Environmental Protection Commision
of Hillsborough County, Florida and Hillsborough County, Florida,
Petitioners,
v.
TAMPA BAY WATER, a Regional Water
Supply Authority,
Respondent.
________________________________________________/
Arbitration Award for Proposed Tampa Bay
Regional Reservoir
Pursuant to Sections 3.13 and 3.16 of the "Amended and Restated
Interlocal Agreement Reorganizing the West Coast Regional Water Supply
Authority," dated June 10, 1998, this is the arbitration award, including
findings of fact and conclusions of law, in the above-captioned proceeding.
Finding of Fact
Background of Parties to Arbitration Proceeding
1. Tampa Bay Water ("TBW") is a regional water
supply authority created pursuant to Sections 373.1962, 373.1963
and 163.01, Florida Statutes (2000). TBW was originally created as
the West Coast Regional Water Supply Authority in 1974 by an interlocal
agreement among Hillsborough County, Pasco County, Pinellas County,
the City of Tampa and the City of St. Petersburg. The City of New
Port Richey was later added as a member of the West Coast Regional
Water Supply Authority. Joint Pre-Hearing Stipulation filed March
16, 2001 ("Joint Pre-Hearing Stipulation"), p.13.
2. The West Coast Regional Water Supply Authority
was reorganized and restructured pursuant to the "Amended and Restated
Interlocal Agreement Reorganizing the West Coast Regional Water
Supply Authority" ("1998 Interlocal Agreement"), dated June 10,
1998. The reorganization of the West Coast Regional Water Supply
Authority was expressly authorized by Section 373.1963, Florida
Statutes, and was approved by Final Order of the Florida Department
of Environmental Protection (FDEP) dated June24, 1998, in OGC Case
No. 98-1921. The parties to the 1998 Interlocal Agreement are Hillsborough
County, Pasco County, Pinellas County, the City of Tampa, the City
of St. Petersburg, and the City of New Port Richey. The Board of
TBW is comprised of elected officials from each of the six member
governments. Joint Pre-Hearing Stipulation, p. 13.
3. By Joint Resolution No. 98-05, the West Coast Regional Water Supply
Authority was renamed "Tampa Bay Water, A Regional Water Supply Authority." Joint
Pre-Hearing Stipulation, p. 13.
4. Hillsborough County is a governmental entity
and a political subdivision of the State of Florida and a member
government of TBW.
5. The Environmental Protection Commission of
Hillsborough County ("EPCHC") is a governmental agency statutorily
created by a special act of the Legislature.
Need for Tampa Bay Regional Reservoir
6. TBW is the exclusive wholesale water supplier
responsible for meeting the potable water needs of its six member
governments. The member governments collectively serve approximately
2 million customers. Joint Pre-Hearing Stipulation, p. 14.
7. Under the 1998 Interlocal Agreement, TBW has
the unequivocal obligation to meet the potable water needs of its
six member governments on a regional basis. The Master Water Supply
Contract between TBW and the six member governments outlines how
TBWs facilities will be connected to the member governments'
facilities and sets forth provisions for billing and collecting
for the sale of water by TBW to the member governments. Joint Pre-Hearing
Stipulation, p. 14.
8. TBWs existing water supply facilities
consist of a series of wellfields located throughout Hillsborough,
Pinellas and Pasco Counties. These are: the Cypress Creek Wellfield;
the Cross Bar Ranch Wellfield; the Cypress Bridge Wellfield; the
Northwest Hillsborough Wellfield; the Starkey Wellfield, the North
Pasco Wellfield; the South-Central Hillsborough Wellfield; the
Cosme-Odessa Wellfield; the Section 21 Wellfield; the South Pasco
Wellfield; the Eldridge-Wilde Wellfield; and the Morris Bridge
Wellfield. With the exception of the South-Central Hillsborough,
Starkey and North Pasco Wellfields, these facilities are interconnected
and are part of an interconnected water production system. Joint
Pre-Hearing Stipulation, p. 14.
9. The 1998 Interlocal Agreement requires that
TBW maintain a supply capacity that is six percent greater than
actual demand, on an average annual basis. The failure of TBW to
maintain this six percent reserve capacity for a continuous six-month
period is defined under the 1998 Interlocal Agreement as "Production
Failure." The six percent reserve capacity is intended to create
a buffer between demand and permitted capacity. Joint Pre-Hearing
Stipulation, p. 14.
10. Should TBW fail to maintain the six percent
reserve capacity for a continuous six-month period, a "Production
Failure," the member governments are entitled under the 1998 Interlocal
Agreement to independently pursue their own water supplies. Joint
Pre-Hearing Stipulation, p. 14.
11. In April, 1998, TBW, its six member governments,
and the Southwest Florida Water Management District ("SWFWMD")
entered into an agreement entitled the "Northern Tampa Bay New
Water Supply and Ground Water Withdrawal Reduction Agreement," commonly
called the "Partnership Agreement." Joint Pre-Hearing Stipulation,
p. 14.
12. The Partnership Agreement has four principal
stated objectives: to develop at least 85 million gallons daily
("mgd") annual average of new water supply to meet the needs of
the area; to effect a reduction in groundwater pumping from the
11 existing wellfields to no more than 121 million gallons daily
annual average as of December
31, 2002 through December 31, 2007, and to no more than 90 mgd annual average
as of December 31, 2007 through December 31, 2010, to allow environmental recovery;
to end existing litigation between the parties to the Partnership Agreement
and avoid future litigation, including administrative proceedings; and to create
a funding mechanism through which TBW can develop new water supply projects.
Joint Pre-Hearing Stipulation, p. 15.
13. Pursuant to the Partnership Agreement, the
existing water use permits for the 11 wellfields specified therein
(Cosme-Odessa, Cross Bar Ranch, Cypress Bridge, Cypress Creek,
Eldridge-Wilde, Morris Bridge, Northwest Hillsborough Regional,
North Pasco, Section 21, Starkey, and South Pasco) were consolidated
into a single permit ("Consolidated Permit") under which TBW is
the sole permittee. The expiration date of the Consolidated Permit
is December 31, 2010. Joint Pre-Hearing Stipulation, p.15.
14. Prior to execution of the Partnership Agreement,
the existing permits for the 11 wellfields allowed for cumulative
withdrawals totaling approximately 192 mgd. Upon execution of the
Partnership Agreement, the Consolidated Permit immediately reduced
allowed withdrawals to 158 mgd. Joint Pre-Hearing Stipulation,
p. 15.
15. The Partnership Agreement requires that wellfield
pumping from the 11 wellfields be further reduced to no more than
121 mgd by December 31, 2002, and then to 90 mgd by December 31,
2007.
16. The Partnership Agreement also requires TBW
to develop at least 38 mgd of new water supply by December 31,
2002, and a total of 85 mgd of new water supply by December 31,
2007. Joint Pre-Hearing Stipulation, p. 15.
17. The Partnership Agreement requires TBW to
submit to the SWFWMD by July 1, 1998, a "New Water Plan" describing
the projects that TBW intends to implement to meet the requirements
of 38 mgd of new water supply by December 31, 2002, and 85 mgd
of new water supply by December 31, 2007. Joint Pre-Hearing Stipulation,
p. 15.
18. TBW and Hillsborough County have each individually
approved a "New Water Plan" that is intended to meet the requirements
of the 1998 Interlocal Agreement and the Partnership Agreement.
The Environmental Protection Commission of Hillsborough County
is not a member government and thus did not approve the New Water
Plan. Joint Pre-Hearing Stipulation, p. 16.
19. The planning and development of the New Water
Plan took into account demand calculations based on population
projections and per capita usage, the six percent reserve capacity
required under the 1998 Interlocal Agreement, and the wellfield
pumping reductions and new water supply requirements mandated by
the 1998 Interlocal Agreement and the Partnership Agreement. The
New Water Plan is designed to meet all of these requirements, including
the projected increased demand during the period between December
31, 2002 (the first phase of wellfield pumping reductions) and
December 31, 2007 (the second phase of wellfield pumping reductions).
Joint Pre-Hearing Stipulation, p. 16.
20. The New Water Plan includes the following
projects: the Brandon Urban Dispersed Wells ("BUDW") project; the
North and South Central Interties; a seawater desalination project;
and the Enhanced Surface Water System, which includes the Alafia
River Project, the Tampa Bypass Canal/Hillsborough River High Water
("TBC") project, the South Central Intertie, the Tampa Bay Regional
Surface Water Treatment Plant, and the proposed off-stream water
reservoir (described in more detail in subsequent sections of this
arbitration award and referred to as the "Proposed Reservoir")
that is at issue in this arbitration proceeding. Joint Pre-Hearing
Stipulation, p. 16.
21. The Proposed Reservoir will provide an additional
25 mgd of water supply to the region in average year conditions
and 40 mgd in drought conditions, without increasing any water
use permits. When withdrawals from other surface water sources
cannot occur because of drought or other conditions, the Proposed
Reservoir can provide up to 66 mgd of water supply.
22. The June 2000 New Water Plan states that the
Enhanced Surface Water System is eligible for a maximum of $120
million from SWFWMD, pursuant to its funding obligation under the
Partnership Agreement. Joint Pre-Hearing Stipulation, p. 16.
23. TBW does not furnish water to any person or
entity other than its six member governments and does not sell
any water on a retail basis. All potable water produced by TBWs
facilities is for resale on a wholesale basis to the member governments.
Joint Pre-Hearing Stipulation, p. 16.
24. The 1998 Interlocal Agreement empowers TBW
to produce and supply drinking water "in such manner as will give
priority to reducing adverse environmental effects of excessive
or improper withdrawals of water from concentrated areas." Joint
Pre-Hearing Stipulation, p. 17.
Background of This Arbitration Proceeding
25. The 1998 Interlocal Agreement requires the
member governments, like Hillsborough County, and TBW to enter
into binding arbitration if there is a dispute regarding "Primary
Environmental Permit Applications," as that term is defined in
the 1998 Interlocal Agreement, for TBW projects. The EPCHC is also
subject to the binding arbitration process set forth in the 1998
Interlocal Agreement for Primary Environmental Permit Applications.
Hillsborough County, by entering into the Interlocal Agreement,
and the EPCHC, by separate agreement with the Authority, waived
their right to challenge proposed agency action on Primary Environmental
Permit Applications pursuant to Chapter 120, Florida Statutes (2000).
26. On September 18, 2000, TBWs Board of
Directors approved the filing of a joint application for an Environmental
Resource Permit from the FDEP and a U. S. Army Corps of Engineers
Section 404 Dredge and Fill Permit (collectively "Joint Application")
for the Proposed Reservoir. The Proposed Reservoir is designed
to be an off-stream water reservoir more particularly described
subsequently in this arbitration award. The Joint Application is
a "Primary Environmental Permit Application" under the 1998 Interlocal
Agreement and is therefore subject to binding arbitration.
27. The approval by TBW of the Joint Application
triggered the timetable under the 1998 Interlocal Agreement for
appropriate parties to file for binding arbitration. On October
16, 2000, Hillsborough County and EPCHC (jointly referred to herein
as "Petitioners") notified TBW of their opposition to the Joint
Application and demanded binding arbitration in accordance with
the 1998 Interlocal Agreement.
28. The 1998 Interlocal Agreement delineates an
expedited and strict procedural process for the binding arbitration,
including a detailed discovery process and an expedited time line
for the completion of all arbitration proceedings. 1998 Interlocal
Agreement, Sections 3.13, 3.16 and Appendix N.
29. This Arbitration Panel was impaneled on November
17, 2000, in accordance with the 1998 Interlocal Agreement. Arbitrator
Daniel Fernandez was selected by TBW and arbitrator Daniel Thompson
was selected by Petitioners. Arbitrator and Chair of the arbitration
panel, Carlos Alvarez, was selected by Mr. Fernandez and Mr. Thompson
in accordance with the 1998 Interlocal Agreement. (The three arbitrators
are jointly referred to as the "Arbitration Panel.") On December8,
2000, each member of the Arbitration Panel took an oath, pursuant
to Section 3.16 of the 1998 Interlocal Agreement, to conduct all
of his duties and responsibilities for the totality of the arbitration
proceedings with "impartiality and fidelity." 1998 Interlocal Agreement,
Section 3.16 (B). In compliance with paragraph 6 the Agreed Order
on Case Management dated December 12, 2000, there have been no
ex parte communications between the arbitrators and any of the
parties or their counsel
30. The Arbitration Panel issued a number of orders
throughout the arbitration process. Two of the orders, Order on
Motion to Determine Scope of Arbitration and Related Motion to
Strike dated December22, 2000 ("Arbitration Panel Order, December
22, 2000"), and Order on Respondents Motion for Order Determining
Applicable Agency Rules, Policies and Statutes dated February 28,
2001 ("Arbitration Panel Order, February 28, 2001"), are attached
as Attachments 1 and 2, respectively, to this arbitration award.
Because the substance of these orders defines the scope and nature
of the arbitration proceeding and ultimately the arbitration award,
these orders are part of this arbitration award.
31. Pursuant to Agreed Order on Case Management
Order dated December 12, 2000, and AppendixN of the 1998 Interlocal
Agreement, the parties proceeded through an expedited discovery
process that ended on March 1, 2001. On February 27, 2001, TBW
also submitted to the FDEP the Response to Request for Additional
Information ("RAI Response"), which provides additional information
about the Proposed Reservoir. The RAI Response was TBWs answer
to the Request for Additional Information ("RAI") submitted by
the FDEP in connection with its permitting review of the Joint
Application.
32. The final hearing on the arbitration award
began on March 16, 2001, and ended on April9, 2001. Within these
dates, the Arbitration Panel heard testimony and argument on 13
days. The hearing was held in Hillsborough County with the consent
of all the parties.
33. On April 4, 2001, the Arbitration Panel visited
the site of the Proposed Reservoir and surrounding areas, accompanied
by counsel and consultants for all parties.
34. All parties were represented by counsel. Appearing
on behalf of TBW were:
Donald D. Conn, General Counsel
Tampa Bay Water
2535 Landmark Drive, Suite 211
Clearwater, FL 33761-3930
E. A. "Seth" Mills, Jr., Esquire
Robert L. Olsen, Esquire
Fowler, White, Gillen, Boggs, Villareal and Banker, P.A.
P.O. Box 1438
Tampa, FL 33601-1438
Appearing on behalf of Petitioners were:
Roger W. Sims, Esquire
Rory C. Ryan, Esquire
Jeffrey T. Donner, Esquire
Holland & Knight LLP
200 S. Orange Avenue, Suite 2600
P.O. Box 1526
Orlando, FL 32802
Frederick T. Reeves, Esquire
Hobby Grey & Reeves
5709 Tidalwave Drive
New Port Richey, FL 34652-3281
Patrick B. Courtney, Esquire
Lansky & Courtney
512 E. Kennedy Blvd.
Tampa, FL 33602
Edward B. Helvenston, Esquire
Rick Muratti, Esquire
Assistant County Attorneys
Office of the Hillsborough County Attorney
P.O. Box 1110
Tampa, FL 33601
Kristin K. Bennett, Esquire
Hillsborough County Environmental Protection Commission
1900 Ninth Avenue East
Tampa, FL 33605
35. TBW presented the following witnesses:
(a) Jerry Maxwell. Mr. Maxwell was a fact witness.
(b) Ed Copeland. Mr. Copeland was qualified as an expert witness in civil engineering,
the management and direction of projects like the Proposed Reservoir, and environmental
resource permit application projects in general.
(c) Dr. Anwar Wisa. Dr. Wisa was qualified as an expert in the area of geotechnical
engineering, specifically with an emphasis in embankment stability of earthen
dams.
(d) Richard Donovan. Mr. Donovan was qualified as an expert in the areas of
civil and geotechnical engineering as they relate specifically to dam embankment
design and stability analyses.
(e) Dr. Sam Upchurch. Dr. Upchurch was qualified as an expert in the areas
of Florida geology, karst, hydrogeology, and water quality analysis.
(f) George Eliason. Mr. Eliason was qualified as an expert in environmental
sciences, delineation of wetland impacts, characterization of wetland systems,
and analysis of wetland functions and value, including hydroperiods.
(g) Helen Bennett. Ms. Bennett was a fact witness.
(h) George Feher. Mr. Feher was qualified as an expert in wetland planning,
including specifically the preparation of preliminary plans and follow-up detail
plans and construction plans, and related permitting processes.
(i) Dr. Mark Stewart. Dr. Stewart was qualified as expert in geology, including
geologic and hydrogeologic site evaluation, and specifically with regard to
sinkholes and karst features, and also as an expert in water resources management,
including integrated mathematical modeling of surface water and groundwater
systems.
(j) Mr. Barry Meyer. Mr. Meyer was qualified as an expert in civil engineering,
including the design of water-control systems and methods of control of groundwater
and surface water.
36. Petitioners presented the following witnesses:
(a) Mark Farrell. Mr. Farrell was a fact witness.
(b) Paula Harvey. Ms. Harvey was a fact witness.
(c) Larry Gispert. Mr. Gispert was qualified as an expert in emergency management
and, specifically, as an expert in emergency management in Hillsborough County.
(d) Jeremy Craft. Mr. Craft was qualified as an expert witness in ERP rule
interpretation, FDEP agency practice regarding the application of the ERP rules
to the reasonable assurance criteria, public interest criteria and the requirements
for meeting those criteria, and wetland impact assessment and mitigation.
(e) Peter Anderson. Mr. Anderson was qualified as an expert in groundwater
hydrology and modeling of groundwater systems.
(f) Thomas Simonetti. Mr. Simonetti was qualified as an expert in water quality
analysis, particularly in the use of chemicals or water treatment additives
and their potential environmental impacts.
(g) Dr. Norman Blake. Dr. Blake was qualified as an expert in pollution ecology
and the effect of copper on marine and freshwater systems.
(h) Ross McWilliams. Mr. McWilliams was qualified as an expert in biology;
wetlands assessments; wetlands mitigation and restoration, including design;
threatened and endangered species assessment; and state wetlands permitting.
(i) Dr. Michael Dennis. Dr. Dennis was qualified as expert in biology, ecology,
threatened and endangered species, and wetland permitting, including mitigation.
