. Upchurch was qualified as an expert in the areas
of Florida geology, karst, hydrogeology, and water quality analysis.
(f) George Eliason. Mr. Eliason was qualified as an expert in environmental
sciences, delineation of wetland impacts, characterization of wetland systems,
and analysis of wetland functions and value, including hydroperiods.
(g) Helen Bennett. Ms. Bennett was a fact witness.
(h) George Feher. Mr. Feher was qualified as an expert in wetland planning,
including specifically the preparation of preliminary plans and follow-up detail
plans and construction plans, and related permitting processes.
(i) Dr. Mark Stewart. Dr. Stewart was qualified as expert in geology, including
geologic and hydrogeologic site evaluation, and specifically with regard to
sinkholes and karst features, and also as an expert in water resources management,
including integrated mathematical modeling of surface water and groundwater
systems.
(j) Mr. Barry Meyer. Mr. Meyer was qualified as an expert in civil engineering,
including the design of water-control systems and methods of control of groundwater
and surface water.
36. Petitioners presented the following witnesses:
(a) Mark Farrell. Mr. Farrell was a fact witness.
(b) Paula Harvey. Ms. Harvey was a fact witness.
(c) Larry Gispert. Mr. Gispert was qualified as an expert in emergency management
and, specifically, as an expert in emergency management in Hillsborough County.
(d) Jeremy Craft. Mr. Craft was qualified as an expert witness in ERP rule
interpretation, FDEP agency practice regarding the application of the ERP rules
to the reasonable assurance criteria, public interest criteria and the requirements
for meeting those criteria, and wetland impact assessment and mitigation.
(e) Peter Anderson. Mr. Anderson was qualified as an expert in groundwater
hydrology and modeling of groundwater systems.
(f) Thomas Simonetti. Mr. Simonetti was qualified as an expert in water quality
analysis, particularly in the use of chemicals or water treatment additives
and their potential environmental impacts.
(g) Dr. Norman Blake. Dr. Blake was qualified as an expert in pollution ecology
and the effect of copper on marine and freshwater systems.
(h) Ross McWilliams. Mr. McWilliams was qualified as an expert in biology;
wetlands assessments; wetlands mitigation and restoration, including design;
threatened and endangered species assessment; and state wetlands permitting.
(i) Dr. Michael Dennis. Dr. Dennis was qualified as expert in biology, ecology,
threatened and endangered species, and wetland permitting, including mitigation.
(j) Dr. Vincent Scovazzo. Dr. Scovazzo was qualified as a geotechnical expert
in the area of dam design, safety, construction, operation, permitting, and
stability.
(k) Daniel Mendelsohn. Mr. Mendelsohn was qualified as expert in the application
and development of unsteady flow models, including the DAMBRK and FLDWAV models,
and the representation of numerical model output in graphical form, including
computer-generated inundation animations.
(l) Dr. Daniel Fread. Dr. Fread was qualified as an expert in the development
and application of unsteady flow models, the development and application of
the DAMBRK and FLDWAV models, the development and application of the DWOPER
model, and the development and application of the BREACH model.
37. Some of the expert witnesses for TBW and Petitioners
were also fact witnesses. There was no rebuttal testimony offered.
The arbitration hearing terminated on April 9, 2001, after closing
arguments by the parties. The parties submitted their proposed
arbitration awards on April20, 2001, and the arbitration hearing
was deemed closed as of that date pursuant to Guideline 34 of the
American Arbitration Association Environmental Arbitration Guidelines.
38. The 1998 Interlocal Agreement requires that
the arbitration award in this matter be issued no later than 60
days after the beginning of the arbitration final hearing. Sixty
days after the beginning of the final arbitration hearing is May
15, 2001.
Background of the Proposed Reservoir
39. TBW selected the Proposed Reservoir site after
an extensive, multi-disciplinary alternative site analysis that included
the review and comparison from an environmental, land use, engineering
and economic basis of other potential sites in the Hillsborough County
and adjacent areas. Since the Proposed Reservoir purpose was to collect
surface waters from the Hillsborough River/Tampa Bypass Canal and
the Alafia River, potential sites needed to be reasonably close to
these sources in order to reduce pipeline costs and reduce land use
conflicts.
40. The Proposed Reservoir is located in southeastern Hillsborough
County, roughly to the west, northwest of Wendel Avenue and between two riverine
systems, Doe Branch to the east and northeast and Long Flat Creek to the west.
Undeveloped land owned by Hillsborough County is south of and adjacent to the
Proposed Reservoir site.
41. The area selected for the Proposed Reservoir
and the immediately surrounding area is mostly rural in character
and sparsely populated except for approximately 51 residences along
Wendel Avenue near to the Proposed Reservoir. The land for the
Proposed Reservoir is zoned agricultural-rural. This zoning classification
allows for the land to be used for a water reservoir so there is
no rezoning required. There is no zoning designation within Hillsborough
County that has a lower density classification than agricultural-rural.
42. The Proposed Reservoir footprint is designed
to be approximately 1,100 acres in size and is expected to hold
approximately 15 billion gallons of water, at an average water
depth of about 50 feet, when full. Five miles of earthen embankments
are designed to impound the water in the Proposed Reservoir.
43. The earthen embankment is designed to range
between 30 to 65 feet in height based on the existing land surface
elevations on the site, with the higher embankments being in the
northwest corner of the Proposed Reservoir and the lower embankments
being on the southeast corner, near Wendel Avenue. The Proposed
Reservoir is designed to be generally above ground with some portion
of the reservoir storage being provided below the existing land
surface as a result of the excavation of materials needed for the
embankment. The top elevation of the Proposed Reservoir is designed
at 145 (ft) NGVD.
44. A crest road is planned for the top of the
earthen embankment. The design also calls for a perimeter road
at the downstream toe of the embankment adjacent to the perimeter
swale, which is, in turn, adjacent to the earthen embankment.
45. The Proposed Reservoir is designed to be an
off-stream reservoir to store surface waters, and it needs facilities
to transport water to and from the area enclosed by the earthen
embankment. Accordingly, the Joint Application also includes construction
of approximately 8 miles of new 84" pipeline to connect to water
sources and to existing water supply facilities. The pipeline route
begins approximately 400 feet north of the intersection of Fishhawk
Drive, Bell Shoals Road and Boyette Road, and runs south and east
in a proposed easement following the alignment of Boyette Road,
then through rural land to the Proposed Reservoir. The pipeline
is planned to be used for obtaining water for the Proposed Reservoir
from the Hillsborough River, the Alafia River and the Tampa Bypass
Canal. The pipeline will also be used to deliver water to the Tampa
Bay Regional Surface Water Treatment Plant, located in Hillsborough
County north of the Proposed Reservoir, for treatment and ultimate
delivery to member governments.
46. The 84" pipeline is designed to be made from
steel or prestressed concrete pipe for the majority of its length.