(j) Dr. Vincent Scovazzo. Dr. Scovazzo was qualified as a geotechnical expert
in the area of dam design, safety, construction, operation, permitting, and
stability.
(k) Daniel Mendelsohn. Mr. Mendelsohn was qualified as expert in the application
and development of unsteady flow models, including the DAMBRK and FLDWAV models,
and the representation of numerical model output in graphical form, including
computer-generated inundation animations.
(l) Dr. Daniel Fread. Dr. Fread was qualified as an expert in the development
and application of unsteady flow models, the development and application of
the DAMBRK and FLDWAV models, the development and application of the DWOPER
model, and the development and application of the BREACH model.
37. Some of the expert witnesses for TBW and Petitioners
were also fact witnesses. There was no rebuttal testimony offered.
The arbitration hearing terminated on April 9, 2001, after closing
arguments by the parties. The parties submitted their proposed
arbitration awards on April20, 2001, and the arbitration hearing
was deemed closed as of that date pursuant to Guideline 34 of the
American Arbitration Association Environmental Arbitration Guidelines.
38. The 1998 Interlocal Agreement requires that
the arbitration award in this matter be issued no later than 60
days after the beginning of the arbitration final hearing. Sixty
days after the beginning of the final arbitration hearing is May
15, 2001.
Background of the Proposed Reservoir
39. TBW selected the Proposed Reservoir site after
an extensive, multi-disciplinary alternative site analysis that included
the review and comparison from an environmental, land use, engineering
and economic basis of other potential sites in the Hillsborough County
and adjacent areas. Since the Proposed Reservoir purpose was to collect
surface waters from the Hillsborough River/Tampa Bypass Canal and
the Alafia River, potential sites needed to be reasonably close to
these sources in order to reduce pipeline costs and reduce land use
conflicts.
40. The Proposed Reservoir is located in southeastern Hillsborough
County, roughly to the west, northwest of Wendel Avenue and between two riverine
systems, Doe Branch to the east and northeast and Long Flat Creek to the west.
Undeveloped land owned by Hillsborough County is south of and adjacent to the
Proposed Reservoir site.
41. The area selected for the Proposed Reservoir
and the immediately surrounding area is mostly rural in character
and sparsely populated except for approximately 51 residences along
Wendel Avenue near to the Proposed Reservoir. The land for the
Proposed Reservoir is zoned agricultural-rural. This zoning classification
allows for the land to be used for a water reservoir so there is
no rezoning required. There is no zoning designation within Hillsborough
County that has a lower density classification than agricultural-rural.
42. The Proposed Reservoir footprint is designed
to be approximately 1,100 acres in size and is expected to hold
approximately 15 billion gallons of water, at an average water
depth of about 50 feet, when full. Five miles of earthen embankments
are designed to impound the water in the Proposed Reservoir.
43. The earthen embankment is designed to range
between 30 to 65 feet in height based on the existing land surface
elevations on the site, with the higher embankments being in the
northwest corner of the Proposed Reservoir and the lower embankments
being on the southeast corner, near Wendel Avenue. The Proposed
Reservoir is designed to be generally above ground with some portion
of the reservoir storage being provided below the existing land
surface as a result of the excavation of materials needed for the
embankment. The top elevation of the Proposed Reservoir is designed
at 145 (ft) NGVD.
44. A crest road is planned for the top of the
earthen embankment. The design also calls for a perimeter road
at the downstream toe of the embankment adjacent to the perimeter
swale, which is, in turn, adjacent to the earthen embankment.
45. The Proposed Reservoir is designed to be an
off-stream reservoir to store surface waters, and it needs facilities
to transport water to and from the area enclosed by the earthen
embankment. Accordingly, the Joint Application also includes construction
of approximately 8 miles of new 84" pipeline to connect to water
sources and to existing water supply facilities. The pipeline route
begins approximately 400 feet north of the intersection of Fishhawk
Drive, Bell Shoals Road and Boyette Road, and runs south and east
in a proposed easement following the alignment of Boyette Road,
then through rural land to the Proposed Reservoir. The pipeline
is planned to be used for obtaining water for the Proposed Reservoir
from the Hillsborough River, the Alafia River and the Tampa Bypass
Canal. The pipeline will also be used to deliver water to the Tampa
Bay Regional Surface Water Treatment Plant, located in Hillsborough
County north of the Proposed Reservoir, for treatment and ultimate
delivery to member governments.
46. The 84" pipeline is designed to be made from
steel or prestressed concrete pipe for the majority of its length.
The portion of the pipeline under the earthen embankment will be
steel. The 84" pipeline is designed to enter the Proposed Reservoir
in the northwest area of the Proposed Reservoir, will be buried
below the ground surface and the earthen embankment, and is designed
to connect to an intake tower inside the Proposed Reservoir. A
water control structure bridge of approximately 263 feet in length
is designed to be built from the crest road on top of the earthen
embankment to the intake tower. Also buried below ground level
at the same location as the 84" pipeline will be a 42" pipeline.
At the present time, the use of this 42" pipeline has not been
determined.
47. There are ten stormwater ponds associated
with the Proposed Reservoir that are planned to be located adjacent
to and outside of the earthen embankments. Two access roads, one
from the east and one from the west side of the Proposed Reservoir,
are planned as part of the project.
48. A one-story maintenance and office building,
approximately 28 feet by 48 feet, is scheduled to be built near
the intake tower. A separate mechanical building adjacent to this
building may be constructed if necessary to improve water quality
in the future.
49. In addition to the 1,100-acre footprint of
the Proposed Reservoir, the SWFWMD has agreed to acquire 4,700
acres surrounding the footprint to the east, west and north. This
additional acreage is planned to be used for mitigation for wetland
impacts and for other unspecified purposes. The SWFWMD plans to
acquire the necessary property for the Proposed Reservoir and mitigation
areas. TBW will be responsible for the construction, operation
and maintenance of the Proposed Reservoir. TBW plans to construct
the wetlands and other areas that may be necessary for mitigation
purposes and to be responsible for these areas until their vegetative
success has been established. SWFWMD or another similar agency
will then be responsible for the long-term management and maintenance
of the mitigation areas. Issues to be Determined by the Arbitration
Panel
50. As will be discussed more fully in the conclusions
of law section of this arbitration award, TBW has the burden of
proof in this arbitration proceeding" of providing reasonable assurances
that [TBWs] Primary Environmental Permit application meets
all applicable agency rules, policy and statutes." 1998 Interlocal
Agreement, Section 3.13(B). (The "applicable agency rules, policy
and statutes" are referred to in this arbitration award as the "Applicable
Substantive Law.") This is the ultimate issue of law in this arbitration
proceeding.
51. While there are many issues of fact that could
be determined pursuant to a determination of "reasonable assurance" for
a project like the Proposed Reservoir, the parties have narrowed
the issues to be determined by this arbitration through the pleading
and discovery process that preceded the final evidentiary hearing.
Petitioners Initial Statement of Issues dated December12,
2000; Joint Pre-Hearing Stipulation; Proposed Final and Binding
Arbitration Decision filed April 20, 2001 ("Petitioners Proposed
Arbitration Award"); Tampa Bay Waters Proposed Final Arbitration
Award filed April 20, 2001 ("TBWs Proposed Arbitration Award");
and all discovery pleadings. The 1998 Interlocal Agreement envisions
the narrowing of issues in this manner. 1998 Interlocal Agreement,
Appendix N, Rules 1(a)(6) and (7); Rules 1(b)(1), (3), and (5).
Indeed, the arbitration process under the 1998 Interlocal Agreement
requires that member governments raise "issues" to initiate the
arbitration process. 1998 Interlocal Agreement, Section 3.13(A).
52. Accordingly, the following generally stated
issues, as set forth by Petitioners in the Joint Pre-Hearing Stipulation,
remain for factual and legal consideration by the Arbitration Panel:
(1) Whether the Application provides reasonable assurance as to the potential
for adverse water quality impacts to the ground water and surface water in
the vicinity of the reservoir and unacceptable impacts to natural systems and
domestic uses.
(2) Whether the Application provides reasonable assurance as to
the potential for impacts to wetlands outside of the "footprint" of
the reservoir due to leakance from the reservoir and alteration to
the natural hydroperiods.
(3) Whether the plan for mitigation of impacts to wetlands is indefinite
and incomplete, does not consider potential adverse impacts to mitigation
projects from reservoir leakance, and fails to provide the necessary
reasonable assurance the wetlands impacts can be adequately offset.
(4) Whether the Application provides reasonable assurance that
the public health and safety has been adequately protected when the
Application does not:
a. include a dam break analysis, including inundation map, and
the emergency action plan is not complete;
b. address design alternatives to avoid or minimize risks to public
health and safety;
c. is based upon "average" site conditions rather than actual conditions;
d. include design or analysis for emergency or rapid drawdown conditions;
and
e. address impacts to adjacent residences, including potential
impacts to septic fields, domestic wells, and surface drainage.
Joint Pre-Hearing Stipulation, p. 17.
53. This arbitration award deals with these contested
factual issues and makes appropriate factual determinations to be
able to apply the Applicable Substantive Law to these factual issues.
All other facts in connection with the Proposed Reservoir that are
not necessary in the determination of the remaining factual and legal
issues are not subject to arbitration, and a "reasonable assurance" evaluation
has not been made as to whether those facts comply with the Applicable
Substantive Law.
Issue 1
Water Quality Compliance
Issue 1: Whether the Application provides reasonable assurance
as to the potential for adverse water quality impacts to the ground
water and surface water in the vicinity of the reservoir and unacceptable
impacts to natural systems and domestic uses.
54. There is general agreement between the parties
that the hydraulic head created by the water to be stored within
the Proposed Reservoir will cause a hydrologic mechanism known as "seepage" i.e.,
some of the water, identified as "leakance," will migrate through
the embankment and underlying soils, a process called "flux," into
the aquifers underlying and surrounding the Proposed Reservoir, as
well as the surrounding surface waters. Disagreement arises over
whether the leakance would cause adverse impacts that violate Applicable
Law, either as to water quality or water quantity. Petitioners first
issue concerns water quality impacts. Their second and third issues
address water quantity impacts.
55. The specific concerns raised here by Petitioners
relate to the likelihood that TBW will use algaecides or other
chemicals to protect TBWs use of the water being stored within
the Proposed Reservoir. TBW acknowledges the need to use water
quality control measures within the Proposed Reservoir, but states
that such measures are still being developed and will be calibrated
with actual reservoir water quality upon filling the Proposed Reservoir.
Therefore, the Joint Application contains no final determination
as to the type or quantity of chemicals that may be used.
56. The chemical of particular concern to Petitioners
is copper sulfate, which the Joint Application acknowledges may
be used in the Proposed Reservoir. Copper sulfate is a common chemical
compound that is applied in lakes, streams and reservoirs throughout
the United States for the purposes of killing algae in the water
column.
57. Because it is still considering how to undertake
these water quality measures, TBW presented no evidence as to application
rates, method of application, spill control, type of equipment
to be used for applications, or any other information regarding
the use of copper sulfate. The parties appear to agree, however,
that effective usage will require many tons of the chemical.
58. The Arbitration Panel concurs with expert
witnesses from both parties to the extent that they agree that
the copper in copper sulfate becomes bound in sediments at the
bottom of water bodies, particularly where the sediments and soils
contain organics, clays and silts. Such a process would be applicable
to the bottom of the Proposed Reservoir.
59. Where the experts disagree is over the fate
of the copper after it becomes bound. Petitioners assert that where
extremely large amounts of copper are used, some of it will go
back into solution at or near the bottom of the reservoir, where
it will be available for transport.
60. The FDEP has adopted surface water quality
standards for copper, which can be found in Rule 62-302.530, F.A.C.
Copper is a groundwater standard pursuant to Rule 62-520.420, F.A.C.,
which incorporates by reference Rule 62-550.320, Table 4, Secondary
Drinking Water Standards.
61. Copper in its soluble form is toxic to low-level
plant and animal life. If copper in soluble form were to reach
wetlands outside the Proposed Reservoir at certain low levels of
concentration, it can be toxic to the ecology and disrupt the entire
food chain.
62. The Wendel Avenue residents obtain their drinking
water from private wells. The potential for leakants containing
copper of moving from the Proposed Reservoir to groundwater underlying
those wells, therefore, should be monitored to confirm that the
leakants will not result in the residents having copper in their
drinking water that exceed the secondary standard level.
63. TBW has not conducted any analysis of fate
and transport of chemicals or contaminants out of the Proposed
Reservoir. Petitioners, however, presented no testimony that copper
could reasonably be expected to migrate from the Proposed Reservoir
or otherwise impact the surface waters or groundwater.
64. While Petitioners presented evidence that
copper may return to soluble form under certain circumstances,
Petitioners presented no evidence that, even assuming the soluble
copper could travel through the reservoir bottom, such transport
would reasonably be expected to cause a violation of water quality
standards for copper in surface water or groundwater outside of
the Proposed Reservoir, or even that the soluble copper would exceed
such standards within the Proposed Reservoir prior to such transport.
65. Witnesses for both parties discussed a monograph
entitled "Aquatic Use of Copper-Based Herbicides in Florida," (Fla.
Dept. of Natural Resources 1990). (Pet. Ex. 104) The monograph
expresses concerns that excessive use of copper sulfate could have
adverse downstream water quality impacts for copper, but did not
address closed reservoir situations such as the Proposed Reservoir,
did not discuss possible groundwater transport, and did not recommend
elimination of copper sulfate as an algaecide in drinking water
reservoirs.
66. Petitioners have not placed at issue in this
proceeding the need for TBW to comply with water quality standards
for copper within the Proposed Reservoir pool. While Petitioners
provided no persuasive proof that leakance from the Proposed Reservoir
would cause water quality violations outside the reservoir embankment,
the testimony indicates that water quality problems may occur at
some point if the usage of copper sulfate is completely unregulated.
This is illustrated by testimony of witnesses from both sides expressing
concern over potential adverse impacts associated with usage of
unspecified numbers of "dump trucks" of the algaecide.
67. TBW responds to concerns regarding uncontrolled
use of algaecides by pointing to AppendixK, Section 2.4 of the
Joint Application, which states, "The water quality control measure
utilized in the reservoir management will be permitted through
the Hillsborough County Health Department Source Water Permit." However,
there is no evidence as to the scope of such permit i.e.,
what specific "measure" would be permitted, what does the permit
regulate, does it address potential offsite water quality concerns,
or whatever. Therefore, the Arbitration Panel is unable to determine
the relevance of this permitting scheme to whether the Joint Application
complies with Applicable Substantive Law.
68. The evidence shows that copper sulfate is
reasonably likely to be bound up in soils within the footprint
of the Proposed Reservoir, and no persuasive evidence has been
presented to the Arbitration Panel that soluble copper may be transported
by leakance from the Proposed Reservoir to adjacent groundwater
or surface water in levels that violate applicable state water
quality standards.
69. Nonetheless, given the lack of information
with regard to how the application of copper sulfate will be regulated,
the Panel finds that it would be prudent for TBW to monitor the
groundwater adjacent to the embankment of the Proposed Reservoir
to determine whether the applications are causing an increase in
copper at levels that would appear to indicate that water quality
standards might be violated in the future.
70. Particular areas of concern for monitoring
are wetlands adjacent to the Proposed Reservoir and the Wendel
Avenue neighborhood. The wetland areas are appropriate because
of the potential impacts of water quality violations on the wetland
systems. The Wendel Avenue neighborhood monitoring is appropriate
because of the residents use of groundwater for drinking
water.
71. TBW has already acknowledged in the Joint
Application its commitment to monitor for water quality and water
levels at various locations around the site of the Proposed Reservoir,
including specifically the Wendel Avenue area. Monitoring wells
will be installed as part of TBWs monitoring and maintenance
plan for leakance, and will be designed to look at both water quality
and water levels. The Arbitration Panel finds that the water quality
monitoring plan should specifically include monitoring for copper.
Since TBW has already committed to implement monitoring in these
location, the Arbitration Panel does not consider it necessary
that the copper monitoring be included as a specific amendment
to the Joint Application.
72. Petitioners have not placed at issue the adequacy
of TBWs water quality monitoring plans for chemicals other
than copper, or for monitoring other potential pollution-causing
constituents in the waters of the Proposed Reservoir, whether added
by TBW or coming from elsewhere, such as from the source waters
for the Proposed Reservoir. Therefore, the Arbitration Panels
findings on copper is not intended as a determination of what should
be the scope of the water quality monitoring plan proposed by TBW
in its Joint Application, only what must be included in the plan
as a result of this arbitration award.
73. On page 43 of Petitioners Proposed Arbitration
Award, under the headings of "Wendel Avenue" and "Water Quality," Petitioners
state their proposals for what should be ordered by the Arbitration
Panel as the part of this arbitration award relating to the water
quality issues. These proposals include a detailed assessment of
the potential impacts of seepage on the Wendel Avenue residents,
avoidance and contingency plans for such impacts, preparation of
models that predict the fate and transport of herbicides and algaecides
that may be used within the Proposed Reservoir, and the implementation
of measures to prevent adverse impacts to water quality or fish
and wildlife.
74. Given the lack of evidence that water quality
exceedences are reasonably expected to occur from copper-containing
leakance outside of the Proposed Reservoir, the Arbitration Panel
rejects these recommendations as being unnecessary amendments to
the Joint Application.
Issues 2 and 3
Water Quantity Monitoring and Management
Issue 2: Whether the Application provides reasonable assurance
as to the potential for impacts to wetlands outside of the "footprint" of
the reservoir due to leakance from the reservoir and alteration
to the natural hydroperiods.
Issue 3: Whether the plan for mitigation of impacts to
wetlands is indefinite and incomplete, does not consider potential
adverse impacts to mitigation projects from reservoir leakance,
and fails to provide the necessary reasonable assurance the wetlands
impacts can be adequately offset.
75. Petitioners have asserted that adverse impacts
may occur to offsite wetlands and the property of others as the result
of changes in water quantity caused by construction and operation
of the Proposed Reservoir. Petitioners question whether TBWs
modeling of the potential extent of such impacts, as well as TBWs
proposals to monitor for and manage any impacts that may be adverse,
comply with Applicable Substantive Law. Since the two issues quoted
above both relate specifically to Petitioners concerns over
impacts resulting from changes in water quantity, the Arbitration
Panel will consider the issues together.
76. In Petitioners Proposed Arbitration
Award, Petitioners restated their concerns in a somewhat different
manner, as follows:
Issue 2: Whether the Application provides reasonable assurance that adverse
water quantity impacts to wetlands outside of the "footprint" of the reservoir
will not occur due to the anticipated alteration of the natural hydroperiods
resulting from continuous seepage out of the reservoir;
Issue 3: Whether the proposal as detailed in the Application
for monitoring and management of impacts to wetlands due to seepage
provides reasonable assurance that adverse impacts to existing
wetlands, streams and proposed mitigation projects can be adequately
detected and avoided or offset before adverse impacts occur and
is capable, based on generally accepted engineering and scientific
principles, of being effectively performed and of functioning as
proposed;
77. The difference between the two statements
of the issues appears in their differing treatment of the issue of
mitigation. In their pre-hearing stipulation statement of the issues,
Petitioners raise objections about the adequacy of TBWs mitigation
plans in general. In the later version, Petitioners focus on their
concerns as they specifically relate to seepagei.e., on the
adequacy of the mitigation plans because of the effects that seepage
may have on the implementation of such plans. Because the argument
of Petitioners has been made more specific, and because issue narrowing
has been a recognized part of this arbitration proceeding, the Arbitration
Panel will treat Petitioners mitigation concerns as being specifically
related to the leakance issuei.e., whether the leakance impacts
are adequately addressed in mitigation plans for areas that would
reasonably be expected to be impacted by the leakance.
78. The parties are in general agreement on a
number of matters relating to these issues. As previously stated
in the Arbitration Panels discussion of Issue 1, the parties
agree that the hydraulic head created by the water to be stored
within the Proposed Reservoir will cause leakance into the aquifers
underlying and surrounding the Proposed Reservoir, as well as the
surrounding surface waters.
79. The parties agree that construction of the
Proposed Reservoir will affect the amount of surface water that
would otherwise flow from the footprint to adjacent wetlands, because
1,100 acres will be removed from the project areas drainage
systems. The elimination of both wetlands drainage and stormwater
runoff from the area within the Proposed Reservoir will result
in at least some decrease in the amount of surface water reaching
property adjacent to the Proposed Reservoir.
80. The parties agree that there will be an elevation
of water tables as the result of construction and operation of
the Proposed Reservoir, at least in some locations outside of the
reservoir embankment, the extent of which is affected by a number
of factors, including accuracy of modeling, reservoir operations,
actual field conditions and the effectiveness of implementation
of management strategies directed towards lowering the water table.
81. The parties agree that construction and operation
of the Proposed Reservoir, therefore, will affect the hydrologic
regime in the area of the Proposed Reservoir, both as to timing
of the existing hydroperiod and as to the quantity of water being
delivered, stored and removed from the affected area. Because these
hydrologic changes have the potential to cause adverse impacts
upon adjacent wetlands and the property of others, the parties
further agree that it is appropriate to consider under Applicable
Substantive Law whether TBW has provided reasonable assurance in
the Joint Application that measures it has proposed to address
these potential adverse impacts comply with Applicable Substantive
Law, both as to evaluating the extent of potential impacts and
as to establishing effective measures to avoid or mitigate for
any impacts that may be adversei.e., that may cause a violation
of Applicable Substantive Law.
82. Where the parties disagree is over the degree
of hydrologic change the Proposed Reservoir is expected to create,
the adequacy of TBWs evaluation of potential impacts associated
with the change, and the sufficiency of TBWs proposals for
preventing or compensating for any impacts that may be adverse.
While TBW has proposed a management program, discussed below, that
is designed to address potential adverse impacts associated with
the hydrologic changes, the Arbitration Panel finds it necessary
first to understand the potential scope of the changes before considering
the adequacy of the management plan.
Calculating the Water Quantity Changes
83. The disagreement between the parties begins
with a difference in how to calculate the total increase in water
quantity that is reasonably expected to occur as the result of seepage
from the water. That disagreement, in turn, starts off with the parties usage
of two different mathematical models to calculate the seepage.
84. Dr. Stewart testified on behalf of TBW. Dr.
Stewart had originally intended to use a model called MODFLOW,
a numerical three-dimensional model used by the United States Geological
Service to evaluate groundwater hydrology. Because of the complexities
of the embankment design, including the geomembrane and soil cement
liners, water table levels within the embankment, the drainage
system and the cutoff slurry wall, Dr. Stewart concluded that the
MODFLOW model, while a "good model," was too restrictive to address
these complexities.
85. Dr. Stewart decided instead to use a SEEP/W
model. The model is two dimensional and used for two-dimensional
problems such as determining flow from dams and embankments. Its
principal use here was to determine the amount of flow of water
from the Proposed Reservoir to the underlying and adjacent aquifers
("fluxes"). The model is not designed to predict changes in elevations
in the water table that might be caused by such fluxes. Dr. Stewart
felt that the MODFLOW model would not be useful in predicting such
movement here because the field data was not sufficient to enable
the model to factor in the effects of variables such as evapotranspiration
(taking water out) and recharge (putting other water in).
86. Dr. Stewart used several conservative input
parameters in running the SEEP/W model, assuming (1) a full reservoir
pool at all times, (2) no sedimentary buildup in the reservoir
bottom, (3) imperfect slurry wall construction, and (4) no capture
of leakance by the creek systems outside of the Proposed Reservoir.
These inputs are conservative because TBW estimates that the Proposed
Reservoir will only be full approximately 15 percent of the time,
that sedimentary buildup will occur over time, that the slurry
wall should operate as designed, and that the creek systems, as
well as the drainage system (toe drains, swales and stormwater
ponds) around the reservoir embankment, will capture some of the
leakance.
87. Based upon the SEEP/W model calculations,
which came up with a range of numbers, Dr. Stewart estimated that
there would most likely be approximately four million gallons per
day (mgd) of leakance given the above-noted input parameters. Approximately
2.5 mgd would go out under the Proposed Reservoir embankment, with
the remainder going straight down to the Floridan Aquifer. Of the
2.5 mgd that would go out, approximately one mgd would move up
and discharge at the water table, with the remainder moving away
from the embankment, eventually going down and recharging the Floridan
Aquifer.
88. Under the SEEP/W model, it would be hard to
predict the actual impact of one mgd in elevating the water table
given the model limitations, the existence of the adjacent creek
systems, the effects of evapotranspiration and recharge, varying
geology (including hydraulic conductivity) around the site, and
the fact that the Proposed Reservoirs pool levels will vary.
This also makes it difficult to predict the lateral reach of the
water table rise. Dr. Stewart estimated that the flux from the
Proposed Reservoir could reasonably be expected to cause a foot
or more of rise for approximately 400-600 feet away from the embankment.
For the first 100-200 feet, the flux would be sufficient to cause
a rise to the surface at some period of the year. Dr. Stewart did
not take into consideration potential impacts of lateral flow induced
by changes in elevation. Furthermore, Dr. Stewart could not be
sure of the full lateral reach of the water table rise, particularly
beyond 600 feet, given that the SEEP/W model does not calculate
the effect that movement of the flux would have in changing water
table elevation, which remains constanti.e., a "boundary
condition"under the model.
89. Petitioners witness, Dr. Anderson, calculated
seepage and "push up" (the upward movement of water outside of
the reservoir footprint caused by the seepage) using the MODFLOW
model, and also evaluated Dr. Stewarts use of the SEEP/W
model. Dr. Anderson was critical of the SEEP/W model for not adequately
analyzing off-site impacts of seepage, and especially for considering
water table levels as remaining constant. He asserted that the
effect of the models application was to disregard the impacts
of push up, particularly beyond the 600 or so foot area immediately
outside the embankment.
90. Dr. Anderson used the MODFLOW model to calculate
the total amount of seepage, using the same set of "conservative
input parameters" as did Dr. Stewart. In so doing, Dr. Anderson
also applied Darcys Law, which is a formula used to calculate
how water levels will change based upon hydraulic conductivity
or permeability and changes along the flow path, the basic assumption
being that an increase in flow will cause a water table rise. Dr.
Andersons modeling efforts were specifically directed towards
looking at water table rise.
91. Dr. Andersons modeling efforts showed
possible ranges in the total amount of seepage from the Proposed
Reservoir of between two and eight mgd, and he concluded that four
mgd would be the most likely number. With regard to the lateral
extent of push up from the Proposed Reservoir, Dr. Anderson concluded
that the one foot push up linei.e., the point at which the
water table would rise by no more than one foot as the result of
leakance from a full pool reservoirwould be between 4,000
to 5,000 feet from the reservoir embankment.
92. While the two experts challenged the conclusions
generated from the models each other preferred, they both did agree
that there would be approximately four mgd of leakance from the
Proposed Reservoir, and that approximately 2.5 mgd of that leakance
would move laterally away from the embankment. The difference was
in how much of the
2.5 mgd would go up or down. Dr. Anderson concluded that there would be approximately
two mgd moving upward outside the footprint of the Proposed Reservoir, whereas
Dr. Stewart estimated the amount to be closer to one mgd.
93. The two experts also both recognized the limitations
of their own models. As Dr. Anderson acknowledged, all models are
a "simplification of the natural system." In the words of Dr. Stewart, "Mathematical
models by definition are simplifications." The experts both recognized
that the models do not look at the impacts of evapotranspiration
or topography, and that the only real way to determine the extent
of leakance and push up is to build the Proposed Reservoir and
fill it with water. The Arbitration Panel finds the opinions of
both Dr. Stewart and Dr. Anderson to be credible, and accepts their
conclusions that estimate leakance of around 4 mgd, which the Arbitration
Panel finds to be a reasonable number to expect when the Proposed
Reservoir is at full pool; and estimate about 2.5 mgd of that leakance
to move laterally away from the footprint of the Proposed Reservoir,
which the Arbitration Panel also finds to be a reasonable number.
94. The Arbitration Panel recognizes that in large
part the conclusions differ as to how much of the 2.5 mgd will
result in an alteration of the water table adjacent to the Proposed
Reservoir, because the two models are looking at two different
impactsthe SEEP/W model primarily at flux, and the MODFLOW
model primarily at push up. As a result, the Arbitration Panel
anticipates that the SEEP/W model is likely to underestimate push
up, and the MODFLOW model to overestimate it. Particularly given
the experts own acknowledgment of the limitations in the
models that they prefer to use, the Arbitration Panel finds, therefore,
that it is reasonable to anticipate that leakance at full pool
will cause between one and two mgd of leakance reasonably likely
to move upwards and thereby cause push up outside of the embankment
of the Proposed Reservoir.
95. With regard to the horizontal and vertical
extent of water table rise caused by the leakance, the experts
disagree most significantly on the extent of impact beyond 600
feet. Since Dr. Stewart conceded that the SEEP/W model was not
intended to calculate water table rise, and since the Arbitration
Panel has determined that the total amount of push up may be up
to twice the amount calculated by Dr. Stewart, the Arbitration
Panel finds it reasonable to take into consideration, for the purposes
of developing monitoring and management plans, potential water
table rise up to 4,000 feet away from the reservoir footprint,
with the amount of push up increasing closer to the embankment.
96. The Arbitration Panel does not intend consideration
of the 4,000-foot distance to constitute a finding that adverse
impacts are reasonably expected to occur up to 4,000 feet away,
or even that there will be push up of one foot up to 1,000 feet
away. Rather, this distance should be the outer limit of the areas
being studied by TBW as part of its monitoring plan, and addressed
if necessary if the monitoring shows that adverse impacts would
reasonably be expected to occur without management plan implementation.
97. Furthermore, the Arbitration Panel recognizes
these distances and depths to be estimations, given the limitations
of the mathematical models. Notwithstanding the Arbitration Panels
acceptance of Dr. Andersons horizontal and vertical calculations
of leakance impacts for the purposes of consideration in a management
plan, the Arbitration Panel would expect the true numbers to be
substantially less, once the Proposed Reservoir is constructed
and TBWs monitoring and management plans implemented.
98. Factors influencing what those true numbers
would be include variations in pool levels, topography, weather
conditions affecting evapotranspiration and water table depths,
hydraulic conductivity at various locations around the embankment,
slurry wall construction, sedimentary buildup in the reservoir
bottom, and other circumstances both contemplated and unexpected.
Given that these variables are at this point unpredictable, however,
and also are likely to have substantially different effects at
different locations throughout the property surrounding the footprint
of the Proposed Reservoir, the Arbitration Panel finds it prudent
that the more conservative assumptions of Dr. Anderson be used
at least for the purposes of determining how large an area should
be considered as part of the monitoring and management plans discussed
below.
99. As previously noted, calculating the true
impact of the Proposed Reservoir on adjacent property outside of
its footprint is further complicated by the fact that its construction
will eliminate a significant amount of surface water currently
flowing onto the adjacent property from the 1,100-acre area within
the reservoir embankment. These impacts take water out of the system
rather than add to it.
100. The Petitioners have not disputed TBWs
calculations of how much reduction will occur in surface water
flows as a result of elimination of drainage from the 1,100-acre
reservoir site. According to Mr. Meyer, there would be a net reduction
of 230 cubic feet per second in stormwater runoff into adjacent
streams as a result of the capture of that stormwater within the
embankment of the Proposed Reservoir. According to calculations
in the Joint Application, the net difference to the ground/surface
water system would be between 0.5 and one mgd. While the surface
water numbers are not disputed, the net difference is disputed,
since the difference would be greater assuming the accuracy of
Dr. Andersons calculations. The environmental effects of
the net difference would also be impacted by the fact that because
so much of the surface water flow comes from stormwater, and the
amount of seepage will vary depending upon the pool levels within
the Proposed Reservoir, the net difference will vary over time.
101. In the final analysis, the true impacts of
groundwater and surface water changes can only be fully calculated
and understood once the Proposed Reservoir is constructed and placed
into operation. Whatever the impacts ultimately prove to be, the
Arbitration Panel finds that there will be leakance from water
stored within the footprint of the Proposed Reservoir, the groundwater
flow of the leakance will cause push up in areas surrounding the
footprint, and elimination of surface water runoff from within
the footprint will result in some reduction in the total amount
of water thereby exiting the Proposed Reservoir and impacting adjacent
wetlands and the property of others. Given the large volume of
water to be stored in the Proposed Reservoir, the amount of water
being added is of sufficient quantity, and the existing hydroperiod
is being sufficiently changed, that without adequate monitoring
and management, adverse impacts are reasonably likely to occur
to receiving waters and adjacent lands. These potential impacts
are substantial enough so as to require that the Joint Application
be evaluated to determine whether TBWs plans to monitor for
and manage these impacts are detailed enough to comply with Applicable
Substantive Law.
102. Furthermore, these impacts need to be evaluated
without assuming they will be offset by a successful management
plan. As explained more fully below, in order to review the scope
and effectiveness of such a management plan, it is first necessary
to establish baseline data.
Assessing Potential Impacts from the Water
Quantity Changes
103. In order to evaluate fully the potential
impacts of the Proposed Reservoir resulting from changes in water
quantity upon adjacent wetlands and the property of others, without
assuming that such impacts will be offset by a management plan, the
first step is to evaluate existing conditions.
104. The parties have identified two wetland systems
that may be adversely impacted by water quantity changes. Immediately
adjacent to the western, eastern and northern boundaries of the
Proposed Reservoir are two riverine, hardwood wetland systems that
extend to within one to two hundred feet of the toe of the embankment:
Long Flat Creek and Doe Branch. Other adjacent natural areas include
improved pasture and upland scrubby flatwoods.
105. Doe Branch supports a mixed canopy of laurel
oak, sweet bay, cabbage palm, and an understory of flowering dogwood
and dahoon holly, with sparse amounts of catbriar and leaf litter
as groundcover. Long Flat Creek generally supports a canopy dominated
by red maple, laurel oak, sweet gum, sweet bay, and cabbage palm.
Wetter areas also support cypress, black gum and Carolina ash.
Groundcover consists of numerous weedy species in addition to Virginia
chain fern, cinnamon fern, netted chain fern, and in wetter areas
lizard tail. All of these species are typical of riverine swamp
and are adapted to temporary to seasonal inundation.
106. Petitioners have also identified as an area
of potential concern the East Pruitt mitigation site. The East
Pruitt property is among the 4,700 acres identified by Petitioners
for acquisition by SWFWMD as part of the mitigation plan for offsetting
the impacts of elimination of wetlands within the footprint of
the Proposed Reservoir and other wetlands being eliminated as part
of reservoir construction activities. The East Pruitt area is located
immediately adjacent to the northwestern edge of the Proposed Reservoir
boundary, and includes within it portions of Doe Branch. TBW has
acknowledged that seepage from the Proposed Reservoir may impact
areas being considered for development as mitigation sites within
the East Pruitt area.
107. Petitioners other area of concern is
the Wendel Avenue neighborhood. Petitioners are concerned that
seepage may adversely affect wells and septic tanks because of
the impacts of changes caused by the seepage in both water quality
(as discussed in Issue 1) and water quantity (from water table
rise).
108. In the Joint Application at Appendix D, Section
5.3, TBW recognizes that potential adverse effects could occur
to the two adjacent wetland systems as a result of seepage from
the Proposed Reservoir. TBW acknowledges, "The exact response of
the aquifer as well as the adjacent environment must be monitored
so that appropriate management strategies can be implemented prior
to the manifestation of any adverse effects. The monitoring protocol
and management strategies will provide reasonable assurances that
adverse environmental effects do not occur as a result of the project."
109. Appendix D refers to Appendix H for an "outline" of
the proposed monitoring program. Appendix H, in turn, at Section
4.6, states that "a monitoring program will be implemented by [TBW]
to assess subsurface groundwater conditions before, during and
after filling of the reservoir." The monitoring program will consist
of a "network of piezometers located along the perimeter of the
reservoir and near the adjacent streams." The program would use
both existing monitoring wells and wells not yet identified.
110. Mr. Eliason testified on behalf of TBW regarding
its efforts to assess wetland impacts associated with construction
and operation of the Proposed Reservoir. Mr. Eliason testified
that TBW has not quantified potential impacts because the modeling
numbers assumed an unlikely worst case scenario and because TBW
is planning to use a management plan to avoid adverse impacts altogether.