The portion of the pipeline under the earthen embankment will be
steel. The 84" pipeline is designed to enter the Proposed Reservoir
in the northwest area of the Proposed Reservoir, will be buried
below the ground surface and the earthen embankment, and is designed
to connect to an intake tower inside the Proposed Reservoir. A
water control structure bridge of approximately 263 feet in length
is designed to be built from the crest road on top of the earthen
embankment to the intake tower. Also buried below ground level
at the same location as the 84" pipeline will be a 42" pipeline.
At the present time, the use of this 42" pipeline has not been
determined.
47. There are ten stormwater ponds associated
with the Proposed Reservoir that are planned to be located adjacent
to and outside of the earthen embankments. Two access roads, one
from the east and one from the west side of the Proposed Reservoir,
are planned as part of the project.
48. A one-story maintenance and office building,
approximately 28 feet by 48 feet, is scheduled to be built near
the intake tower. A separate mechanical building adjacent to this
building may be constructed if necessary to improve water quality
in the future.
49. In addition to the 1,100-acre footprint of
the Proposed Reservoir, the SWFWMD has agreed to acquire 4,700
acres surrounding the footprint to the east, west and north. This
additional acreage is planned to be used for mitigation for wetland
impacts and for other unspecified purposes. The SWFWMD plans to
acquire the necessary property for the Proposed Reservoir and mitigation
areas. TBW will be responsible for the construction, operation
and maintenance of the Proposed Reservoir. TBW plans to construct
the wetlands and other areas that may be necessary for mitigation
purposes and to be responsible for these areas until their vegetative
success has been established. SWFWMD or another similar agency
will then be responsible for the long-term management and maintenance
of the mitigation areas. Issues to be Determined by the Arbitration
Panel
50. As will be discussed more fully in the conclusions
of law section of this arbitration award, TBW has the burden of
proof in this arbitration proceeding" of providing reasonable assurances
that [TBWs] Primary Environmental Permit application meets
all applicable agency rules, policy and statutes." 1998 Interlocal
Agreement, Section 3.13(B). (The "applicable agency rules, policy
and statutes" are referred to in this arbitration award as the "Applicable
Substantive Law.") This is the ultimate issue of law in this arbitration
proceeding.
51. While there are many issues of fact that could
be determined pursuant to a determination of "reasonable assurance" for
a project like the Proposed Reservoir, the parties have narrowed
the issues to be determined by this arbitration through the pleading
and discovery process that preceded the final evidentiary hearing.
Petitioners Initial Statement of Issues dated December12,
2000; Joint Pre-Hearing Stipulation; Proposed Final and Binding
Arbitration Decision filed April 20, 2001 ("Petitioners Proposed
Arbitration Award"); Tampa Bay Waters Proposed Final Arbitration
Award filed April 20, 2001 ("TBWs Proposed Arbitration Award");
and all discovery pleadings. The 1998 Interlocal Agreement envisions
the narrowing of issues in this manner. 1998 Interlocal Agreement,
Appendix N, Rules 1(a)(6) and (7); Rules 1(b)(1), (3), and (5).
Indeed, the arbitration process under the 1998 Interlocal Agreement
requires that member governments raise "issues" to initiate the
arbitration process. 1998 Interlocal Agreement, Section 3.13(A).
52. Accordingly, the following generally stated
issues, as set forth by Petitioners in the Joint Pre-Hearing Stipulation,
remain for factual and legal consideration by the Arbitration Panel:
(1) Whether the Application provides reasonable assurance as to the potential
for adverse water quality impacts to the ground water and surface water in
the vicinity of the reservoir and unacceptable impacts to natural systems and
domestic uses.
(2) Whether the Application provides reasonable assurance as to
the potential for impacts to wetlands outside of the "footprint" of
the reservoir due to leakance from the reservoir and alteration to
the natural hydroperiods.
(3) Whether the plan for mitigation of impacts to wetlands is indefinite
and incomplete, does not consider potential adverse impacts to mitigation
projects from reservoir leakance, and fails to provide the necessary
reasonable assurance the wetlands impacts can be adequately offset.
(4) Whether the Application provides reasonable assurance that
the public health and safety has been adequately protected when the
Application does not:
a. include a dam break analysis, including inundation map, and
the emergency action plan is not complete;
b. address design alternatives to avoid or minimize risks to public
health and safety;
c. is based upon "average" site conditions rather than actual conditions;
d. include design or analysis for emergency or rapid drawdown conditions;
and
e. address impacts to adjacent residences, including potential
impacts to septic fields, domestic wells, and surface drainage.
Joint Pre-Hearing Stipulation, p. 17.
53. This arbitration award deals with these contested
factual issues and makes appropriate factual determinations to be
able to apply the Applicable Substantive Law to these factual issues.
All other facts in connection with the Proposed Reservoir that are
not necessary in the determination of the remaining factual and legal
issues are not subject to arbitration, and a "reasonable assurance" evaluation
has not been made as to whether those facts comply with the Applicable
Substantive Law.
Issue 1
Water Quality Compliance
Issue 1: Whether the Application provides reasonable assurance
as to the potential for adverse water quality impacts to the ground
water and surface water in the vicinity of the reservoir and unacceptable
impacts to natural systems and domestic uses.
54. There is general agreement between the parties
that the hydraulic head created by the water to be stored within
the Proposed Reservoir will cause a hydrologic mechanism known as "seepage" i.e.,
some of the water, identified as "leakance," will migrate through
the embankment and underlying soils, a process called "flux," into
the aquifers underlying and surrounding the Proposed Reservoir, as
well as the surrounding surface waters. Disagreement arises over
whether the leakance would cause adverse impacts that violate Applicable
Law, either as to water quality or water quantity. Petitioners first
issue concerns water quality impacts. Their second and third issues
address water quantity impacts.
55. The specific concerns raised here by Petitioners
relate to the likelihood that TBW will use algaecides or other
chemicals to protect TBWs use of the water being stored within
the Proposed Reservoir. TBW acknowledges the need to use water
quality control measures within the Proposed Reservoir, but states
that such measures are still being developed and will be calibrated
with actual reservoir water quality upon filling the Proposed Reservoir.
Therefore, the Joint Application contains no final determination
as to the type or quantity of chemicals that may be used.
56. The chemical of particular concern to Petitioners
is copper sulfate, which the Joint Application acknowledges may
be used in the Proposed Reservoir. Copper sulfate is a common chemical
compound that is applied in lakes, streams and reservoirs throughout
the United States for the purposes of killing algae in the water
column.
57. Because it is still considering how to undertake
these water quality measures, TBW presented no evidence as to application
rates, method of application, spill control, type of equipment
to be used for applications, or any other information regarding
the use of copper sulfate. The parties appear to agree, however,
that effective usage will require many tons of the chemical.