111. TBW asserts that it is seeking not to avoid
any impacts from the hydrologic changes caused by the Proposed
Reservoir, but to avoid any adverse impacts. TBW intends to accomplish
this through monitoring the existing wetland regime so that indicators
of stress can be identified prior to irreparable damage occurring,
and through manipulating groundwater levels by pumping to relieve
the stress prior to such damage. In Mr. Eliasons words, "The
goal of the monitoring and management plan is not to mimic the
natural fluctuations in that water table . . . [, but] to manage
for adverse impacts."
112. The monitoring plan proposed by TBW to FDEP
would involve the location of additional wells to those already
identified in the Joint Application, the setting of vegetation
transects at strategic locations along the creek beds to look for
stress, and the use of color infrared aerial photography to evaluate
the spread of moisture in the soils from leakance.
113. TBWs proposal does not lay out specific
details of a monitoring or management strategy. Rather, the plans
are "conceptual" only, with details to be worked out with FDEP
during the permit application process. Mr. Eliason testified that
TBW had gathered the information necessary with regard to groundwater
monitoring and infrared photography to put a more specific plan
together, and that transects were in the process of being performed
and should be completed shortly. The information has yet to be
included within the Joint Application, however.
114. Therefore, there is no information in the
Joint Application that would enable quantification of the extent
of potential damage to the wetlands surrounding the Proposed Reservoir
assuming an "unmanaged" scenarioi.e., no implementation of
a management plan designed to prevent any adverse impacts. Nor
is such a quantification available assuming a "mismanaged" scenarioi.e.,
unsuccessful implementation of the management plan.
115. Hydrologic changes can cause stress to occur
in wetland species that may not be detectable until substantial
adverse impacts have already occurred. While the management plan
relies upon stress indicators to trigger corrective action, the
monitoring plan does not clearly define when stress results in
an unacceptable adverse impact. To the extent, therefore, that
a monitoring plan relies upon stress indicators, those indicators
must be clearly identified in order for the plan to be reviewable
for compliance with Applicable Substantive Law.
116. Because the monitoring and management plans
are only "conceptual" in nature at this point in the proceedings,
and because TBW has not made any effort either to identify or to
quantify potential adverse impacts in the event the management
plan does not prove effective, the Joint Application does not currently
meet the reasonable assurance test for compliance with Applicable
Substantive Law.
117. The Panel finds that TBW has established
a reasonable conceptual basis for monitoring and management plans,
and therefore does not consider the Proposed Reservoir at this
point in the proceedings to be unpermittable. But the Joint Application
as presented to the Panel is incomplete. As Mr. Eliason acknowledged,
the Joint Application is not at this point in time a "permittable
document," even though the project itself may be permittable, because
the monitoring and management plans have not been fully developed.
118. This acknowledgment is also contained in
the text of the Joint Application. Appendix D, Sections 5.3.1&2,
states that details of the monitoring plan have "not yet been fully
developed," and that specific criteria for unacceptable changes
that need to be addressed "will be developed during the permitting
process through coordination with regulatory agencies."
119. The Joint Application in its current state
is incomplete because it lacks sufficient detail for a determination
of whether potential adverse impacts from leakance have been appropriately
and accurately identified. In order to overcome this incompleteness,
TBW must provide in the Joint Application a delineation of the
wetland system and its supporting hydrologic regime with enough
specificity so that the full extent of potential adverse impacts
can be determined, for three reasons:
(a) To establish a baseline so that the potential for adverse impacts to occur
can be fully measured;
(b) To assist in the development of a management plan, by identifying specifically
the wetlands to be protected, the hydroperiod needed to maintain these wetlands
with the same level of protection, and the types of strategies that can be
utilized to accomplish the protection; and
(c) To provide a basis for the establishment of a backup mitigation plan in
the event that the management plan proves unsuccessful in whole or part.
120. To help determine potential impacts and evaluate possible
remedial measures, the delineation should take into consideration the wetland
species, topography, soils and geology of the area. One way to accomplish this
was illustrated by Dr. Dennis, who performed a series of surveys of transects
into the wetland systems adjacent to the Proposed Reservoir. Dr. Dennis transects
point out that the wetland system potentially impacted has seepage slopes that
require careful attention in any management plan if adverse impacts are to
be avoided.
121. The Joint Application is also insufficient
because the East Pruitt mitigation plan has not yet been developed.
Here the baseline would be established through development of a
plan with sufficient detail to know where the mitigation area or
areas will be located, how large they will be, and what they will
consist of in the way of type, nature and function of the wetland
systems to be created, enhanced or protected. Without such detail
there is no way to determine how a management plan would be protective
of these mitigation areas.
122. Mr. Eliason indicated that TBW has gathered
enough historical information over the last 20 years, to make a
determination of what groundwater levels should be included in
the Joint Application as establishing how adverse impacts can be
avoided. TBW has not yet included this type of information in its
Joint Application, however, and those levels need to be included
because they are an important component of the reasonable assurance
criteria. Similarly, the Joint Application should include information
regarding transects of wetlands vegetation that TBW has already
undertaken.
123. A management plan alone cannot suffice for
establishing baseline conditions. While monitoring for stress may
be an appropriate component to a management plan that relies on
groundwater manipulation to avoid adverse impacts, such monitoring
is insufficient by itself. It is critically important to have a
detailed description in the monitoring plan as to how stress indicators
are determined and which ones are acceptable, since adverse impacts
may have already occurred prior to corrective action being able
to be undertaken.
124. TBW has already indicated both its commitment
to and the necessity of undertaking a monitoring program, as indicated
by Section 5.3.1. of Appendix D to the Joint Application. TBW recognizes
that elements of the monitoring program must include "[t]ransects
[to] be established in the hardwood floodplains of both Long Flat
Creek and Doe Branch for the collection of data related to tree
health, reproductive state, and growth. Herbaceous and shrub cover
will be evaluated for composition and distribution within the floodplain
as well as qualitative assessments of plant health." The monitoring
plan must also identify groundwater levels and hydroperiod, since
the goal of the plan, as TBW acknowledges, "is to detect changes
in surficial water levels and manage them prior to
the occurrence of any adverse environmental effects."
125. While this commitment sounds appropriate
as a conceptual description of what TBW should include in a Joint
Application, the commitment needs to be implemented to establish
reasonable assurance. Given Mr. Eliasons testimony about
the substantial work that has been done and is ongoing at the project
site, and given the quality of the work performed by TBW on the
project to date, TBW should be able to develop a delineation that
will provide sufficient specificity to meet the reasonable assurance
test.
126. TBW has asserted that there may be impacts
not adverse to the wetland systems that nonetheless alter their
character in some way. All wetland systems are not the same, however,
and the natural community here has adapted to the system as it
currently exists. If the system changes, the burden would be on
TBW to show that the new system would not constitute an adverse
impact. This cannot be done without a baseline evaluation of the
current wetland system.
127. In addition, the Joint Application should
include a quantification of stream flows in Long Flat Creek and
Doe Branch, so that the potential impacts from seepage and surface
water runoff can be evaluated and managed together.
Managing Adverse Water Quantity Impacts
128. Petitioners have criticized TBWs management
plan because TBW has not identified with sufficient detail the number
of extraction wells needed, the location and spacing of the wells,
or the precise levels at which groundwater must be maintained in
order to avoid adverse impacts. TBW, in turn, asserts that such information
should be developed subsequent to permit issuance and project construction,
because existing leakance predictions are unrealistically conservative
and cannot accurately predict the location or amount of anticipated
leakance. Once the filling of the Proposed Reservoir begins, TBW
would then have an ability to respond to actual conditions and to
efficiently calibrate the system at the locations and in consideration
of the amounts of leakance which actually occur .
129. Petitioners criticisms have merit.
The management plan does not have specific extraction well locations,
pumping rates, water table levels to achieve, or hydroperiods to
maintain. This does not mean that every detail of a management
plan must be carved in stone prior to permit issuance. The Arbitration
Panel finds that the project can meet the reasonable assurances
standard even though TBW defers much of the management plan details
until after permit issuance and commencement of reservoir operation,
provided the agencies have sufficient information to impose conditions
that will ensure a management plan that meets the reasonable assurance
test. This can be accomplished provided that TBW has already established
baseline conditions through a detailed delineation of the wetland
system as described herein. Only then would the permitting agencies
be able to evaluate whether in fact the impacts from the Proposed
Reservoir would be adverse or not.
130. Nonetheless, TBW has not provided sufficient
information on its management plan to explain how it will control
leakance. At this time, therefore, TBW has not provided reasonable
assurance that its management plan is sufficient to offset adverse
impacts from push up. The Arbitration Panel agrees with TBW that
it is too soon to provide a final, detailed management plan since
the exact amount and location of leakance cannot be presently predicted
given a number of factors previously discussed. But this uncertainty
does not mean that specific information should not be provided
at this time to assure that the components of the management plan
are effective at controlling the expected leakance. Such a plan
should indicate the types of wells to be used to maintain those
levels, the capacity of such wells to reduce leakance in terms
of time and space, historical information on how similar strategies
have performed in the past, and the proposed placement of those
wells given potential leakance to a distance of 4,000 feet from
the Proposed Reservoir footprint. The precise locations, depths
and types of wells to be used at the various areas around the Proposed
Reservoir need not be shown, since that will be determined according
to baseline and actual site conditions after the Proposed Reservoir
is built.
131. A greater degree of specificity can also
be used to develop a mitigation plan to address potential adverse
impacts that cannot be avoided through the maintenance plan. The
monitoring and maintenance plans must have a level of detail sufficient
to enable the permitting agencies to assess the extent of adverse
impacts if maintenance is not completely successful, as well as
to be able to formulate as a permit condition a backup plan for
mitigation for any adverse impacts that the management plan is
ineffective in preventing. Because of the difficulties in developing
all of the details of a maintenance plan when not all of the impacts
can be known until construction and operation of the Proposed Reservoir,
TBW must include in its Joint Application a commitment to implement
this backup mitigation plan to compensate for any adverse impacts
that the maintenance plan cannot prevent.
132. The maintenance plan should also be integrated
with the mitigation plans for the East Pruitt area. This requires
first that the East Pruitt mitigation plans must be developed with
sufficient detail so that there is reasonable assurance that the
mitigation can be constructed and maintained successfully. Secondly,
the maintenance plan must be coordinated with the East Pruitt mitigation
plans so that the maintenance plan will not be damaging to and
will in fact protect and enhance the establishment and maintenance
of those mitigation areas.
133. Finally, the maintenance plan should address
potential adverse impacts to residents of the Wendel Avenue neighborhood.
Since the Arbitration Panel has determined that TBW should be prepared
to address potential impacts from water table push up of one foot
or more within 4,000 feet of the reservoir embankment, since at
least some of the homes in the neighborhood are within that distance,
and since the homes use private wells and septic systems, the management
plan should address these considerations. The focus of the maintenance
plan for the Wendel Avenue neighborhood should be to ensure that
no septic tanks or drinking water wells are adversely impacted
by leakance or push up. As previously noted, the Arbitration Panel
rejects Petitioners request that the plan also include extensive
modeling to determine adverse water quality impacts, since the
Panel has found that those are not reasonably expected to occur.
The maintenance plan, instead, should be implemented in a manner
consistent with the Arbitration Panels findings under Issue
1 i.e., that groundwater should be monitored, for both quality
and quantity.
134. In Petitioners Proposed Arbitration
Award, Petitioners ask the Arbitration Panel to require TBW to
make a further and more detailed assessment of the effect of push
up outside the Proposed Reservoir. Since Petitioners have already
done their own assessment, and since the Arbitration Panel finds
that reasonable assurance can be met if TBWs monitoring and
maintenance plan assumes as an outside limit the assessment contained
in Petitioners modeling efforts as presented at hearing in
this case, the Arbitration Panel sees no need for TBW to do further
modeling as part of the permit application. If TBW prefers not
to incorporate Petitioners modeling into TBWs own monitoring
plan, however, the Arbitration Panel finds that it would be acceptable
for TBW to propose its own additional modeling, provided the modeling
takes into consideration the vertical and horizontal extent of
push up.
135. In Petitioners Proposed Arbitration
Award, Petitioners also ask the Arbitration Panel to provide more
complete responses to RAI Nos. 2, 5, and 9. These RAIs appear to
be asking for more information regarding the adequacy of the mitigation
proposed for wetland impacts within the footprint of the Proposed
Reservoir. The Arbitration Panel finds it difficult to understand
exactly what Petitioners are seeking by this request, but considers
the appropriate response to be that the East Pruitt mitigation
plan needs to be more fully developed for the reasons set forth
herein, but that none of the plans for other mitigation areas proposed
by TBW remain at issue in this proceeding.
Issue 4
Public Health, Safety, and Welfare
Issue 4: Whether the Application provides reasonable assurance
that the public health and safety has been adequately protected
when the Application does not:
a. include a dam break analysis, including inundation map,
and the emergency action plan is not complete;
c. address design alternatives to avoid or minimize risks
to public health and safety;
d. is based upon "average" site conditions rather than
actual conditions;
e. include design or analysis for emergency or rapid drawdown
conditions; and
f. address impacts to septic fields, domestic wells, and
surface drainage.
136. Petitioners take the position that TBW has
not demonstrated reasonable assurance that public health, safety
and welfare will be adequately protected by the Proposed Reservoir.
These concerns are addressed in this arbitration award, first from
the standpoint of embankment design and stability, and then in connection
with dam breach analysis, inundation mapping and the Emergency Action
Plan ("EAP"). Except to the extent that it may be relevant to this
analysis of public health, safety and welfare, potential impacts
to septic tanks, domestic wells, and surface drainage are discussed
in the earlier sections of this arbitration award dealing with water
quantity, quality and leakance.
Embankment Design and Stability
Site Selection and Geologic Analysis
137. Site selection is the first step in designing
a stable embankment. In a project such as the Proposed Reservoir,
it is important to have an understanding of the subsurface structure
because it is a factor in the stability and safety of the embankment.
The results of this type of study may indicate a need for design
changes or the unsuitability of a particular location. Safety of
the Proposed Reservoir has been a major consideration for TBW.
138. One of TBWs original goals was to find
a site outside the urban service area that had already been disturbed
by human activity, and that was in reasonable proximity to a water
supply source, which in this case would be the Hillsborough and
Alafia Rivers. TBW went through an extensive site selection process,
which initially focused on 17 sites, was subsequently reduced to
7 sites, and then to 3 sites before the final site was selected.
139. While densely populated areas were avoided
during site selection for a number of reasons, not all populated
areas could be avoided nor is such avoidance necessary. Other manmade
water supply reservoirs are commonly located in urban or suburban
areas. For example, in places within California, Colorado, Texas,
North Carolina and along the Missouri River, water reservoirs are
located in places within close proximity to populated areas. Also,
in Denver, dams co-exist alongside major infrastructure projects,
including state roads and interstate highways running along the
toe and crest of the reservoirs.
140. As the list of potential sites was narrowed,
TBW began to conduct rudimentary geophysical and geotechnical investigations,
including soil borings. TBW assembled a multi-disciplinary team
of experts for the embankment design facet of the Proposed Reservoir.
The team included experts in civil engineering, geotechnical engineering,
geology, hydrogeology, and hydrology. The embankment design also
included quality assurance provided by expert peer review. 141.
An extensive geophysical and geotechnical analysis was undertaken
to evaluate the site, including "photolineament" analysis of the
substrata and bore holes, to locate features that might indicate
potential for sinkholes or other subsurface features that would
tend to be unstable as a foundation for the earthen embankment
of the Proposed Reservoir. These data also helped refine the geophysical
exploration and supplement the database from which the geologists
ran a sinkhole risk analysis. After the photolineament analysis,
a three-tiered combination of geophysical and geotechnical approaches
was used. The geophysical exploration program included 29 miles
of ground-penetrating radar, 13.6 miles of seismic refraction and
over three miles of seismic reflection. Dr. Upchurch described
this amount of analysis as far more extensive than the typical
analysis. The geotechnical program involved doing soil borings
along 15,000 feet of the site, as well as cone penetrometer tests
and digging trenches to visually inspect the material below grade.
The extensive study was necessary to understand the geology of
the site as a foundation, and the suitability of the materials
in the site for construction of the earthen embankment since the
materials for construction of the embankment will come from the
site.
142. All of these tests, investigations and procedures
culminated in a site characterization report. The site characterization
report, including the results of over one year of geophysical and
geotechnical studies, is an extensive two-volume set comprising
approximately 2,500 pages and is included in the Arbitration Hearing
Evidence. (See Paragraph 6 of the Conclusions of Law for a definition
of "Arbitration Hearing Evidence") Dr. Wisa, Mr. Donovan and the
TBW team of experts are well-qualified in geophysics, geotechnical
engineering and have experience and expertise with regard to dam
embankment design and stability, particularly earthen dams including
phosphate dams in Florida. Dr. Wisa, Dr. Upchurch and Mr. Donovan
testified that this was the most extensive field investigation
in which they have ever been involved. Mr. Donovan testified that
not only was the team of experts highly competent in their respective
fields, but the interdisciplinary coordination of effort was extremely
well done.
143. The final site design for the Proposed Reservoir
was reconfigured along the western footprint, in part, to avoid
an area that could have a potential for sinkholes that may have
compromised the integrity of the embankment, to minimize any potential
public safety risk , and to avoid wetlands. The area of Hillsborough
County where the Proposed Reservoir is planned is one of low sinkhole
activity. Petitioners agreed that no sinkhole issues exist which
might affect embankment stability.
144. Petitioners contend that aspects of TBWs
geologic analysis of the site were incorrectly performed. In particular,
Petitioners are concerned with two layers of the substrata found
in the area around the Proposed Reservoir site and their potential
to make the embankment unstable: leach zones and clay layers.
145. Petitioners expert, Dr. Scovazzo, opined
that the "leach zone," a weak layer in the substrata, should have
been analyzed separately with a sensitivity analysis, that TBW
used an "averaging" of geologic features instead of actual site
conditions, and "averaging" would not identify the weakest areas
of the foundation such as the discontinuous clay layers and leach
zones. Dr. Scovazzo then concluded these zones could be weaker
than those that were represented in the stability analyses conducted
by TBWs experts.