58. The Arbitration Panel concurs with expert
witnesses from both parties to the extent that they agree that
the copper in copper sulfate becomes bound in sediments at the
bottom of water bodies, particularly where the sediments and soils
contain organics, clays and silts. Such a process would be applicable
to the bottom of the Proposed Reservoir.
59. Where the experts disagree is over the fate
of the copper after it becomes bound. Petitioners assert that where
extremely large amounts of copper are used, some of it will go
back into solution at or near the bottom of the reservoir, where
it will be available for transport.
60. The FDEP has adopted surface water quality
standards for copper, which can be found in Rule 62-302.530, F.A.C.
Copper is a groundwater standard pursuant to Rule 62-520.420, F.A.C.,
which incorporates by reference Rule 62-550.320, Table 4, Secondary
Drinking Water Standards.
61. Copper in its soluble form is toxic to low-level
plant and animal life. If copper in soluble form were to reach
wetlands outside the Proposed Reservoir at certain low levels of
concentration, it can be toxic to the ecology and disrupt the entire
food chain.
62. The Wendel Avenue residents obtain their drinking
water from private wells. The potential for leakants containing
copper of moving from the Proposed Reservoir to groundwater underlying
those wells, therefore, should be monitored to confirm that the
leakants will not result in the residents having copper in their
drinking water that exceed the secondary standard level.
63. TBW has not conducted any analysis of fate
and transport of chemicals or contaminants out of the Proposed
Reservoir. Petitioners, however, presented no testimony that copper
could reasonably be expected to migrate from the Proposed Reservoir
or otherwise impact the surface waters or groundwater.
64. While Petitioners presented evidence that
copper may return to soluble form under certain circumstances,
Petitioners presented no evidence that, even assuming the soluble
copper could travel through the reservoir bottom, such transport
would reasonably be expected to cause a violation of water quality
standards for copper in surface water or groundwater outside of
the Proposed Reservoir, or even that the soluble copper would exceed
such standards within the Proposed Reservoir prior to such transport.
65. Witnesses for both parties discussed a monograph
entitled "Aquatic Use of Copper-Based Herbicides in Florida," (Fla.
Dept. of Natural Resources 1990). (Pet. Ex. 104) The monograph
expresses concerns that excessive use of copper sulfate could have
adverse downstream water quality impacts for copper, but did not
address closed reservoir situations such as the Proposed Reservoir,
did not discuss possible groundwater transport, and did not recommend
elimination of copper sulfate as an algaecide in drinking water
reservoirs.
66. Petitioners have not placed at issue in this
proceeding the need for TBW to comply with water quality standards
for copper within the Proposed Reservoir pool. While Petitioners
provided no persuasive proof that leakance from the Proposed Reservoir
would cause water quality violations outside the reservoir embankment,
the testimony indicates that water quality problems may occur at
some point if the usage of copper sulfate is completely unregulated.
This is illustrated by testimony of witnesses from both sides expressing
concern over potential adverse impacts associated with usage of
unspecified numbers of "dump trucks" of the algaecide.
67. TBW responds to concerns regarding uncontrolled
use of algaecides by pointing to AppendixK, Section 2.4 of the
Joint Application, which states, "The water quality control measure
utilized in the reservoir management will be permitted through
the Hillsborough County Health Department Source Water Permit." However,
there is no evidence as to the scope of such permit i.e.,
what specific "measure" would be permitted, what does the permit
regulate, does it address potential offsite water quality concerns,
or whatever. Therefore, the Arbitration Panel is unable to determine
the relevance of this permitting scheme to whether the Joint Application
complies with Applicable Substantive Law.
68. The evidence shows that copper sulfate is
reasonably likely to be bound up in soils within the footprint
of the Proposed Reservoir, and no persuasive evidence has been
presented to the Arbitration Panel that soluble copper may be transported
by leakance from the Proposed Reservoir to adjacent groundwater
or surface water in levels that violate applicable state water
quality standards.
69. Nonetheless, given the lack of information
with regard to how the application of copper sulfate will be regulated,
the Panel finds that it would be prudent for TBW to monitor the
groundwater adjacent to the embankment of the Proposed Reservoir
to determine whether the applications are causing an increase in
copper at levels that would appear to indicate that water quality
standards might be violated in the future.
70. Particular areas of concern for monitoring
are wetlands adjacent to the Proposed Reservoir and the Wendel
Avenue neighborhood. The wetland areas are appropriate because
of the potential impacts of water quality violations on the wetland
systems. The Wendel Avenue neighborhood monitoring is appropriate
because of the residents use of groundwater for drinking
water.
71. TBW has already acknowledged in the Joint
Application its commitment to monitor for water quality and water
levels at various locations around the site of the Proposed Reservoir,
including specifically the Wendel Avenue area. Monitoring wells
will be installed as part of TBWs monitoring and maintenance
plan for leakance, and will be designed to look at both water quality
and water levels. The Arbitration Panel finds that the water quality
monitoring plan should specifically include monitoring for copper.
Since TBW has already committed to implement monitoring in these
location, the Arbitration Panel does not consider it necessary
that the copper monitoring be included as a specific amendment
to the Joint Application.
72. Petitioners have not placed at issue the adequacy
of TBWs water quality monitoring plans for chemicals other
than copper, or for monitoring other potential pollution-causing
constituents in the waters of the Proposed Reservoir, whether added
by TBW or coming from elsewhere, such as from the source waters
for the Proposed Reservoir. Therefore, the Arbitration Panels
findings on copper is not intended as a determination of what should
be the scope of the water quality monitoring plan proposed by TBW
in its Joint Application, only what must be included in the plan
as a result of this arbitration award.
73. On page 43 of Petitioners Proposed Arbitration
Award, under the headings of "Wendel Avenue" and "Water Quality," Petitioners
state their proposals for what should be ordered by the Arbitration
Panel as the part of this arbitration award relating to the water
quality issues. These proposals include a detailed assessment of
the potential impacts of seepage on the Wendel Avenue residents,
avoidance and contingency plans for such impacts, preparation of
models that predict the fate and transport of herbicides and algaecides
that may be used within the Proposed Reservoir, and the implementation
of measures to prevent adverse impacts to water quality or fish
and wildlife.
74. Given the lack of evidence that water quality
exceedences are reasonably expected to occur from copper-containing
leakance outside of the Proposed Reservoir, the Arbitration Panel
rejects these recommendations as being unnecessary amendments to
the Joint Application.
Issues 2 and 3
Water Quantity Monitoring and Management
Issue 2: Whether the Application provides reasonable assurance
as to the potential for impacts to wetlands outside of the "footprint" of
the reservoir due to leakance from the reservoir and alteration
to the natural hydroperiods.
Issue 3: Whether the plan for mitigation of impacts to
wetlands is indefinite and incomplete, does not consider potential
adverse impacts to mitigation projects from reservoir leakance,
and fails to provide the necessary reasonable assurance the wetlands
impacts can be adequately offset.