146. In regard to the observations by Dr. Scovazzo,
Mr. Donovan, one of TBWs embankment stability experts, testified
that he ran separate computer analyses on each of the zones that
are of concern to Dr. Scovazzo. Then, in order to verify the results
of the computer analyses, Mr. Donovan checked the calculations
by hand and evaluate the results against his substantial knowledge
and experience with soil properties for dam embankments. Mr. Donovan
analyzed each of these zones individually and found them stable.
Apparently, Dr. Scovazzo had not seen this analysis.
147. Furthermore, with regard to Petitioners contention
that TBW used an inappropriate "averaging" of geologic features,
TBWs experts testified that they utilized the approved methodology
recommended by the USCOE for determining the soil strength properties
of a layer of soil. This involves using a combination of the top
two-thirds and the bottom one-third of all of the soil strength
properties identified at the Proposed Reservoir site, thus producing
a biased "weighted average" as recommended by the USCOE in its
Engineering Manual EM 1110-2-1902, Engineering and Design - Stability
of Earth and Rock-Fill Dams (1970), discussed above regarding embankment
stability. The USCOE Engineering Manual provides:
For each embankment zone and foundation layer, design shear strengths should
be selected such that two-thirds of the test values exceeded the design values.
In most cases, the design shear strength for the various zones and layers should
always be greater than the lowest test value for the zones and layers being
considered.
(USCOE Engineering Manual, p. 13) TBW followed USCOEs
recommendations and Petitioners did not provide contrary authority
to the Arbitration Panel. Petitioners embankment stability
expert, Dr. Scovazzo, stated that he would apply the same embankment
safety factors used by TBW for his analysis except that, in addition,
he would have done a "rapid draw-down" analysis (to be discussed
later in this arbitration award). Nonetheless, Dr. Scovazzo said
that he was unable to render a professional opinion as to embankment
stability from a design standpoint.
148. Additionally, Dr. Wisa testified that the
discontinuous clay layers questioned by Petitioners were not a
concern primarily because they were discontinuous, as verified
by soil borings. He evaluated both the discontinuous clay lenses
and the leach zones from the standpoint of their location and strength
properties, based on his extensive knowledge of soil properties,
and concluded that they would have little impact on the stability
of the dam.
149. In summary, Petitioners experts have
acknowledged the extensive and competent geologic investigation
of the site. Petitioners have presented no evidence that the site
is unsuitable for the proposed earthen embankment. The Arbitration
Panel finds that the extensive geologic analysis conducted by TBWs
experts was thorough, credible and demonstrated that an adequate
analysis was done of the leach zones and discontinuous clay layers
and that the stability of the earthen embankments will not be jeopardized.
Geologic Modeling
150. Petitioners also contend that TBWs
two-dimensional (2-D) modeling of the embankment design cannot take
into consideration the "interfingering" of the permeable and impermeable
layers that are potential pathways for seepage. Petitioners claim
that the seepage may result in structural instability.
151. Petitioners expert, Dr. Scovazzo, asserts
that a three-dimensional (3-D) model is needed to better evaluate
the geology of the specific area. Dr. Scovazzo merely offered his
personal opinion on this subject and did not refer to any generally
accepted engineering principles or agency criteria to support the
need for a 3-D model with regard to the Proposed Reservoir. Furthermore,
no evidence was introduced to show that 3-D modeling is required
by any specific Applicable Substantive Law, so again the Arbitration
Panel must look to the totality of the Arbitration Hearing Evidence
to evaluate for public health, safety and welfare considerations.
152. Dr. Wisa testified that 2-D modeling is usually
done for earthen dams of this type because in an earthen dam there
is typically a very long section, miles long with a fairly small-height
dam, so that everything is in plane. Thus, there is not a need
to analyze the embankment in terms of vertical, horizontal, and
along the axis. The analysis involves picking a slice and examining
the slice. On the other hand, for example, where a very high dam
is being built in a steep, narrow gorge, the sides of the gorge
have a big influence because they are high and narrow compared
to the dam. In that case the side effects of the natural ground
walls play a substantial role in stability, and a 3-D approach
is appropriate.
153. The Arbitration Panel accepts Dr. Wisas
testimony and concludes that the 2-D model used by TBW is appropriate
and adequate for the geologic modeling of the embankment.
Embankment Stability Analysis
154. The ERP permitting requirements contain no
Applicable Substantive Law establishing any specific design standard
for the construction of embankments as part of an off-stream reservoir.
Instead, the only pertinent Applicable Substantive Law is general
in nature, i.e., that a permit applicant provide a reasonable assurance
demonstration that the embankment is designed not to fail. This requirement
comes from Rules 40D-4.301 and 0D-4.302, F.A.C., and 33 C.F.R. §320.4,
requiring that an ERP project not be a threat to public health, safety
or welfare, or cause off-site flooding, and must be capable of functioning
as proposed.
155. In a stability analysis for embankments,
engineers evaluate "safety factors," or "factors of safety." As
it pertains to an embankment stability analysis, "safety factor" is
defined generally as the available shear strength, that is, the
strength of the soil divided by the strength required to maintain
stability. Accordingly, it is a measure, or a ratio, of shear strength
available to shear strength required. For example, a factor of
safety of one implies that there would be enough shear strength
available to meet that which is required as a result of sliding
and instability analysis. Thus, a factor of safety of 1.5 means
that there would be 50 percent more strength available along that
failure plane than is required to maintain it stable.
156. Embankments are not normally involved in
an ERP application, nor are there any specific criteria, such as
safety factors, mandated for embankment design. However, because
of the public safety-related issues, TBW looked to the guidelines
and regulations of the USCOE, United States Soil Conservation Service,
and the State of Georgia for guidance as to safety and function
of the embankment design. These governmental agencies have extensive
experience in the regulation of earthen embankments.
157. A comparison of the factors of safety for
the stability analysis is presented in Table 6.1, contained in
RAI Response No. 60. Mr. Donovan and Dr. Wisa used their professional
judgment based on extensive and long-term experience with dam and
embankment design to evaluate the applicability of and to select
the appropriate safety factors for the stability analysis of the
embankment. They did not select inapplicable factors, such as those
for earthquakes, for example, because the Proposed Reservoir site
is located in seismic zone "0." Thus, the USCOE guidelines for
safety factors were adopted, along with consideration of some from
the United States Soil Conservation Service and the State of Georgia,
as the most applicable for the Proposed Reservoir, and then were
used for the design of the facility. The USCOE guidelines were
taken from USCOE Engineering Manual EM 1110-2-1902, Engineering
and Design - Stability of Earth and Rock-Fill Dams (1970).
158. The embankment design and stability analysis
for the Proposed Reservoir was conducted for the safety factors
pertaining to the following scenarios, i.e., at the end of construction
but before filling, the initial and cyclic filling, during the
process of impounding water, and drawdown after there is a seepage
or "phreatic" surface, which is a line of seepage through the embankment
and the foundation. Mr. Donovan testified that the safety factors
of both the USCOE and the State of Georgia were met for all of
these scenarios.
159. The Arbitration Panel concludes that, with
regard to embankment stability, TBW conducted a thorough and competent
analysis of available safety factors, and that the appropriate
safety factors were met or exceeded. Therefore, TBW has demonstrated
that the embankment, as designed, will be stable and capable of
functioning as proposed, will be protective of public health, safety
and welfare and will not cause off-site flooding.
Rapid Drawdown Analysis and Emergency Drawdown
160. Petitioners assert that a "rapid drawdown" analysis
is required not only by good engineering practice but also by the
Soil Conservation Service (SCS) Technical Release #60 (Oct. 1985)
("SCS TR-60"), as well as the USCOE Engineering Manual, EM 1110-2-1902,
in order to analyze the stability of the upstream embankment to ensure
that the Proposed Reservoir is conservatively designed. A "rapid
drawdown" analysis has the water surface in the Proposed Reservoir
theoretically lowered instantaneously in order to evaluate the embankment
stability. Petitioners assert that TBW did not conduct a "rapid drawdown" analysis,
but rather allowed the water surface to be gradually lowered over
time. This would allow the embankment to adjust to the lowering of
the water in the Proposed Reservoir instead of being a rapid drawdown
analysis.
161. All parties recognize that an "instantaneous
drawdown" of the Proposed Reservoir is impossible; nevertheless,
Petitioners contend that, pursuant to SCS TR-60, such an analysis
is required in order to determine embankment stability and provide
a conservative embankment design. Petitioners expert, Dr.
Scovazzo, agreed that the USCOE allows a rapid drawdown analysis
based upon "effective drawdown rates," as was done by TBW, when
the assumed "instantaneous rapid drawdown" is "excessively conservative." Thus,
the disagreement between Petitioners and TBWs experts
revolves around the applicability of SCS TR-60, and whether an "instantaneous
drawdown" analysis would be "excessively conservative" for the
Proposed Reservoir.
162. TBWs expert, Mr. Donovan, had extensive,
high-level USCOE experience and testified that applicable USCOE
guidelines had been followed. He went on to explain that an "instantaneous
drawdown" analysis had not been done because it is not applicable
in the context of the USCOE criteria, and the SCS criteria is silent
on the issue of drawdown rate. Dr. Scovazzos response to
the issue of drawdown rate was to state that no rate needed to
be specified.
163. Mr. Donovan explained that, in the rapid
drawdown case, the water in a reservoir empties immediately. The "phreatic" surface,
or water seepage level within the embankment, however, does not
drop along with the water in the reservoir, and moves to destabilize
the embankment by then draining from the embankment.
164. The USCOE guidelines state that the rapid
drawdown analysis is a conservative analysis. The guidelines give
two situations where there are mitigating circumstances that do
not require it: inability to draw down the structure instantaneously,
and the soil conditions are such that they will drain along with
the pool. Mr. Donovan testified that both of those mitigating circumstances
will exist with regard to the Proposed Reservoir.
165. Both Petitioners and TBWs expert
witnesses agreed that, in the unlikely event that an instantaneous
rapid drawdown did occur at the Proposed Reservoir, the only damage
which would be sustained would be to the upstream face of the embankment
and there would be no risk of off-site flooding. No evidence was
submitted that there would be damage to other persons, property,
or any flooding created in the event an instantaneous drawdown
at the facility occurred and there was damage to the embankment.
166. Petitioners also are concerned about the "emergency
drawdown" situation. Unlike the "rapid drawdown," which is a design
test for evaluating embankment stability and not a real-world scenario,
an emergency drawdown is related to the capability of the operators
to draw down the facility as fast as operationally feasible. For
example, should a structural problem develop, emergency drawdown
of the reservoir might be necessary for the safety of nearby residents
and, eventually, access for repairs.
167. Petitioners are critical of the "emergency
drawdown" operational capacity, since it is described in the Joint
Application as only 2"-3" per day. Further, Petitioners assert
that an "emergency drawdown" capability of only 2"-3" per day was
insufficient according to TBWs independent quality assurance
reviewers, XCORPS. However, testimony offered at the hearing indicates
the document reviewed by XCORPS was only at the 30% completeness
stage, which, according to the XCORPS correspondence produced at
the arbitration hearing, was commensurate with the level of information
that should be expected at that stage.
168. Mr. Donovan testified that the embankment
is designed to be stable for emergency drawdowns of up to one and
one-half feet per day, which is the maximum amount of water which
can be withdrawn from the facility at any time absent a pre-existing
breach of the embankment. As a result, the embankment remains stable
at any lesser drawdown rates which might be applied to it. Emergency
drawdown of up to one and one-half feet per day can be accomplished,
given the 84" pipeline and the blow-off valves that are part of
the pipeline. Lesser drawdowns of six inches per day can be achieved
by sending 66 mgd per day to the water treatment plant, and using
the blow-off valve system to evacuate another 94 mgd. Operational
drawdown conditions are two to three inches per day, sending only
66 mgd per day to the water treatment plant.
169. Thus, the Arbitration Panel finds that the
rapid drawdown analysis is not a requirement, but is rather one
method to evaluate dam stability. The rapid drawdown analysis is
not required for the Proposed Reservoir because it is an "excessively
conservative" analysis given the design of the Proposed Reservoir.
Additionally, the Arbitration Panel finds that the operational
and emergency drawdown scenarios evaluated by TBW are reasonable
for the Proposed Reservoir .
Piping
170. Petitioners have also raised the issue of "piping" as
a possible mode of failure for the earthen embankment planned for
the Proposed Reservoir. "Piping" is a term used in embankment design
to refer to the movement of soil carried by water. Piping can occur
along the water supply pipelines that are part of the Proposed Reservoir
or through the soil anywhere in the embankment.
171. The testimony of the embankment stability
experts concurred that piping would be the most likely cause of
failure of an earthen dam. Petitioners are critical of the embankment
materials, contend that the embankment would be exposed to water
seepage, and that the embankment and foundation will be susceptible
to piping. Moreover, Petitioners claim that TBWs analysis
also failed to fully consider the potential for piping along the
water supply pipelines penetrating the dam, which is an area of
major concern because the pipeline area is a location more likely
to fail than the rest of the embankment. Finally, Petitioners assert
that TBW failed to consider design alternatives, such as a filter
drainage diaphragm, and suggest that such alternatives could add
a significant level of protection.
172. Dr. Wisa and Mr. Donovan stated that the
overall intent of the design for the Proposed Reservoir is to slow
the movement of water through the embankment and control it, thus
averting piping. They admitted that some water is always expected
to move through earthen embankments and, if the water carries enough
soil with it, a pipe-like hole can form in the embankment, potentially
compromising the stability of the embankment. Such movement can
occur for a number of reasons, including the nature of the soil,
the head (pressure of the water table), or lack of proper soil
compaction in the case of foreign items in the embankment, such
as a water supply pipeline.
173. Dr. Wisa and Mr. Donovan further elaborated
that control of piping begins with the design, type and compaction
of the material that goes into the embankment. That is one reason
why the site characterization was done, to understand what sort
of material would be installed, compacted and built as designed,
to prevent soil driven by water from piping through the facility.
The design of the Proposed Reservoir calls for removal of potentially
problematic clays, selection of the proper soils, mixing them to
create a homogeneous blend, and then compacting them properly to
reduce head within the embankment. Additionally, the interior of
the embankment is designed to have a geomembrane, a plastic liner
faced with soil cement. The geomembrane and the soil cement would
tie into the a soil-bentonite cutoff wall to contain and control
the water and slow its movement to the outside. There could be
waves inside of the embankment, and the soil cement is designed
for erosion protection of the interior or upstream slope and to
protect the geomembrane from deterioration. Water in the embankment
would also be controlled and diverted by the use of a blanket drain
and toe drain system.
174. Furthermore, TBW has designed additional
systems to reduce the risk of piping failure at the Proposed Reservoir.
Such systems include: (1) the design of a blanket drain system
to drop the head differential of water passing through the embankment;
(2) a toe drain collection system to drop the water gradient; (3)
a 3:1 slope design which extends the path within which piping must
occur.
175. In addition to the soil analysis, mixture
and compaction of soils, and the above-referenced measures related
to the stability of the entire embankment, the design of the Proposed
Reservoir has addressed potential piping along the two pipelines
that would be connected to the facility by: (1) designing the pipelines
to go approximately 13 feet below grade, that is, under the embankment
rather than through it; (2) encasing the pipe in flowable fill
(a specialized concrete mixture) in the lower half of the pipe
bed where it is difficult to get adequate compaction of the soil,
so that there will be no voids conducive to piping; and (3) including
a circumferential piezometer blanket and monitoring system that
goes around the flowable fill to measure whether there is any movement
of water or materials in the area around the pipeline to detect
any potential piping problems and to control the movement before
it becomes problematic.
176. Mr. Donovan testified that TBWs experts
decided against the use of seepage collars or filter drainage diaphragms
on the pipeline because, after many years of study, the USCOE found
that instead of retarding or preventing piping along pipelines
within embankments, these devices tended to make the area around
the pipe more susceptible to piping. He also said that the USCOE
no longer allows them on its projects.
177. Lastly, the Reservoir Operation and Maintenance
Plan will also play a significant role in quickly detecting any
signs of piping and in taking immediate corrective action. A Reservoir
Operation and Maintenance Plan was developed to outline the operational
and maintenance procedures for the Proposed Reservoir. See Joint
Application, AppendixK. The plan describes the Proposed Reservoir
operation, focusing primarily on maintaining the embankments. The
plan addresses filling the Proposed Reservoir as well as withdrawals,
and provides a procedure for visual inspection of the embankments.
It also includes maintenance guidelines. Moreover, the design consultant
will have a significant role in supervising construction and then
in training the TBW staff in the operation and maintenance.
178. Thus, the Arbitration Panel finds that the:
(1) piping issue has been adequately addressed by the soils to
be used and the design compaction of these soils; (2) soils, when
properly compacted, will meet the selected embankment design criteria
adopted from the USCOE Engineering Manual referenced earlier; (3)
embankment design systems are reasonable and appropriate to reduce
the risk of a piping failure at the Proposed Reservoir; (4) specific
design measures relative to piping along the pipeline are reasonable
and appropriate to reduce the risk of piping along the pipeline;
and, (5) the Reservoir Operation and Maintenance Plan, implemented
as proposed, should be effective in observing and correcting any
potential piping before it becomes problematic. The Arbitration
Panel finds that these factors are protective of public health,
safety and welfare relative to piping concerns.
Downstream Toe Protection
179. Petitioners assert that TBW has failed to
consider the potential effects of flooding on the downstream toe
of the embankment. They also contend that during a significant storm
event, water may flow against the toe of the dam, causing erosion
of the embankment with water also backing up in the toe drain and
blanket drain, further compromising the embankment integrity.
180. The various experts for the parties generally
agreed that the downstream toe is a critical part of the embankment.
Erosion of the downstream toe by natural storm events or other
events could compromise the stability of the embankment. Thus,
the regular inspections as provided by the Operation and Maintenance
Manual, during both dry and wet seasons, will be an important part
of proper operation and maintenance.
181. In addition to all of the soils and stability
engineering provided for the embankment, the downstream toe would
be protected on the side away from the embankment by a paved toe
road. It serves two purposes. First, it would provide access for
inspection of the downstream toe around the entire perimeter of
the Proposed Reservoir. Second, it would protect the toe from the
natural forces of a 500-year flood event by virtue of the construction
and elevation of the toe road. TBWs experts testified that
the elevation of the toe/perimeter road is designed to be set more
than one foot above the elevation of a 500-year flood. The 500-year
flood event translates into one chance in 500 of such a flood happening
in any one year.
182. Petitioners expert, Dr. Scovazzo, contended
that the downstream toe should be protected from the natural forces
of a "probable maximum precipitation" ("PMP") event, rather than
a 500-year flood event. Both Petitioners and TBWs experts
concurred, however, that there is no Applicable Substantive Law
or other criteria which specifically requires the use of a PMP
event for analysis of downstream toe protection. Rather, Petitioners expert
stated that this is his "personal" standard, rather than a standard
or guideline adopted by any regulatory body or a generally accepted
and sound engineering practice.
183. Mr. Donovan testified that in his experience
relative to dam design, the PMP event has been used only to size
inflows into the reservoirs, and that he has never seen it used
for storm drainage control outside the reservoir. Furthermore,
he stated that the most common designs he has seen associated with
downstream drainage, or storm water control outside the footprint,
are either the 100-year storm or, more frequently, the 25-year
storm. TBW by design would protect the downstream toe to the more
conservative level of a 500-year storm event.
184. In addition, no evidence was introduced that
would indicate how, if at all, the downstream toe stability would
be jeopardized in the event of a PMP occurrence. Petitioners expert
was unable to state any probability of a stability problem being
caused, even if a PMP event occurred at the facility.
185. The Arbitration Panel concludes that the
downstream toe would be adequately protected by the design measures
for the Proposed Reservoir.
Dam Breach Analysis, Inundation Mapping, and Emergency Action Plan
186. From the outset of this arbitration process,
Petitioners have contended that TBW had not provided the reasonable
assurance required by Applicable Substantive Law because it failed
in the Joint Application to include a dam breach analysis, including
inundation mapping, and a final or complete Emergency Action Plan
("EAP"). A dam breach analysis involves selecting sites along the
embankment and evaluating the potential hazard that breach events,
at those points, might present to the surrounding area. An inundation
map is a geographical map that represents the dispersal of water
once it gets out of its containment. Modeling animations or representations
may be done that attempt to predict the direction, depth and the
time of flow of water once it has escaped a reservoir. This shows
what populations and property might be affected by the inundation
of water. An EAP is a planned course of action that a person and/or
a facility would follow in response to an abnormal circumstance at
that facility. Generally, the EAP should delineate specifically who
does what, who is notified, and what actual response actions should
be taken. The EAP should be completed before a facility is operational.
187. These items raise the issues of off-site
flooding, and public health, safety and welfare. The actual framing
of this issue began on January 26, 2001, when TBW filed its "Motion
For Order Determining Applicable Agency Rules, Policy and Statutes
and Memorandum in Support." The Arbitration Panel ruled that "[T]he
Applicable Substantive Law does not specifically require the inclusion
in the Joint Application, or consideration at the final hearing,
of an Emergency Action Plan, dam break analysis or inundation map(s)." However,
the Arbitration Panel did not preclude the parties from developing
an evidentiary basis for demonstrating the relevance of these items
to the more general permitting criteria related to off-site flooding,
or public health, safety and welfare. The ruling stated that reasonable
assurance, or the lack of it, may be shown in a number of ways
for these more generic standards.
188. Accordingly, TBW had the choice as to how
to demonstrate reasonable assurance of no off-site flooding and
no threat to the public health, safety, or welfare as a result
of the design, construction and operation of the Proposed Reservoir.
TBW chose to do so through the evidence of the design and stability
of the embankment and showing that there would not be off-site
flooding or threat to public health, safety, or welfare. TBW did
present a preliminary EAP in the Joint Application and the criteria
it would use to finalize the EAP, including the use of the FLDWAV
model in coordination with the State Dam Safety Officer.
189. On the other hand, Petitioners assert that
a dam breach analysis, inundation mapping and an EAP are relevant,
necessary and should be performed at this time, at least with regard
to reasonable assurances related to off-site flooding and public
health, safety and welfare. Also, FDEP, both in correspondence
related to the Joint Application and in the RAI, requested a dam
breach analysis, inundation mapping and an EAP, suggesting northwest
and southeast scenarios for a dam breach analysis and inundation
mapping. At least one witness suggested that these locations were
chosen because they were the closest points on the Proposed Reservoir
to areas with residences.
190. One of TBWs witnesses stated that TBW
plans to submit inundation mapping and a dam break analysis to
the FDEP as part of the permitting procedure after its staff meets
with the FDEP staff and further clarifies the modeling scenarios
that FDEP proposed. According to the Arbitration Hearing Evidence,
it appears that the FDEP had not yet formulated any final agency
positions concerning what modeling parameters or scenarios, if
any, it would like modeled, what assumptions might be appropriate
for such models, what data input parameters would be appropriate
or what locations should be modeled.
191. Petitioners conducted their own dam breach
analysis, produced associated inundation mapping, and presented
testimony in this regard by Mr. Mendelsohn and Dr. Fread. Petitioners dam
breach analysis and inundation mapping are the only ones in the
Arbitration Hearing Evidence. Additionally, in order to support
their contention that the EAP in the Joint Application is deficient,
Petitioners presented testimony by Mr. Gispert, an expert in emergency
management.
192. While the evidence showed that there is reasonable
assurance that the embankment is stable and highly unlikely to
fail, the issue that remains is the adequacy of an EAP in the highly
unlikely event of a dam failure. A substantial breach in the Proposed
Reservoir could lead to loss of life and extensive damage to property.
There are two residential areas in the general vicinity of the
Proposed Reservoir. To the northwest of the Proposed Reservoir
is the developed portion of a development of regional impact ("DRI")
known as Fishhawk Ranch. It does not abut the Proposed Reservoir
and there is a natural buffer between the reservoir footprint and
the DRI. The developed residential area of the DRI is at least
one mile away from the reservoir footprint. The Wendel Avenue subdivision,
containing about 51 residences, is located approximately one-quarter
of a mile from the southeast embankment toe.
193. Wendel Avenue residents are the closest neighbors
to the Proposed Reservoir. While the embankment profile is the
lowest in the southeast area near Wendel Avenue because the natural
grade is the highest, testimony was offered that a landscaping
berm could provide some additional protection for the residents
of Wendel Avenue in the unlikely event of a breach. However, there
was insufficient evidence to make findings with regard to the nature
of the landscape berm. TBW representatives, at a public meeting
with residents from Wendel Avenue, stated that there ought to be
a landscape buffer installed next to them and agreed to build one.
Additionally, sirens or an automatic telephone notification system
were suggested by Mr. Gispert as helpful tools to give public warning
if needed.
194. TBW has already prepared a draft EAP for
the Proposed Reservoir that is contained in AppendixL of the Joint
Application. Also, TBW voluntarily submitted its EAP to Hillsborough
County and its Director of Emergency Management for review. The
testimony indicated that the EAP followed FEMA guidelines. While
Mr. Gispert had a number of criticisms of the EAP, the document
he reviewed is only a draft.
195. The EAP would not be kept as a part of Hillsborough
Countys Emergency Plan, and would only be an internal document
used by TBW, not Hillsborough County. Although various other dams
and impoundments exist within Hillsborough County, the only other
EAP which has been submitted to Mr. Gispert involves a plan submitted
by IMC after a dam failure occurred. He has no other plans or maps
for any other dams or impoundments, or for the City of Tampas
dam on the Hillsborough River.
196. Mr. Gispert testified that emergency planning
should begin with a hazard vulnerability analysis. The hazard vulnerability
analysis is a general name for determining what may affect persons
or facilities. It is an assessment of the risk associated with
a possible breach. An inundation map is just one of a number of
hazard vulnerability analyses. There are other types or forms as
well. However, there was no evidence that, from an emergency planning
standpoint, the Proposed Reservoir should be redesigned or moved,
or that any roads or bridges in the vicinity required design changes.
197. In their dam breach analysis, Petitioners
assume that a breach will occur at the Proposed Reservoir at two
specified locations, but the evidence did not show design flaws
or problems at those sites. Nor was a probability analysis made
as to the likelihood of a breach occurring at the Proposed Reservoir
and/or occurring at the locations which Petitioners modeled. The
dam breach analyses and associated mapping provided by the Petitioners
were designed to show a "worst-case scenario" impact upon Fishhawk
Creek and the residents at Wendel Avenue.
198. In the event that a future breach occurred
at a location different from those which were selected and modeled,
new modeling would have to be performed. The purpose of producing
dam breach analysis modeling and a hazard vulnerability analysis
(which may or may not be in the form of associated inundation maps)
is primarily to assist emergency action planners in planning for
and dealing with any potential breach at the facility.
199. Even assuming that all of the Petitioners dam
breach analysis modeling and associated mapping were correctly
performed, the modeled results represent only a mathematical prediction
of a "possible" result rather than a probable or realistic one.
Moreover, while Petitioners modeling is useful as a starting
point for contingency planning purposes, it contains limitations
relating to assumptions and input parameters.
200. All of the stability experts who opined as
to the possible breach of the earthen embankment agreed that there
was practically no risk of an overtopping or embankment stability
failure at the Proposed Reservoir. As a result, the only plausible
type of design, construction or operational failure would be a
piping failure.
201. As the Arbitration Panel has previously found,
embankment failure as a result of piping is highly unlikely at
the Proposed Reservoir, provided it is designed, constructed and
operated in a manner consistent with the Joint Application. In
addition, piping failures usually provide enough time for either
correction of the problem or appropriate notice of the problem
to be given to affected persons. Piping usually results in deposits
of soil material and is commonly referred to as "sand volcanos." These
indicators of piping build over a period of weeks and are usually
spotted in advance of failure by inspection personnel at a facility
like the Proposed Reservoir.
202. Typically, repairs of earthen dam structures
which have been subjected to piping involve sufficient advance
warning to allow for the installation of relief wells and other
repair techniques on the downstream toe of the embankment. Given
the design of the Proposed Reservoir, even the Petitioners experts
agree that it would be a more probable event to have "weeks" of
advance notice of a piping problem, as opposed to hours of notice.
In this regard, the Operation and Maintenance Plan provides for
regular inspections to identify and take immediate corrective action.
Also, the EAP which was submitted by TBW included the presence
of operational and maintenance personnel at the facility, 24 hours
per day, 7 days per week.
203. In light of the above factual analysis, the
Arbitration Panel makes the following findings with regard to the
issue of a dam breach analysis, inundation mapping and the EAP:
(a) Based on the weight of the Arbitration Hearing Evidence related to embankment
design and stability, the Proposed Reservoir should reasonably be expected
to function as intended, not cause off-site flooding, and not adversely affect
the public health, safety, or welfare, or the property of others.
(b) The dam breach analyses and inundation mapping may be useful planning tools
for developing an EAP.
(c) To be helpful and useful to emergency planners, an EAP should be completed
and implemented prior to placing the Proposed Reservoir into operation.
(d) Applicable Substantive Law does not compel the need for an EAP to be implemented
until sometime before the Proposed Reservoir begins to receive water and does
not require completion of an EAP at this time.
(e) The EAP is an organic document that should be updated as circumstances,
agency contacts and other matters related to emergency planning related to
the Proposed Reservoir and vicinity change.
CONCLUSIONS OF LAW
1. The Arbitration Panel has authority to issue
a binding arbitration award in this matter pursuant to the 1998 Interlocal
Agreement.
2. Petitioners are authorized pursuant to the
1998 Interlocal Agreement to seek this binding arbitration.
3. The procedural rules followed by the Arbitration
Panel to decide this matter are contained in the 1998 Interlocal
Agreement and the American Arbitration Associations Environmental
Arbitration Guidelines.
4. Pursuant to the 1998 Interlocal Agreement,
TBW has the burden of proof in this arbitration proceeding "of
providing reasonable assurances that [TBWs] Primary Environmental
Permit application meets all applicable agency rules, policy and
statutes." ("Applicable Substantive Law") 1998 Interlocal Agreement,
Section 3.13(B). This is the ultimate issue of law in this arbitration
proceeding.
5. The Arbitration Panel has previously decided
that TBWs burden of proof in this arbitration proceeding
is to show compliance with the applicable substantive statutes,
rules and policies and not merely whether the "application" for
a "Primary Environmental Permit" is complete. Arbitration Panel
Order, December 22, 2000.
6. The Arbitration Panel has also previously determined
the applicable "rules, policy and statutes" for this arbitration
proceeding. Arbitration Panel Order, February 28, 2001. These "rules,
policy and statutes" are listed as part of Attachment 2 (Arbitration
Panel Order, February 28, 2001, Appendix A) to this arbitration
award. In addition, the Arbitration Panel has determined that the
term "application" should be construed to mean the information
provided in the original application submitted to the agencies
for the Primary Environmental Permit as well as any other information
properly developed during the arbitration discovery process, including,
but not limited to, information provided to agencies pursuant to
agencys request for additional information, and admitted
into the arbitration hearing record at the final arbitration hearing.
Arbitration Panel Order, December 22, 2000. (The Joint Application,
the RAI Response and all the evidence admitted at the final arbitration
hearing are jointly referred to in this arbitration award as the "Arbitration
Hearing Evidence.")
7. The Arbitration Panel has not previously decided
what the term "reasonable assurances" means as that term is used
in the 1998 Interlocal Agreement. The Arbitration Panel did discuss
in the Arbitration Panel Order of December 22, 2000, that "reasonable
assurance" is a term of art used extensively in Floridas
environmental statutes and regulations. Arbitration Panel Order,
December 22, 2000, pp. 3-6. In their respective recommended arbitration
award pleadings and in oral argument to the Arbitration Panel,
both TBW and Petitioners have proposed that the term "reasonable
assurances" should be interpreted in a manner consistent with how
that term has been interpreted under Floridas environmental
statutes. The Arbitration Panel has not found any authority inconsistent
with this interpretation. Accordingly, the Arbitration Panel will
consider the term "reasonable assurance" to mean the same as how
that term has been interpreted under Floridas environmental
laws.
8. Reasonable assurance requires TBW to demonstrate
that the Proposed Reservoir has a "substantial likelihood" of being "successfully
implemented" to comply with all applicable statutes, rules and
policies. Metropolitan Dade County v. Coscan Florida, Inc., 609
So. 2d 644, 648 (Fla. 3d DCA 1992); Save Anna Maria, Inc. v. Department
of Transportation, 700 So.2d. 113, 117 (Fla. 2d DCA 1997).
9. To meet the reasonable assurance standard,
an applicant must address impacts and contingencies which can reasonably
be expected to occur, but an applicant is not required to eliminate
all contrary possibilities, however remote, or to address impacts
which are only theoretical and not reasonably likely. Hoffert v.
St. Joe Paper Co., 1990 WL 749536, *15 (Fla. Div. Admin. Hrgs.
1990); Alafia River Basin Stewardship Council, Inc. v. SWFWMD,
1999 WL 1486358, *28 (Fla. Div. Admin. Hrgs. 1999); Crystal Springs
Recreational Preserve, Inc. v. Southwest Florida Water Management
District, 2000 WL 248392, *36 (Fla. Div. Admin. Hrgs. 2000). The
applicants burden "is one of reasonable assurances, not absolute
guarantees." Manasota 88, Inc. v. Agrico Chemical Company and Florida
Department of Environmental Regulation, 12 FALR 1319, 1325 (February19,
1990).
10. The parties and the Arbitration Panel have
all struggled with the practical application of determining whether
the Joint Application meets the reasonable assurance standard at
this stage of the permit application process. The difficulty is
that under the 1998 Interlocal Agreement, the Arbitration Panel
has been called upon to determine whether TBW has met its "burden
of providing reasonable assurance that the Authoritys Primary
Environmental Permit meets all applicable agency rules, policy
and statutes." When the permitting agency, here the FDEP, makes
a similar evaluation pursuant to Rule 62-4.070, F.A.C., the FDEP
is reviewing an application that has already been determined complete
after having received responses to requests for additional information
pursuant to the provisions of Section 373.4141, Florida Statutes,
and Rule 62-4.055 F.A.C.
11. Because the arbitration process was initiated,
as required under the 1998 Interlocal Agreement, within 30 days
of the date the TBW Board approved filing the Joint Application
with the FDEP, and the FDEP has continued to review the Joint Application
and has yet to conclude its completeness determination, the result
is that the parties must present, and the Arbitration Panel must
consider, a Joint Application that has not yet even been determined
complete by the FDEP. The difficulty that this presents to the
arbitration process is illustrated by the discussion of the legal
standard for review contained in the Arbitration Panels "Order
on Motion to Determine Scope of Arbitration and Related Motion
to Strike," wherein the parties argued over the appropriate standard
for evaluating the reasonable assurance requirements of the Interlocal
Agreement. The conclusion of the order was to interpret the intent
of the Interlocal Agreement "to require TBW to provide reasonable
assurance that the information contained in the Joint Application
will comply with the applicable substantive criteria of relevant
agency permitting statutes, rules and policies."
12. The only way that the Arbitration Panel can
determine whether such reasonable assurance has been provided is
through review of the Arbitration Hearing Evidence with regard
to the disputed issues, based upon whether the particular issue
has a level of detail necessary to make it consistent with the
criteria for a complete application, since incompleteness itself
can be a basis for permit denial by FDEP. See Rule 62-4.055(1),
F.A.C. Indeed, the 90-day time frame within which FDEP must process
and take agency action upon a permit application does not even
commence until FDEP has received a complete application. See Rule
62-4.055(5), F.A.C.; Fonte v. State Dept. of Environmental Regulation,
93 ER FALR 29, 1993 Fla. ENV LEXIS 23 (DER 1993).
13. This is a difficult situation for all parties
to arbitration proceedings created under the 1998 Interlocal Agreement.
For TBW, it raises the possibility of multiple arbitrations one
at the time that the permit application is approved by the TBW
Board, and another at the time or times the application is amended
as a result of arbitration. This is particularly problematic given
recognition by experts versed in FDEP procedures that an applicant
for a permit does not normally offer everything in the way of mitigation
in the original application.