75. Petitioners have asserted that adverse impacts
may occur to offsite wetlands and the property of others as the result
of changes in water quantity caused by construction and operation
of the Proposed Reservoir. Petitioners question whether TBWs
modeling of the potential extent of such impacts, as well as TBWs
proposals to monitor for and manage any impacts that may be adverse,
comply with Applicable Substantive Law. Since the two issues quoted
above both relate specifically to Petitioners concerns over
impacts resulting from changes in water quantity, the Arbitration
Panel will consider the issues together.
76. In Petitioners Proposed Arbitration
Award, Petitioners restated their concerns in a somewhat different
manner, as follows:
Issue 2: Whether the Application provides reasonable assurance that adverse
water quantity impacts to wetlands outside of the "footprint" of the reservoir
will not occur due to the anticipated alteration of the natural hydroperiods
resulting from continuous seepage out of the reservoir;
Issue 3: Whether the proposal as detailed in the Application
for monitoring and management of impacts to wetlands due to seepage
provides reasonable assurance that adverse impacts to existing
wetlands, streams and proposed mitigation projects can be adequately
detected and avoided or offset before adverse impacts occur and
is capable, based on generally accepted engineering and scientific
principles, of being effectively performed and of functioning as
proposed;
77. The difference between the two statements
of the issues appears in their differing treatment of the issue of
mitigation. In their pre-hearing stipulation statement of the issues,
Petitioners raise objections about the adequacy of TBWs mitigation
plans in general. In the later version, Petitioners focus on their
concerns as they specifically relate to seepagei.e., on the
adequacy of the mitigation plans because of the effects that seepage
may have on the implementation of such plans. Because the argument
of Petitioners has been made more specific, and because issue narrowing
has been a recognized part of this arbitration proceeding, the Arbitration
Panel will treat Petitioners mitigation concerns as being specifically
related to the leakance issuei.e., whether the leakance impacts
are adequately addressed in mitigation plans for areas that would
reasonably be expected to be impacted by the leakance.
78. The parties are in general agreement on a
number of matters relating to these issues. As previously stated
in the Arbitration Panels discussion of Issue 1, the parties
agree that the hydraulic head created by the water to be stored
within the Proposed Reservoir will cause leakance into the aquifers
underlying and surrounding the Proposed Reservoir, as well as the
surrounding surface waters.
79. The parties agree that construction of the
Proposed Reservoir will affect the amount of surface water that
would otherwise flow from the footprint to adjacent wetlands, because
1,100 acres will be removed from the project areas drainage
systems. The elimination of both wetlands drainage and stormwater
runoff from the area within the Proposed Reservoir will result
in at least some decrease in the amount of surface water reaching
property adjacent to the Proposed Reservoir.
80. The parties agree that there will be an elevation
of water tables as the result of construction and operation of
the Proposed Reservoir, at least in some locations outside of the
reservoir embankment, the extent of which is affected by a number
of factors, including accuracy of modeling, reservoir operations,
actual field conditions and the effectiveness of implementation
of management strategies directed towards lowering the water table.
81. The parties agree that construction and operation
of the Proposed Reservoir, therefore, will affect the hydrologic
regime in the area of the Proposed Reservoir, both as to timing
of the existing hydroperiod and as to the quantity of water being
delivered, stored and removed from the affected area. Because these
hydrologic changes have the potential to cause adverse impacts
upon adjacent wetlands and the property of others, the parties
further agree that it is appropriate to consider under Applicable
Substantive Law whether TBW has provided reasonable assurance in
the Joint Application that measures it has proposed to address
these potential adverse impacts comply with Applicable Substantive
Law, both as to evaluating the extent of potential impacts and
as to establishing effective measures to avoid or mitigate for
any impacts that may be adversei.e., that may cause a violation
of Applicable Substantive Law.
82. Where the parties disagree is over the degree
of hydrologic change the Proposed Reservoir is expected to create,
the adequacy of TBWs evaluation of potential impacts associated
with the change, and the sufficiency of TBWs proposals for
preventing or compensating for any impacts that may be adverse.
While TBW has proposed a management program, discussed below, that
is designed to address potential adverse impacts associated with
the hydrologic changes, the Arbitration Panel finds it necessary
first to understand the potential scope of the changes before considering
the adequacy of the management plan.
Calculating the Water Quantity Changes
83. The disagreement between the parties begins
with a difference in how to calculate the total increase in water
quantity that is reasonably expected to occur as the result of seepage
from the water. That disagreement, in turn, starts off with the parties usage
of two different mathematical models to calculate the seepage.
84. Dr. Stewart testified on behalf of TBW. Dr.
Stewart had originally intended to use a model called MODFLOW,
a numerical three-dimensional model used by the United States Geological
Service to evaluate groundwater hydrology. Because of the complexities
of the embankment design, including the geomembrane and soil cement
liners, water table levels within the embankment, the drainage
system and the cutoff slurry wall, Dr. Stewart concluded that the
MODFLOW model, while a "good model," was too restrictive to address
these complexities.
85. Dr. Stewart decided instead to use a SEEP/W
model. The model is two dimensional and used for two-dimensional
problems such as determining flow from dams and embankments. Its
principal use here was to determine the amount of flow of water
from the Proposed Reservoir to the underlying and adjacent aquifers
("fluxes"). The model is not designed to predict changes in elevations
in the water table that might be caused by such fluxes. Dr. Stewart
felt that the MODFLOW model would not be useful in predicting such
movement here because the field data was not sufficient to enable
the model to factor in the effects of variables such as evapotranspiration
(taking water out) and recharge (putting other water in).
86. Dr. Stewart used several conservative input
parameters in running the SEEP/W model, assuming (1) a full reservoir
pool at all times, (2) no sedimentary buildup in the reservoir
bottom, (3) imperfect slurry wall construction, and (4) no capture
of leakance by the creek systems outside of the Proposed Reservoir.
These inputs are conservative because TBW estimates that the Proposed
Reservoir will only be full approximately 15 percent of the time,
that sedimentary buildup will occur over time, that the slurry
wall should operate as designed, and that the creek systems, as
well as the drainage system (toe drains, swales and stormwater
ponds) around the reservoir embankment, will capture some of the
leakance.
87. Based upon the SEEP/W model calculations,
which came up with a range of numbers, Dr. Stewart estimated that
there would most likely be approximately four million gallons per
day (mgd) of leakance given the above-noted input parameters. Approximately
2.5 mgd would go out under the Proposed Reservoir embankment, with
the remainder going straight down to the Floridan Aquifer. Of the
2.5 mgd that would go out, approximately one mgd would move up
and discharge at the water table, with the remainder moving away
from the embankment, eventually going down and recharging the Floridan
Aquifer.
88. Under the SEEP/W model, it would be hard to
predict the actual impact of one mgd in elevating the water table
given the model limitations, the existence of the adjacent creek
systems, the effects of evapotranspiration and recharge, varying
geology (including hydraulic conductivity) around the site, and
the fact that the Proposed Reservoirs pool levels will vary.
This also makes it difficult to predict the lateral reach of the
water table rise. Dr. Stewart estimated that the flux from the
Proposed Reservoir could reasonably be expected to cause a foot
or more of rise for approximately 400-600 feet away from the embankment.
For the first 100-200 feet, the flux would be sufficient to cause
a rise to the surface at some period of the year. Dr. Stewart did
not take into consideration potential impacts of lateral flow induced
by changes in elevation. Furthermore, Dr. Stewart could not be
sure of the full lateral reach of the water table rise, particularly
beyond 600 feet, given that the SEEP/W model does not calculate
the effect that movement of the flux would have in changing water
table elevation, which remains constanti.e., a "boundary
condition"under the model.
89. Petitioners witness, Dr. Anderson, calculated
seepage and "push up" (the upward movement of water outside of
the reservoir footprint caused by the seepage) using the MODFLOW
model, and also evaluated Dr. Stewarts use of the SEEP/W
model. Dr. Anderson was critical of the SEEP/W model for not adequately
analyzing off-site impacts of seepage, and especially for considering
water table levels as remaining constant. He asserted that the
effect of the models application was to disregard the impacts
of push up, particularly beyond the 600 or so foot area immediately
outside the embankment.
90. Dr. Anderson used the MODFLOW model to calculate
the total amount of seepage, using the same set of "conservative
input parameters" as did Dr. Stewart. In so doing, Dr. Anderson
also applied Darcys Law, which is a formula used to calculate
how water levels will change based upon hydraulic conductivity
or permeability and changes along the flow path, the basic assumption
being that an increase in flow will cause a water table rise. Dr.
Andersons modeling efforts were specifically directed towards
looking at water table rise.
91. Dr. Andersons modeling efforts showed
possible ranges in the total amount of seepage from the Proposed
Reservoir of between two and eight mgd, and he concluded that four
mgd would be the most likely number. With regard to the lateral
extent of push up from the Proposed Reservoir, Dr. Anderson concluded
that the one foot push up linei.e., the point at which the
water table would rise by no more than one foot as the result of
leakance from a full pool reservoirwould be between 4,000
to 5,000 feet from the reservoir embankment.
92. While the two experts challenged the conclusions
generated from the models each other preferred, they both did agree
that there would be approximately four mgd of leakance from the
Proposed Reservoir, and that approximately 2.5 mgd of that leakance
would move laterally away from the embankment. The difference was
in how much of the
2.5 mgd would go up or down. Dr. Anderson concluded that there would be approximately
two mgd moving upward outside the footprint of the Proposed Reservoir, whereas
Dr. Stewart estimated the amount to be closer to one mgd.
93. The two experts also both recognized the limitations
of their own models. As Dr. Anderson acknowledged, all models are
a "simplification of the natural system." In the words of Dr. Stewart, "Mathematical
models by definition are simplifications." The experts both recognized
that the models do not look at the impacts of evapotranspiration
or topography, and that the only real way to determine the extent
of leakance and push up is to build the Proposed Reservoir and
fill it with water. The Arbitration Panel finds the opinions of
both Dr. Stewart and Dr. Anderson to be credible, and accepts their
conclusions that estimate leakance of around 4 mgd, which the Arbitration
Panel finds to be a reasonable number to expect when the Proposed
Reservoir is at full pool; and estimate about 2.5 mgd of that leakance
to move laterally away from the footprint of the Proposed Reservoir,
which the Arbitration Panel also finds to be a reasonable number.
94. The Arbitration Panel recognizes that in large
part the conclusions differ as to how much of the 2.5 mgd will
result in an alteration of the water table adjacent to the Proposed
Reservoir, because the two models are looking at two different
impactsthe SEEP/W model primarily at flux, and the MODFLOW
model primarily at push up. As a result, the Arbitration Panel
anticipates that the SEEP/W model is likely to underestimate push
up, and the MODFLOW model to overestimate it. Particularly given
the experts own acknowledgment of the limitations in the
models that they prefer to use, the Arbitration Panel finds, therefore,
that it is reasonable to anticipate that leakance at full pool
will cause between one and two mgd of leakance reasonably likely
to move upwards and thereby cause push up outside of the embankment
of the Proposed Reservoir.
95. With regard to the horizontal and vertical
extent of water table rise caused by the leakance, the experts
disagree most significantly on the extent of impact beyond 600
feet. Since Dr. Stewart conceded that the SEEP/W model was not
intended to calculate water table rise, and since the Arbitration
Panel has determined that the total amount of push up may be up
to twice the amount calculated by Dr. Stewart, the Arbitration
Panel finds it reasonable to take into consideration, for the purposes
of developing monitoring and management plans, potential water
table rise up to 4,000 feet away from the reservoir footprint,
with the amount of push up increasing closer to the embankment.
96. The Arbitration Panel does not intend consideration
of the 4,000-foot distance to constitute a finding that adverse
impacts are reasonably expected to occur up to 4,000 feet away,
or even that there will be push up of one foot up to 1,000 feet
away. Rather, this distance should be the outer limit of the areas
being studied by TBW as part of its monitoring plan, and addressed
if necessary if the monitoring shows that adverse impacts would
reasonably be expected to occur without management plan implementation.
97. Furthermore, the Arbitration Panel recognizes
these distances and depths to be estimations, given the limitations
of the mathematical models. Notwithstanding the Arbitration Panels
acceptance of Dr. Andersons horizontal and vertical calculations
of leakance impacts for the purposes of consideration in a management
plan, the Arbitration Panel would expect the true numbers to be
substantially less, once the Proposed Reservoir is constructed
and TBWs monitoring and management plans implemented.
98. Factors influencing what those true numbers
would be include variations in pool levels, topography, weather
conditions affecting evapotranspiration and water table depths,
hydraulic conductivity at various locations around the embankment,
slurry wall construction, sedimentary buildup in the reservoir
bottom, and other circumstances both contemplated and unexpected.
Given that these variables are at this point unpredictable, however,
and also are likely to have substantially different effects at
different locations throughout the property surrounding the footprint
of the Proposed Reservoir, the Arbitration Panel finds it prudent
that the more conservative assumptions of Dr. Anderson be used
at least for the purposes of determining how large an area should
be considered as part of the monitoring and management plans discussed
below.
99. As previously noted, calculating the true
impact of the Proposed Reservoir on adjacent property outside of
its footprint is further complicated by the fact that its construction
will eliminate a significant amount of surface water currently
flowing onto the adjacent property from the 1,100-acre area within
the reservoir embankment. These impacts take water out of the system
rather than add to it.