14. For the challenger, the problem is in determining
what to challenge. TBW can submit an application that under normal
procedures would be considered incomplete, provide additional information
that has the effect of changing the impacts of the project in significant
ways, and then be issued a permit that looks very different from
the original application. Since the member governments have waived
their rights to challenge a permitting decision under Chapter 120,
Florida Statutes (2000), the member governments could thereby be
precluded from any challenge to permit conditions that appear different
than what originally was proposed in the application, unless the
original application is challenged. Similarly, if the Arbitration
Panel were to rule that the information provided as to the disputed
issues was incomplete, but not require TBW to amend its application
to provide the necessary information, the member governments would
lose any subsequent opportunity to challenge that additional information,
whether or not that additional information meets the reasonable
assurance standard of Applicable Substantive Law.
15. Confounding this analysis is the question
of whether a response by TBW to a RAI must necessarily result in
an amendment to an application that must be approved by the TBW
Board and thereby even be subject to arbitration. There is nothing
in the Interlocal Agreement that identifies what constitutes an
amendment for arbitration purposes, other than by an arbitration
award requiring one or one that TBW decides to file. FDEP rules
do not expressly require or define what are "amendments" to permit
applications. Since FDEP asks for additional information to an
application rather than an amendment to it, this provides a member
government with yet further incentive to challenge an incomplete
application. This points to the importance of the Arbitration Panels
determination of reasonable assurance based upon completeness rather
than upon a work in progress that will likely become complete.
16. The Arbitration Panel believes that when considered
in the light of agency policy regarding conditions precedent and
subsequent to permit issuance, the arbitration process as approved
under the Interlocal Agreement provides a way of working through
the difficulties described herein. First of all, as Petitioners
acknowledged in closing argument, any subsequent arbitration would
be limited to those subjects that TBW will have to include in its
amendment to its Joint Application in response to the arbitration
award. The new proceeding does not create an opportunity to challenge
previously unchallenged areas of the permit application or areas
resolved by the previous arbitration. This gives further weight
to the importance of a member government in identifying specifically
the matters in dispute, which it is required to do under the Interlocal
Agreement. Unlike a Chapter 120 proceeding, where an ALJ must decide
whether an applicant has provided reasonable assurance that the
application meets the relevant permitting criteria, here the only
issues subject to arbitration are those identified by the challenging
member government. All others are not subject to review for permit
compliance, either in the subject arbitration proceeding or at
some later date, at least not by a member government.
17. Therefore, while the process allows for the
potential of multiple arbitrations in the event of incompleteness,
the new arbitrations would be limited in scope, only to those items
for which the Arbitration Panel has determined an amended application
is needed. This protects both TBW from open-ended proceedings and
the member government from having to accept a permit application
without knowing whether certain provisions may have potential impacts
that the member government opposes because they violate Applicable
Substantive Law.
18. A somewhat separate but related issue is the
degree of specificity that permit conditions need to have to meet
the reasonable assurance test. The Arbitration Panel rejects TBWs
argument that it only needs to prove that it has an application
that is capable of becoming permittable in order to meet the reasonable
assurance test. At the same time, however, the Arbitration Panel
recognizes that all conditions need not be identified in full detail
in the proposed agency action on the permit conditions subsequent
can often be acceptable. Therefore, even though the Arbitration
Panel has determined some of the project details to require further
definition, it is permissible for those details to be developed
subsequent to permit issuance, without requiring TBW to amend,
as long as TBW has provided reasonable assurance at this stage
of the application process that it has provided sufficient information
for the Arbitration Panel to determine that the condition subsequent
meets the reasonable assurance test.
19. Determining the degree of specificity required
to meet the reasonable assurances test for conditions subsequent
to permit issuance can be a difficult process. The difficulties
are illustrated through comparison of Metropolitan Dade County
v. Coscan Florida, Inc., 609 So. 2d 644 (Fla. 3d DCA 1992), with
Save Anna Maria, Inc., v. Department of Transportation, 700 So.
2d 113 (Fla. 2d DCA 1997).
20. In Coscan, the court reversed a dredge and
fill permit issuance for a marina because the permitting agency,
DER (predecessor to FDEP), did not adequately analyze the likely
anticipated effects of the proposed project, and in particular
whether the permit applicant had provided reasonable assurance
that water quality standards would be met. The agency instead relied
upon an agreement it had with the applicant in which the applicant
promised to correct adverse impacts if they occurred, but without
the applicants being able to demonstrate with substantial
likelihood that project construction or subsequent corrective measures
could in fact be successfully implemented. The court rejected the
deferral of the determination as not meeting the reasonable assurance
test.
21. In Save Anna Maria, the court found permissible
the applicants demonstration that its mitigation plan would
meet the reasonable assurance test, notwithstanding the fact that
its success was based upon future monitoring. The court concluded
that the monitoring plan, along with contingent corrective actions
if the mitigation being monitored was not successful, were sufficiently
detailed to meet the reasonable assurance test. The court distinguished
Coscan as a case in which the agency had "deferred to a future
date a determination of whether reasonable assurance had been provided." 700
So. 2d at 117.
22. The standard to apply, therefore, is whether
reasonable assurance has been provided, or whether it has been "deferred
to a future date." The Arbitration Panel will evaluate the issues
raised by Petitioners based upon these criteria. A related issue
is the degree of detail that a permit application must have in
order to meet the reasonable assurance test. On that issue, a useful
comparison to Coscan is Hamilton County Bd. of County Commissioners
v. State Dept. of Environmental Regulation, 587 So. 2d 1378 (Fla.
1st DCA 1991). In Hamilton, petitioner challenged a DER permit
issuance on the grounds that the applicant failed to provide DER
with sufficient engineering reports and design details on the proposed
facility. The applicant instead provided general information about
engineering details in the application, and at hearing also presented
testimony from a professional engineer expert on the subject matter
on how the specific pollution abatement equipment could be installed
and was designed to work. The court concluded that DER "was entitled
to issue the construction permits subject to [the condition that
the expert oversee construction] to insure that the facility would
be constructed in compliance with the applicable rules." Id. at
1389. The court went on to cite to Kralik v. Dept. of Environmental
Regulation, 11 FALR 669 (DER 1989), affirmed without opinion, Decker
v. Dept. of Environmental Regulation, 545 So.2d 882 (Fla. 5th DCA
1989), for the proposition that DER could issue permits that provide
for submission of engineering plans for a component of a project
at a later date, provided there was evidence as part of the application
that such component "could be designed, installed and operated
in a manner to ensure [compliance] with water quality standards." Id.
23. Applying the case law to the Joint Application,
the Arbitration Panel concludes that in some instances, TBW is
requesting that the Arbitration Panel accept TBWs invitation
to defer its reasonable assurance determination to another date,
contrary to Coscan, but in other situations Petitioners are asking
more of TBW than the reasonable assurance standard requires prior
to permit issuance. Therefore, as detailed and for the reasons
stated below, the Arbitration Panel has concluded that the Joint
Application meets the reasonable assurance standard in some instances
but in others an amendment is required.
Water Quality Compliance
24. Pertinent to the issue of whether TBW has
provided reasonable assurance that its Joint Application complies
with Applicable Substantive Law are the following:
(a) Section 403.088, Florida Statutes, which prohibits any person, without
FDEP authorization, from discharging into waters within the state any waste
which reduces the quality of the receiving waters.
(b) The general permitting requirements for ERPs contained in Section 373.414,
Florida Statutes, and in particular requirements that the activity will not
be harmful to the water resources or will not be inconsistent with the overall
objectives of the SWFWMD, will not violate water quality and will not be contrary
to the public interest.
(c) The requirements of the following subsections of Rule 40D-4.301(1), F.A.C.,
which requires a permit applicant to provide reasonable assurance that construction,
alteration, operation, maintenance, removal or abandonment of a surface water
management system (i.e., the Proposed Reservoir and appurtenances):
(1) Rule 40D-4.301(1)(d), F.A.C., will not adversely impact the value of functions
provided to fish and wildlife, and listed species, by wetlands, other surface
waters, and other water related resources of the SWFWMD;
(2) Rule 40D-4.301(1)(e), F.A.C., will not adversely affect the quality of
receiving waters; and
(3) Rule 40D-4.301(1)(f), F.A.C., will not cause adverse secondary impacts
to the water resources.
(d) State surface water quality standards for copper established in Rule 62-302.530,
F.A.C., and groundwater quality standards found in Rule 62-520.420, F.A.C.,
which incorporates by reference Rule 62-550.320, Table 4, Secondary Drinking
Water Standards.
(e) 33 C.F.R. §320.4(d), which requires dredge and fill permits to comply
with water quality standards.
25. TBW has provided reasonable assurance that application
of copper sulfate will not result in a violation of state water quality standards.
In this regard, therefore, the Joint Application meets Applicable Substantive
Law relating to water quality issues raised by Petitioners.
26. Petitioners concerns have focused on
the potential adverse impacts of copper if and when it might be
transported through leakance out of the Proposed Reservoir and
into adjacent groundwater and surface waters. Petitioners have
therefore requested a ruling from the Arbitration Panel that the
Proposed Reservoir should not be permitted unless TBW first performs
a fate and transport analysis. Petitioners have not, however, presented
any persuasive evidence that copper would become soluble again
and travel to adjacent groundwater and surface waters; and even
if it does, that the transport would occur in quantities sufficient
to establish a violation of water quality standards. Furthermore,
Petitioners have not provided any persuasive evidence that even
if copper transport did occur, such transport would result in a
violation of water quality standards for copper outside of the
waters of the Proposed Reservoir.
27. As stated, for example, in Sheridan v. Deep
Lagoon Boat Club and Department of Environmental Protection, DOAH
Case No. 99-2234, 2000 Fla. ENV LEXIS 52, 00 ER FALR 118, 22 FALR
2358, 2387 (DEP 2000), "Applicant's reasonable assurances must
take into account objections of opponents and deal with reasonably
foreseeable contingencies. Opponents must do more than simply raise concerns or
speculation about what might occur. See Chipola Basin
Protective Group, Inc. v. Dept. of Environmental Reg., 11 FALR
467, 480-81 (DER 1988)."
28. Furthermore, it is not sufficient, from the
standpoint of making a reasonable assurance determination, that
there may simply be "adverse impacts" resulting from copper transport.
There must, instead, be a determination that the transport will
result in a violation of state water quality standards. As stated
in Peebles v. Department of Environmental Regulation, DOAH Case
No. 89-3725, 1990 Fla. ENV LEXIS 70, 12 FALR 1961, 1965 (DER 1989), "To
the extent the Hearing Officer's finding implies that the project
will impair water quality, such a finding cannot affect the outcome
of this case because impairment of water quality is not a proper
legal criterion for deciding whether to grant or deny the permit."
29. Rule 40D-4.301(1)(e), F.A.C., referenced above,
which requires an applicant to demonstrate that the proposed project
will not adversely affect the quality of receiving waters, cross
references numeric state surface water quality standards for copper,
which can be found in Rule 62-302.530, F.A.C.; and groundwater
standards for copper found in Rule 62-520.420, F.A.C., which in
turn incorporates by reference Rule 62-550.320, Table 4, Secondary
Drinking Water Standards. Petitioners have neither alleged nor
proven that these numeric standards are reasonably expected to
be violated as a result of construction or operation of the Proposed
Reservoir.
30. The Arbitration Panel is concerned, however,
that the evidence does show a potential problem in the event the
use of copper sulfate is wholly unregulated and the application
of it abused.
31. TBW responds to these concerns by citing to
Appendix K, Section 2.4 of the Joint Application, which states, "The
water quality control measure utilized in the reservoir management
will be permitted through the Hillsborough County Health Department
Source Water Permit." However, TBW has presented no evidence as
to the scope of such permit i.e., whether it regulates the
amount of usage, whether it requires any monitoring, or whatever.
Nor did any party point the Arbitration Panel to any aspect of
the Applicable Substantive Law that imposes any relevant regulatory
requirements upon such a permit or any other governmental controls
over application of chemicals into the Proposed Reservoir.
32. The Arbitration Panel concludes, therefore,
that mere cross reference to the Hillsborough County Health Department
permitting procedures is insufficient by itself to foreclose any
further inquiry as to possible adverse impacts of chemical application
under any set of circumstances. Given the lack of information with
regard to how the application of copper sulfate will be regulated,
the Panel concludes that it would be prudent for TBW to commit
to include copper as a constituent for which TBW will monitor as
part of its groundwater quality monitoring regime, in order to
determine whether concentrations of copper are exceeding water
quality standards or are increasing at levels that would appear
to indicate that water quality standards might be violated in the
future.
33. Given the speculative nature of the likelihood
of future exceedences, the Arbitration Panel does not find it necessary
that the Joint Application be amended to require TBW to provide
any specific measures if the monitoring shows a reasonable likelihood
of water quality exceedences, but only to include a commitment
by TBW to undertake such measures in such an event.
Water Quantity Monitoring and Management
34. Among the Applicable Substantive Law pertinent
to this specific issue are the following:
(a) The general permitting requirements for ERPs contained in Section 373.414,
Florida Statutes, and in particular requirements that the activity will not
be harmful to the water resources or will not be inconsistent with the overall
objectives of the SWFWMD, will not violate water quality and will not be contrary
to the public interest.
(b) The general permitting requirements under Section 404 of the Clean Water
Act, 33 U.S.C. §1344, for discharge of dredged or fill material into navigable
waters.
(c) The requirements of the following subsections of Rule 40D-4.301(1), F.A.C.,
which requires a permit applicant to provide reasonable assurance that construction,
alteration, operation, maintenance, removal or abandonment of a surface water
management system (i.e., the Proposed Reservoir and appurtenances):
(1) Rule 40D-4.301(1)(a), F.A.C., will not cause adverse water quantity impacts
to receiving waters and adjacent streams;
(2) Rule 40D-4.301(1)(b), F.A.C., will not cause adverse flooding to on-site
or off-site property;
(3) Rule 40D-4.301(1)(c), F.A.C., will not cause adverse impacts to existing
surface water storage and conveyance capabilities;
(4) Rule 40D-4.301(1)(d), F.A.C., will not adversely impact the value of functions
provided to fish and wildlife, and listed species, by wetlands, other surface
waters, and other water related resources of the SWFWMD;
(5) Rule 40D-4.301(1)(e), F.A.C., will not adversely affect the quality of
receiving waters;
(6) Rule 40D-4.301(1)(f), F.A.C., will not cause adverse secondary impacts
to the water resources;
(7) Rule 40D-4.301(1)(g), F.A.C., will not adversely impact the maintenance
of surface or ground water levels; and
(8) Rule 40D-4.301(1)(i), F.A.C., is capable of being effectively performed
and of functioning as proposed.
(d) The requirements of Rule 40D-4.302(1), F.A.C. which requires a permit applicant
to provide reasonable assurance that construction, alteration, operation, maintenance,
removal or abandonment of a surface water management system (i.e., the Proposed
Reservoir and appurtenances) will not be contrary to the public interest, as
determined by balancing criteria including the following:
(1) Rule 40D-4.302(1)(a)1., F.A.C., adversely affecting the public health,
safety or welfare or the property of others;
(2) Rule 40D-4.302(1)(a)2., F.A.C., adversely affecting the conservation of
fish and wildlife, including endangered or threatened species, or their habitats;
(3) Rule 40D-4.302(1)(a)5., F.A.C., whether the activity will be of a temporary
or permanent nature; and
(4) Rule 40D-4.302(1)(a)7., F.A.C., the current condition and relative value
of functions being performed by areas affected by the proposed activity.
(e) The requirements of the Basis of Review ("BOR"), incorporated by reference
in Rules 40D-4.301 & 302, F.A.C., which restate and further explain those
rules. Particularly pertinent is ERP BOR Section 3.2.2.4, which requires an
applicant to provide reasonable assurance that the activity will not change
the hydroperiod of a wetland or other surface water so as to adversely affect
wetland functions or other surface water functions, including situations where
activities that have the potential to increase discharge or water levels will
not affect the functioning of the specific wetland or other surface water subject
to the increased discharge or water level. Section 3.2.2.4 also requires that
where water levels may be altered, the applicant is required "to monitor the
wetland or other surface waters to demonstrate that such alteration has not
resulted in adverse impacts, or to calibrate the system to prevent adverse
impacts. Monitoring parameters, methods, schedules, and reporting requirements
shall be specified in permit conditions." Also pertinent is BOR Section 3.3,
which establishes criteria for mitigation.
(f) Federal regulations implementing the Clean Water Act, including 33 C.F.R. §320.4(a)(1),
the federal public interest test; and 33 C.F.R. §320.4(g), which prohibits
injury to the property of others.
35. As to that portion of the Joint Application
that addresses potential impacts of leakance from the Proposed
Reservoir to wetlands and the property of others adjacent to the
Proposed Reservoir site, the Arbitration Panel holds that TBW has
failed to provide reasonable assurance that the Joint Application
complies with the above-listed Applicable Substantive Law.
36. The reason for the failure is that the monitoring
and management plans proposed by TBW in the Joint Application to
address the potential adverse impacts of leakance from the Proposed
Reservoir are not yet complete, and so the Panel does not have
sufficient information at this time to determine whether the plans
are adequate to offset potential adverse impacts to the adjacent
wetland systems and the species that rely on those systems. In
the words of Save Anna Maria, TBW has "deferred to a future date
a determination of whether reasonable assurance had been provided." 700
So. 2d at 117.
37. By its own admission, TBW has not yet provided
necessary baseline data to determine, from the onset, what are
the existing conditions upon which any adverse environmental impacts
can be measured. Without such baseline data the FDEP would be "unable
to make an informed analysis or to reach the conclusion that [the
applicant] had provided reasonable assurance" of compliance with
Applicable Substantive Law. Id. at 118. While TBW has committed
to developing a management plan designed to prevent such adverse
impacts from occurring, that commitment is insufficient at this
point in the permit application process, because there is no baseline
to determine what are the adverse impacts, as well as insufficient
details to describe the specific management efforts that will be
undertaken to avoid those impacts.
38. In reaching this conclusion, the Panel has
also taken into consideration Florida Power Corporation v. Department
of Environmental Regulation, 638 So. 2d 545 (Fla. 1st DCA 1994).
In that case the DER Secretary rejected an ALJs recommendation
that in turn was contrary to the DERs original decision to
deny a permit because the applicant had declined to offer mitigation
for the destruction of six acres of forested wetlands. The applicant
had argued that those six acres were replaced by six acres of equally
(if not more) valuable herbaceous wetlands, and that at any rate
the trees would eventually grow back.
39. The court in Florida Power upheld the Secretarys
rejection of the ALJs recommendation based upon the Secretarys
conclusion that forested wetlands were not environmentally equivalent
to herbaceous wetlands, and her rejection of the ALJs conclusion
that "in general one type of wetland may be replaced with another
with no adverse impact." Id. at 559. Florida Power illustrates
the importance here in obtaining baseline data regarding wetlands
that may be impacted by the Proposed Reservoir. Since the FDEP,
as a matter of policy, has determined that wetland systems are
not interchangeable, any wetlands that may be adversely impacted
by the project must be evaluated prior to such potential impact,
in order to better understand what that impact might be. Such an
evaluation is particularly important where the evidence demonstrates,
as here, that impacts such as stress from hydroperiod changes may
not readily be determined until after adverse impacts have already
occurred.
40. The baseline conditions are important not
only for understanding the extent of potential impacts to the existing
wetland system, but also for determining what kind of mitigation
may be needed in the event that the impacts are adverse, the maintenance
plan is unsuccessful in whole or in part, and the remaining adverse
impacts must therefore be offset by mitigation. The baseline assessment
is needed here, therefore, so that TBW can develop a backup mitigation
plan to compensate for any adverse impacts that cannot be completely
remedied through the management plan.
41. The Applicable Substantive Law for developing
such a mitigation plan can be found in the BOR. Under the BOR,
Section 3.3, "Protection of wetlands and other surface waters is
preferred to destruction and mitigation . . . . Applicants are
encouraged to consult with District staff in pre-application conferences
or during the application process to identity appropriate mitigation
options." Section 3.3.1.1 states, "In general, mitigation is best
accomplished through creation, restoration, enhancement, or preservation
of ecological communities similar to those being impacted." The
BOR goes on to explain the process for identifying appropriate
mitigation sites and strategies, and presenting mitigation proposals
to the permitting agency.
42. Both the Florida Power holding and the BOR
mitigation rules show that the analysis for wetland impacts is
somewhat different from that for reviewing adverse impacts to water
quality. As noted in the discussion on Issue 1, the adverse impact
determination as to water quality involves determining whether
numeric water quality standards have been violated. With wetlands,
however, the inquiry is qualitative as well as quantitative, looking
at whether the impacts will change the historic ecological community. "Mitigation
involving other ecological communities is acceptable if impacts
are offset and the applicant demonstrates that greater improvement
in ecological value will result." BOR §3.3.1.1.
43. In its application and in testimony at trial,
TBW has been candid in acknowledging
the need to provide DEP more information, as part of the permitting process,
with regard to background conditions at the potentially impacted areas, as
well as monitoring and management plans for addressing those adverse impacts.
TBW argues that the Joint Application, nonetheless, meets the reasonable assurance
standard because TBW would otherwise be held to an impossible burden to "prove
now that which cannot reasonably be proven until a point later in the application
process." TBWs Proposed Arbitration Award, p. 36 (emphasis in original).
44. In a sense, TBW is between a rock and a hard
place. The rock is the need, acknowledged by TBWs consultants
at trial, to await providing more extensive information on impacts
and potential mitigation until FDEP has had the opportunity to
review the application and issue its completeness comments. The
hard place is the fact that while TBW is going through the normal
give and take of permit application review, there is a parallel
arbitration proceeding at which the adequacy of the Joint Application
is being evaluated based upon the adequacy of proposals that, at
least to some degree, are still being developed with the permitting
agency.
45. Petitioners, however, suffer from a similar
quandary. On the one hand, they have contracted away their rights
to challenge a permit through the Chapter 120, Florida Statutes,
process. On the other, they instead enter into an arbitration process
without fully knowing what conditions the permit will ultimately
include.
46. Under the 1998 Interlocal Agreement, the Arbitration
Panel must determine under Section 3.13 whether the Joint Application
meets all Applicable Substantive Law. If the Arbitration Panel
does not determine that it does, then TBW can either amend or withdraw
the application. While the Arbitration Panel cannot dictate to
TBW which way to go in the event that any portion of the Joint
Application does not meet Applicable Substantive Law, it at least
can provide explanation to its decision, and in so doing provide
guidance to TBW as to whether the Joint Applications limitations
can be corrected through amendment or whether the Joint Application
is more seriously deficient.
47. The Arbitration Panel is providing a detailed
explanation of its reasons for determining that certain aspects
of the Joint Application do not meet the Applicable Substantive
Law in order to facilitate TBWs decision as to how to respond
to the Arbitration Panels determination, as well as to assist
Petitioners in deciding whether or to what extent they should challenge
an amended application, should TBW decide to amend. Hopefully this
explanation will help, at least to some degree, address the quandaries
of the parties noted by the Arbitration Panel.
48. Set forth in the "Award" section of this arbitration
award are the Arbitration Panels rulings regarding what should
be included in an amended application.
Embankment Stability and Safety
49. TBW must provide reasonable assurance that
the Proposed Reservoir:
(a) Complies with Rule 40D-4.301(1)(b), F.A.C., in that it will not cause adverse
flooding to on-site or off-site property;
(b) Complies with Rule 40D-4.301(1)(i), F.A.C., in that it must be "...capable,
based on generally accepted engineering and scientific principles, of being
effectively performed and of functioning as proposed;"
(c) Complies with Rule 40D-4.302(1)(a), F.A.C., which requires the public interest
balancing of a number of factors including public health, safety and welfare;
(d) Complies with the public interest review, including the public health,
safety and welfare considerations of 33 C.F.R. § 320.4(a) & (k); and
(e) Complies with Section 373.414, Florida Statutes, which requires a determination
that the activity to be permitted is not contrary to the public interest.
50. This Applicable Substantive Law relates to the issue of
embankment stability and safety, and is evaluated in the context of: considering
and balancing public interest criteria, whether the Proposed Reservoir will
cause flooding to off-site or on-site property, and whether it is capable of
functioning and performing as proposed. Competent, substantial evidence based
on detailed site plans and engineering studies, coupled with credible expert
engineering testimony, is a sufficient basis for a finding of reasonable assurance.
Hamilton County Board of County Commissioners v. FDEP, 587 So. 2d 1378 (Fla.
1st DCA 1991). TBW has presented competent and substantial evidence in the
form of site plans, maps, extensive geologic and hydrogeologic studies and
reports, as well as the testimony of credible expert witnesses. Thus, TBW has
adequately addressed all relevant stability issues, including site geology
and foundation soil composition, overall embankment stability, applicable drawdown
criteria, factors of safety, and embankment erosion protection. After evaluating
all of the Arbitration Hearing Evidence, TBW has provided reasonable assurance
that the embankment design for the Proposed Reservoir will result in an embankment
that is stable.
51. In balancing the public interest considerations,
the Panel has also considered a number of other matters that weigh
in favor of determining that there is the requisite reasonable
assurance. First , the arbitration panel has considered the public
interest to be served, that is, the need for water to be supplied
by the Proposed Reservoir. Additionally, the permit would not become
effective (i.e., TBW will not be allowed to fill/operate the Reservoir)
until: (1) a registered professional engineer certifies compliance
in writing, and (2) the FDEP has inspected the system for compliance.
Rule 62-343.110(1)(d), F.A.C. By that time, the project would have
already been inspected periodically by the FDEP during construction,
and would continue to be inspected by the FDEP after operation
commenced, pursuant to Section 373.423, Florida Statutes. If, at
any time, the FDEP finds that work is not being done in accordance
with plans and specifications, immediate compliance can be required.
See Sections 373.423, 373.436 and 373.439, Florida Statutes. Finally,
TBW has committed to an operation and maintenance plan to ensure
that the Proposed Reservoir will be operated and maintained as
designed.
52. Therefore, this Arbitration Panel concludes
from an embankment stability and design standpoint, that TBW has
provided reasonable assurance, based on the Arbitration Hearing
Evidence, that the Proposed Reservoir complies with the Applicable
Substantive Law.
Dam Breach Analysis, Inundation Mapping
and Emergency Action Plan
53. Petitioners contend that the Joint Application
fails to provide reasonable assurance that the public health, safety
and welfare have been adequately protected because, among other reasons,
the Joint Application does not include a dam breach analysis, inundation
mapping, or an adequate EAP. Petitioners conducted their own dam
breach analysis and produced associated inundation maps. The Petitioners dam
breach analysis, however, assumed that a breach will occur without
regard to an analysis of the Proposed Reservoir design, and further
assumed that the breach will occur at specified locations. The Petitioners
conducted no probability analysis as to the likelihood of a breach
occurring at the modeled locations, or at all. Moreover, this Arbitration
Panel has found that, from an emergency planning standpoint, there
was no evidence that the Proposed Reservoir should be redesigned
or moved, or that any roads or bridges in the vicinity required design
changes.
54. Petitioners dam breach analysis modeling,
associated mapping and the modeled results represent only a mathematical
prediction of a "possible " result rather than a probable or realistic
one. While Petitioners modeling may be a useful starting
point for contingency planning purposes, it was found to contain
limitations relating to assumptions and input parameters.
55. TBW has provided reasonable assurance that
off-site flooding and any resulting adverse effects to public health,
safety, or welfare should not reasonably be expected to occur.
TBW chose not to include a dam breach analysis, inundation mapping,
or a finalized EAP as part of the Arbitration Hearing Evidence
in this case. However, the public health, safety and welfare issue
is a rather broad one with little specificity in the Applicable
Substantive Law. In this case, the evidence has shown that the
Wendel Avenue residents are the closest neighbors to the proposed
embankment. A permit applicant is required only to provide reasonable
assurance, not absolute guarantees regarding a proposed facility.
It is common sense and many of the experts in this case testified
that anything is possible. Thus, it is within the realm of possibility
that there could be a breach at the SE corner that would impact
the Wendel Avenue residents. Preparation of an EAP is an appropriate
public interest consideration and necessary to protect the public
health, safety and welfare.
56. TBW has been developing an EAP as evidenced
by the fact that a draft is in the Joint Application, and that
Mr. Gispert reviewed and commented on it. Moreover, considerable
work on a dam breach analysis and inundation mapping has been initiated
by Petitioners. TBW plans to submit inundation mapping and a dam
break analysis to the FDEP as part of the permitting procedure
as soon as its staff can meet again with the FDEP staff and further
clarify the modeling scenarios that FDEP proposed.
57. In the normal course of permitting, some details
of a proposed project can only be developed as the permit process
unfolds and pursuant to the permit conditions even after the permit
is issued. This is especially the case in situations where to provide
the details at an early stage would not serve the purpose of compliance
with the Applicable Substantive Law. The Arbitration Panel has
found that an EAP needs to be timely to be effective and an EAP
done too soon could be outdated by the time the Proposed Reservoir
becomes operational. These types of details are in the nature of
conditions subsequent. Therefore, the Arbitration Panel makes the
following rulings with regard to the issue of a dam breach analysis,
inundation mapping and the EAP:
(a) Based on the weight of the Arbitration Hearing Evidence related to embankment
design and stability, the Proposed Reservoir should reasonably be expected
to function and perform as proposed, not cause on-site or off-site flooding,
not be contrary to the public interest, and not cause adverse impacts to the
public health, safety, or welfare.
(b) The dam breach analyses and inundation mapping may be useful planning tools
for developing an EAP and implementation of an EAP is a necessary public interest
consideration for the Proposed Reservoir not to cause adverse impacts to the
public health, safety and welfare.
(c) To be helpful to emergency planners and persons that may be affected, an
EAP should be completed and implemented prior to placing the Proposed Reservoir
into operation, i.e., prior to storing water.
(d) Applicable Substantive Law does not compel the need for an EAP to be implemented
until sometime before the Proposed Reservoir begins to receive water and does
not require completion of an EAP at this time.
(e) The EAP is an organic document that should be updated as circumstances,
agency contacts and other matters related to emergency planning, the Proposed
Reservoir and vicinity, change.
(f) The design parameters for the EAP proposed in the Joint Application by
TBW comply with the Applicable Substantive Law.
AWARD
Based upon the foregoing Findings of Fact and Conclusions of Law,
the Arbitration Panel issues the following Award:
A. TBW has provided reasonable assurance that the Joint Application meets all
Applicable Substantive Law as to those aspects of the Joint Application that
Petitioners have challenged, except as otherwise provided in this Award.
B. In order for TBW to provide reasonable assurance that the Joint Application
meets all Applicable Substantive Law as to potential adverse impacts associated
with seepage of waters from the Proposed Reservoir into surrounding groundwater
and surface waters, TBW must amend its application in the following manner
and as further explained in the foregoing Findings of Fact and Conclusions
of Law:
(1) TBW shall develop baseline data regarding
the wetlands that may be impacted by the seepage. This baseline
data shall assume the possibility of groundwater push up from leakance
of a foot or more up to 4,000 feet away from the embankment of
the Proposed Reservoir, assuming the water level is at full pool,
unless TBW provides more detailed modeling, beyond that currently
available, that shows the push up distance to be different.
(2) The baseline data shall include a characterization
and quantification of the wetland systems that currently exist
within this area, as well as the hydrologic regime that supports
those systems. The characterization shall include the use of transects
as identified in Section 5.3.1 of Appendix D to the Joint Application,
as well as an identification of groundwater levels and hydroperiods
within the affected wetlands.
(3) The baseline data shall also include information
about wells and septic systems in the Wendel Avenue area that are
within 4,000 feet of the embankment of the Proposed Reservoir,
as to locations and, if available, depths of the wells and septic
tanks.
(4) For those areas in the East Pruitt mitigation
site that are within 4,000 feet of the embankment of the Proposed
Reservoir and are planned to be used as mitigation for impacts
to wetlands from construction of the Proposed Reservoir, TBW shall
develop mitigation plans that are sufficiently detailed as to comply
with the requirements of Section 3.3 of the Basis of Review.
(5) Along with the development of the baseline
data, TBW shall include a monitoring plan containing locations,
devices, sampling frequencies and methodologies necessary to monitor
the baseline conditions established. TBW shall specify how the
monitoring plan will detect seepage, the level of impact at which
detection occurs, and the level of impact considered adverse based
on Applicable Substantive Law.
(6) TBW shall amend its management plan to demonstrate
how it will manage changes to the wetland hydroperiod from normal
baseline, demonstrate the feasibility and effectiveness of such
a plan for maintaining the viability of the water resources outside
the footprint of the Proposed Reservoir (including wetlands and
streams), and integrate the management plan and the monitoring
plan to demonstrate that management can and will be initiated before
adverse impacts occur to the wetlands ecology or to wetlands mitigation
projects proposed to offset direct impacts resulting from construction.
(7) Remedial methods shall be delineated by type,
location, procedure for controlling the effects of remediation,
disposal strategies for water withdrawn to offset elevated levels,
and sources of water for supplementing levels if water level reductions
occur.
(8) The management plan shall also document how
TBW intends to manage the water levels and hydroperiod needed to
maintain the existing wetland system, the types of wells to be
used to maintain those levels, and the general location and depths
of such wells. The management plan shall be integrated with the
plans for mitigation at the East Pruitt mitigation site so that
the East Pruitt mitigation can be successfully established and
maintained. Finally, the management plan shall include monitoring
of water levels, so that the potential for adverse impacts of leakance
on adjacent wetlands and wells and septic tanks of the Wendel Avenue
residents can reasonably be anticipated.
(9) TBW shall commit to having backup contingency
plans in the event that the management plan is unsuccessful in
reaching any of its objectives. The contingency plans need not
be specified at this time other than in very general terms, with
the further understanding that any such contingency plans will
be developed in coordination with the responsible agencies.
C. In addition to requiring the foregoing amendments
to the Joint Application, the Arbitration Panel has found that the
following actions should be performed, at the time specified below,
but do not require an amendment to the Joint Application for reasons
stated in the Findings of Fact and Conclusions of Law:
(1) Water quality monitoring for copper around the perimeter of the
Proposed Reservoir shall be initiated no later than at the time TBW begins
to use copper sulfate as an algaecide in the Proposed Reservoir.
(2) An EAP shall be completed and implemented
no later than when water starts to be stored in the Proposed Reservoir,
and be revised on an annual basis, or sooner if necessary, based
on FEMA guidelines and the FLDWAV Analysis Methodology described
in Appendix A to Attachment L.2 to Appendix L (Emergency Action
Plan Overview) to the Joint Application. In considering FLDWAV
modeling scenarios, the Arbitration Panel encourages TBW to take
into consideration the inundation mapping modeling that has already
been performed by Petitioners experts.
DATED this 15th day of May, 2001.
By_________________________________
CARLOS ALVAREZ
Chair, Arbitration Panel
DANIEL P. FERNANDEZ DANIEL H. THOMPSON
Except as specifically noted, copies sent by electronic mail and U.S. Mail
to the following:
Roger W. Sims, Esquire
Rory C. Ryan, Esquire
Holland & Knight LLP
200 S. Orange Avenue, Suite 2600
P.O. Box 1526
Orlando, FL 32802
Edward B. Helvenston, Esquire
Rick Muratti, Esquire
Assistant County Attorneys
Office of the Hillsborough County Attorney
P.O. Box 1110
Tampa, FL 33601
Frederick T. Reeves, Esquire
Hobby Grey & Reeves
5709 Tidalwave Drive
New Port Richey, FL 34652-3281
Patrick B. Courtney, Esquire
Lansky & Courtney
512 E. Kennedy Blvd.
Tampa, FL 33602
Kristin K. Bennett, Esquire
Richard Tschantz, Esquire
Hillsborough County Environmental Protection Commission
1900 Ninth Avenue East
Tampa, FL 33605
(By electronic mail to Regina Kavanagh for Donald D. Conn)
Donald D. Conn, General Counsel
Tampa Bay Water
2535 Landmark Drive, Suite 211
Clearwater, FL 33761-3930
E. A. "Seth" Mills, Jr., Esquire
Robert L. Olsen, Esquire
Rhea Law, Esquire
Fowler, White, Gillen, Boggs, Villareal and Banker, P.A.
P.O. Box 1438
Tampa, FL 33601-1438
|