100. The Petitioners have not disputed TBWs
calculations of how much reduction will occur in surface water
flows as a result of elimination of drainage from the 1,100-acre
reservoir site. According to Mr. Meyer, there would be a net reduction
of 230 cubic feet per second in stormwater runoff into adjacent
streams as a result of the capture of that stormwater within the
embankment of the Proposed Reservoir. According to calculations
in the Joint Application, the net difference to the ground/surface
water system would be between 0.5 and one mgd. While the surface
water numbers are not disputed, the net difference is disputed,
since the difference would be greater assuming the accuracy of
Dr. Andersons calculations. The environmental effects of
the net difference would also be impacted by the fact that because
so much of the surface water flow comes from stormwater, and the
amount of seepage will vary depending upon the pool levels within
the Proposed Reservoir, the net difference will vary over time.
101. In the final analysis, the true impacts of
groundwater and surface water changes can only be fully calculated
and understood once the Proposed Reservoir is constructed and placed
into operation. Whatever the impacts ultimately prove to be, the
Arbitration Panel finds that there will be leakance from water
stored within the footprint of the Proposed Reservoir, the groundwater
flow of the leakance will cause push up in areas surrounding the
footprint, and elimination of surface water runoff from within
the footprint will result in some reduction in the total amount
of water thereby exiting the Proposed Reservoir and impacting adjacent
wetlands and the property of others. Given the large volume of
water to be stored in the Proposed Reservoir, the amount of water
being added is of sufficient quantity, and the existing hydroperiod
is being sufficiently changed, that without adequate monitoring
and management, adverse impacts are reasonably likely to occur
to receiving waters and adjacent lands. These potential impacts
are substantial enough so as to require that the Joint Application
be evaluated to determine whether TBWs plans to monitor for
and manage these impacts are detailed enough to comply with Applicable
Substantive Law.
102. Furthermore, these impacts need to be evaluated
without assuming they will be offset by a successful management
plan. As explained more fully below, in order to review the scope
and effectiveness of such a management plan, it is first necessary
to establish baseline data.
Assessing Potential Impacts from the Water
Quantity Changes
103. In order to evaluate fully the potential
impacts of the Proposed Reservoir resulting from changes in water
quantity upon adjacent wetlands and the property of others, without
assuming that such impacts will be offset by a management plan, the
first step is to evaluate existing conditions.
104. The parties have identified two wetland systems
that may be adversely impacted by water quantity changes. Immediately
adjacent to the western, eastern and northern boundaries of the
Proposed Reservoir are two riverine, hardwood wetland systems that
extend to within one to two hundred feet of the toe of the embankment:
Long Flat Creek and Doe Branch. Other adjacent natural areas include
improved pasture and upland scrubby flatwoods.
105. Doe Branch supports a mixed canopy of laurel
oak, sweet bay, cabbage palm, and an understory of flowering dogwood
and dahoon holly, with sparse amounts of catbriar and leaf litter
as groundcover. Long Flat Creek generally supports a canopy dominated
by red maple, laurel oak, sweet gum, sweet bay, and cabbage palm.
Wetter areas also support cypress, black gum and Carolina ash.
Groundcover consists of numerous weedy species in addition to Virginia
chain fern, cinnamon fern, netted chain fern, and in wetter areas
lizard tail. All of these species are typical of riverine swamp
and are adapted to temporary to seasonal inundation.
106. Petitioners have also identified as an area
of potential concern the East Pruitt mitigation site. The East
Pruitt property is among the 4,700 acres identified by Petitioners
for acquisition by SWFWMD as part of the mitigation plan for offsetting
the impacts of elimination of wetlands within the footprint of
the Proposed Reservoir and other wetlands being eliminated as part
of reservoir construction activities. The East Pruitt area is located
immediately adjacent to the northwestern edge of the Proposed Reservoir
boundary, and includes within it portions of Doe Branch. TBW has
acknowledged that seepage from the Proposed Reservoir may impact
areas being considered for development as mitigation sites within
the East Pruitt area.
107. Petitioners other area of concern is
the Wendel Avenue neighborhood. Petitioners are concerned that
seepage may adversely affect wells and septic tanks because of
the impacts of changes caused by the seepage in both water quality
(as discussed in Issue 1) and water quantity (from water table
rise).
108. In the Joint Application at Appendix D, Section
5.3, TBW recognizes that potential adverse effects could occur
to the two adjacent wetland systems as a result of seepage from
the Proposed Reservoir. TBW acknowledges, "The exact response of
the aquifer as well as the adjacent environment must be monitored
so that appropriate management strategies can be implemented prior
to the manifestation of any adverse effects. The monitoring protocol
and management strategies will provide reasonable assurances that
adverse environmental effects do not occur as a result of the project."
109. Appendix D refers to Appendix H for an "outline" of
the proposed monitoring program. Appendix H, in turn, at Section
4.6, states that "a monitoring program will be implemented by [TBW]
to assess subsurface groundwater conditions before, during and
after filling of the reservoir." The monitoring program will consist
of a "network of piezometers located along the perimeter of the
reservoir and near the adjacent streams." The program would use
both existing monitoring wells and wells not yet identified.
110. Mr. Eliason testified on behalf of TBW regarding
its efforts to assess wetland impacts associated with construction
and operation of the Proposed Reservoir. Mr. Eliason testified
that TBW has not quantified potential impacts because the modeling
numbers assumed an unlikely worst case scenario and because TBW
is planning to use a management plan to avoid adverse impacts altogether.
111. TBW asserts that it is seeking not to avoid
any impacts from the hydrologic changes caused by the Proposed
Reservoir, but to avoid any adverse impacts. TBW intends to accomplish
this through monitoring the existing wetland regime so that indicators
of stress can be identified prior to irreparable damage occurring,
and through manipulating groundwater levels by pumping to relieve
the stress prior to such damage. In Mr. Eliasons words, "The
goal of the monitoring and management plan is not to mimic the
natural fluctuations in that water table . . . [, but] to manage
for adverse impacts."
112. The monitoring plan proposed by TBW to FDEP
would involve the location of additional wells to those already
identified in the Joint Application, the setting of vegetation
transects at strategic locations along the creek beds to look for
stress, and the use of color infrared aerial photography to evaluate
the spread of moisture in the soils from leakance.
113. TBWs proposal does not lay out specific
details of a monitoring or management strategy. Rather, the plans
are "conceptual" only, with details to be worked out with FDEP
during the permit application process. Mr. Eliason testified that
TBW had gathered the information necessary with regard to groundwater
monitoring and infrared photography to put a more specific plan
together, and that transects were in the process of being performed
and should be completed shortly. The information has yet to be
included within the Joint Application, however.
114. Therefore, there is no information in the
Joint Application that would enable quantification of the extent
of potential damage to the wetlands surrounding the Proposed Reservoir
assuming an "unmanaged" scenarioi.e., no implementation of
a management plan designed to prevent any adverse impacts. Nor
is such a quantification available assuming a "mismanaged" scenarioi.e.,
unsuccessful implementation of the management plan.
115. Hydrologic changes can cause stress to occur
in wetland species that may not be detectable until substantial
adverse impacts have already occurred. While the management plan
relies upon stress indicators to trigger corrective action, the
monitoring plan does not clearly define when stress results in
an unacceptable adverse impact. To the extent, therefore, that
a monitoring plan relies upon stress indicators, those indicators
must be clearly identified in order for the plan to be reviewable
for compliance with Applicable Substantive Law.
116. Because the monitoring and management plans
are only "conceptual" in nature at this point in the proceedings,
and because TBW has not made any effort either to identify or to
quantify potential adverse impacts in the event the management
plan does not prove effective, the Joint Application does not currently
meet the reasonable assurance test for compliance with Applicable
Substantive Law.
117. The Panel finds that TBW has established
a reasonable conceptual basis for monitoring and management plans,
and therefore does not consider the Proposed Reservoir at this
point in the proceedings to be unpermittable. But the Joint Application
as presented to the Panel is incomplete. As Mr. Eliason acknowledged,
the Joint Application is not at this point in time a "permittable
document," even though the project itself may be permittable, because
the monitoring and management plans have not been fully developed.
118. This acknowledgment is also contained in
the text of the Joint Application. Appendix D, Sections 5.3.1&2,
states that details of the monitoring plan have "not yet been fully
developed," and that specific criteria for unacceptable changes
that need to be addressed "will be developed during the permitting
process through coordination with regulatory agencies."
119. The Joint Application in its current state
is incomplete because it lacks sufficient detail for a determination
of whether potential adverse impacts from leakance have been appropriately
and accurately identified. In order to overcome this incompleteness,
TBW must provide in the Joint Application a delineation of the
wetland system and its supporting hydrologic regime with enough
specificity so that the full extent of potential adverse impacts
can be determined, for three reasons:
(a) To establish a baseline so that the potential for adverse impacts to occur
can be fully measured;
(b) To assist in the development of a management plan, by identifying specifically
the wetlands to be protected, the hydroperiod needed to maintain these wetlands
with the same level of protection, and the types of strategies that can be
utilized to accomplish the protection; and
(c) To provide a basis for the establishment of a backup mitigation plan in
the event that the management plan proves unsuccessful in whole or part.
120. To help determine potential impacts and evaluate possible
remedial measures, the delineation should take into consideration the wetland
species, topography, soils and geology of the area. One way to accomplish this
was illustrated by Dr. Dennis, who performed a series of surveys of transects
into the wetland systems adjacent to the Proposed Reservoir. Dr. Dennis transects
point out that the wetland system potentially impacted has seepage slopes that
require careful attention in any management plan if adverse impacts are to
be avoided.
121. The Joint Application is also insufficient
because the East Pruitt mitigation plan has not yet been developed.
Here the baseline would be established through development of a
plan with sufficient detail to know where the mitigation area or
areas will be located, how large they will be, and what they will
consist of in the way of type, nature and function of the wetland
systems to be created, enhanced or protected. Without such detail
there is no way to determine how a management plan would be protective
of these mitigation areas.
122. Mr. Eliason indicated that TBW has gathered
enough historical information over the last 20 years, to make a
determination of what groundwater levels should be included in
the Joint Application as establishing how adverse impacts can be
avoided. TBW has not yet included this type of information in its
Joint Application, however, and those levels need to be included
because they are an important component of the reasonable assurance
criteria. Similarly, the Joint Application should include information
regarding transects of wetlands vegetation that TBW has already
undertaken.
123. A management plan alone cannot suffice for
establishing baseline conditions. While monitoring for stress may
be an appropriate component to a management plan that relies on
groundwater manipulation to avoid adverse impacts, such monitoring
is insufficient by itself. It is critically important to have a
detailed description in the monitoring plan as to how stress indicators
are determined and which ones are acceptable, since adverse impacts
may have already occurred prior to corrective action being able
to be undertaken.
124. TBW has already indicated both its commitment
to and the necessity of undertaking a monitoring program, as indicated
by Section 5.3.1. of Appendix D to the Joint Application. TBW recognizes
that elements of the monitoring program must include "[t]ransects
[to] be established in the hardwood floodplains of both Long Flat
Creek and Doe Branch for the collection of data related to tree
health, reproductive state, and growth. Herbaceous and shrub cover
will be evaluated for composition and distribution within the floodplain
as well as qualitative assessments of plant health." The monitoring
plan must also identify groundwater levels and hydroperiod, since
the goal of the plan, as TBW acknowledges, "is to detect changes
in surficial water levels and manage them prior to
the occurrence of any adverse environmental effects."
125. While this commitment sounds appropriate
as a conceptual description of what TBW should include in a Joint
Application, the commitment needs to be implemented to establish
reasonable assurance. Given Mr. Eliasons testimony about
the substantial work that has been done and is ongoing at the project
site, and given the quality of the work performed by TBW on the
project to date, TBW should be able to develop a delineation that
will provide sufficient specificity to meet the reasonable assurance
test.
126. TBW has asserted that there may be impacts
not adverse to the wetland systems that nonetheless alter their
character in some way. All wetland systems are not the same, however,
and the natural community here has adapted to the system as it
currently exists. If the system changes, the burden would be on
TBW to show that the new system would not constitute an adverse
impact. This cannot be done without a baseline evaluation of the
current wetland system.
127. In addition, the Joint Application should
include a quantification of stream flows in Long Flat Creek and
Doe Branch, so that the potential impacts from seepage and surface
water runoff can be evaluated and managed together.
Managing Adverse Water Quantity Impacts
128. Petitioners have criticized TBWs management
plan because TBW has not identified with sufficient detail the number
of extraction wells needed, the location and spacing of the wells,
or the precise levels at which groundwater must be maintained in
order to avoid adverse impacts. TBW, in turn, asserts that such information
should be developed subsequent to permit issuance and project construction,
because existing leakance predictions are unrealistically conservative
and cannot accurately predict the location or amount of anticipated
leakance. Once the filling of the Proposed Reservoir begins, TBW
would then have an ability to respond to actual conditions and to
efficiently calibrate the system at the locations and in consideration
of the amounts of leakance which actually occur .
129. Petitioners criticisms have merit.
The management plan does not have specific extraction well locations,
pumping rates, water table levels to achieve, or hydroperiods to
maintain. This does not mean that every detail of a management
plan must be carved in stone prior to permit issuance. The Arbitration
Panel finds that the project can meet the reasonable assurances
standard even though TBW defers much of the management plan details
until after permit issuance and commencement of reservoir operation,
provided the agencies have sufficient information to impose conditions
that will ensure a management plan that meets the reasonable assurance
test. This can be accomplished provided that TBW has already established
baseline conditions through a detailed delineation of the wetland
system as described herein. Only then would the permitting agencies
be able to evaluate whether in fact the impacts from the Proposed
Reservoir would be adverse or not.
130. Nonetheless, TBW has not provided sufficient
information on its management plan to explain how it will control
leakance. At this time, therefore, TBW has not provided reasonable
assurance that its management plan is sufficient to offset adverse
impacts from push up. The Arbitration Panel agrees with TBW that
it is too soon to provide a final, detailed management plan since
the exact amount and location of leakance cannot be presently predicted
given a number of factors previously discussed. But this uncertainty
does not mean that specific information should not be provided
at this time to assure that the components of the management plan
are effective at controlling the expected leakance. Such a plan
should indicate the types of wells to be used to maintain those
levels, the capacity of such wells to reduce leakance in terms
of time and space, historical information on how similar strategies
have performed in the past, and the proposed placement of those
wells given potential leakance to a distance of 4,000 feet from
the Proposed Reservoir footprint. The precise locations, depths
and types of wells to be used at the various areas around the Proposed
Reservoir need not be shown, since that will be determined according
to baseline and actual site conditions after the Proposed Reservoir
is built.
131. A greater degree of specificity can also
be used to develop a mitigation plan to address potential adverse
impacts that cannot be avoided through the maintenance plan. The
monitoring and maintenance plans must have a level of detail sufficient
to enable the permitting agencies to assess the extent of adverse
impacts if maintenance is not completely successful, as well as
to be able to formulate as a permit condition a backup plan for
mitigation for any adverse impacts that the management plan is
ineffective in preventing. Because of the difficulties in developing
all of the details of a maintenance plan when not all of the impacts
can be known until construction and operation of the Proposed Reservoir,
TBW must include in its Joint Application a commitment to implement
this backup mitigation plan to compensate for any adverse impacts
that the maintenance plan cannot prevent.
132. The maintenance plan should also be integrated
with the mitigation plans for the East Pruitt area. This requires
first that the East Pruitt mitigation plans must be developed with
sufficient detail so that there is reasonable assurance that the
mitigation can be constructed and maintained successfully. Secondly,
the maintenance plan must be coordinated with the East Pruitt mitigation
plans so that the maintenance plan will not be damaging to and
will in fact protect and enhance the establishment and maintenance
of those mitigation areas.
133. Finally, the maintenance plan should address
potential adverse impacts to residents of the Wendel Avenue neighborhood.
Since the Arbitration Panel has determined that TBW should be prepared
to address potential impacts from water table push up of one foot
or more within 4,000 feet of the reservoir embankment, since at
least some of the homes in the neighborhood are within that distance,
and since the homes use private wells and septic systems, the management
plan should address these considerations. The focus of the maintenance
plan for the Wendel Avenue neighborhood should be to ensure that
no septic tanks or drinking water wells are adversely impacted
by leakance or push up. As previously noted, the Arbitration Panel
rejects Petitioners request that the plan also include extensive
modeling to determine adverse water quality impacts, since the
Panel has found that those are not reasonably expected to occur.
The maintenance plan, instead, should be implemented in a manner
consistent with the Arbitration Panels findings under Issue
1 i.e., that groundwater should be monitored, for both quality
and quantity.
134. In Petitioners Proposed Arbitration
Award, Petitioners ask the Arbitration Panel to require TBW to
make a further and more detailed assessment of the effect of push
up outside the Proposed Reservoir. Since Petitioners have already
done their own assessment, and since the Arbitration Panel finds
that reasonable assurance can be met if TBWs monitoring and
maintenance plan assumes as an outside limit the assessment contained
in Petitioners modeling efforts as presented at hearing in
this case, the Arbitration Panel sees no need for TBW to do further
modeling as part of the permit application. If TBW prefers not
to incorporate Petitioners modeling into TBWs own monitoring
plan, however, the Arbitration Panel finds that it would be acceptable
for TBW to propose its own additional modeling, provided the modeling
takes into consideration the vertical and horizontal extent of
push up.
135. In Petitioners Proposed Arbitration
Award, Petitioners also ask the Arbitration Panel to provide more
complete responses to RAI Nos. 2, 5, and 9. These RAIs appear to
be asking for more information regarding the adequacy of the mitigation
proposed for wetland impacts within the footprint of the Proposed
Reservoir. The Arbitration Panel finds it difficult to understand
exactly what Petitioners are seeking by this request, but considers
the appropriate response to be that the East Pruitt mitigation
plan needs to be more fully developed for the reasons set forth
herein, but that none of the plans for other mitigation areas proposed
by TBW remain at issue in this proceeding.
Issue 4
Public Health, Safety, and Welfare
Issue 4: Whether the Application provides reasonable assurance
that the public health and safety has been adequately protected
when the Application does not:
a. include a dam break analysis, including inundation map,
and the emergency action plan is not complete;
c. address design alternatives to avoid or minimize risks
to public health and safety;
d. is based upon "average" site conditions rather than
actual conditions;
e. include design or analysis for emergency or rapid drawdown
conditions; and
f. address impacts to septic fields, domestic wells, and
surface drainage.
136. Petitioners take the position that TBW has
not demonstrated reasonable assurance that public health, safety
and welfare will be adequately protected by the Proposed Reservoir.
These concerns are addressed in this arbitration award, first from
the standpoint of embankment design and stability, and then in connection
with dam breach analysis, inundation mapping and the Emergency Action
Plan ("EAP"). Except to the extent that it may be relevant to this
analysis of public health, safety and welfare, potential impacts
to septic tanks, domestic wells, and surface drainage are discussed
in the earlier sections of this arbitration award dealing with water
quantity, quality and leakance.
Embankment Design and Stability
Site Selection and Geologic Analysis
137. Site selection is the first step in designing
a stable embankment. In a project such as the Proposed Reservoir,
it is important to have an understanding of the subsurface structure
because it is a factor in the stability and safety of the embankment.
The results of this type of study may indicate a need for design
changes or the unsuitability of a particular location. Safety of
the Proposed Reservoir has been a major consideration for TBW.
138. One of TBWs original goals was to find
a site outside the urban service area that had already been disturbed
by human activity, and that was in reasonable proximity to a water
supply source, which in this case would be the Hillsborough and
Alafia Rivers. TBW went through an extensive site selection process,
which initially focused on 17 sites, was subsequently reduced to
7 sites, and then to 3 sites before the final site was selected.
139. While densely populated areas were avoided
during site selection for a number of reasons, not all populated
areas could be avoided nor is such avoidance necessary. Other manmade
water supply reservoirs are commonly located in urban or suburban
areas. For example, in places within California, Colorado, Texas,
North Carolina and along the Missouri River, water reservoirs are
located in places within close proximity to populated areas. Also,
in Denver, dams co-exist alongside major infrastructure projects,
including state roads and interstate highways running along the
toe and crest of the reservoirs.
140. As the list of potential sites was narrowed,
TBW began to conduct rudimentary geophysical and geotechnical investigations,
including soil borings. TBW assembled a multi-disciplinary team
of experts for the embank |